Release Schedule
Revision: r2
Activity Log
RC : May 16 → May 23
Sign off: June 6 → June 13
Gliffy Diagram | ||||||||
---|---|---|---|---|---|---|---|---|
|
Activity Log
Date | Rev | Event or Update |
---|---|---|
Initial draft posted | ||
#Agree: TSC agrees to proposed release planning schedule for New Delhi |
Reviewed draft schedule with the TSC. TSC approved the schedule.
Shared draft schedule with PTL meeting. No objections or other feedback.
Uploaded a proposed schedule for New Delhi using the guidelines for scheduling for the new release process (see note for Sept 7, below).
The TSC approved a new release process, following several weeks of discussions and meetings. The new release process greatly simplifies the release process and release schedule, including eliminating milestones. The only events on the schedule for the new process will be Kickoff, Release Candidate (RC), and Sign Off.
The TSC approved a proposal to push M1 out by two weeks to avoid conflicting with the updated London schedule.
Also added D&TF event and updated date for London Sign Off.
Met with ODL to review New Delhi schedule. The draft schedule appears to be a good fit for projected ODL release activities. The plan is to integrate the ODL Argon release.
No updates to the New Delhi draft required.