Practice AreaCheckpointYes/NoEvidencesHow to?
Product ManagementAre all tasks associated with the release been marked as "Done" in Jira?Link to JiraIn progress


Have all findings from previous milestones been addressed?Provide link to JIRA findingsin progressReach 50% Unit test coverage
DevelopmentHave all Defects of priority Highest and High been in status "Done" in Jira?Provide link to JIRA issue (type bug) of priority Highest and High. In progress

Jira
serverONAP JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keySDC-1273

Jira
serverONAP JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keySDC-1249


Are all JIRA issues used as a reference in a commit in status "Done" in Jira?Very often, some JIRA issue remains in status "Todo" in JIRA while the commit they are referenced to is successful.yes

Is there any pending commit related to Highest and High priority issues older than 36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours.Yessdc all repo querey
Are all the Jenkins jobs successfully passed (verify + merge jobs)?Provide link to "Merge job" as evidence in Jenkins project tabyes

https://jenkins.onap.org/view/sdc/

https://jenkins.onap.org/view/sdc-jtosca/

https://jenkins.onap.org/view/sdc-sdc-distribution/

https://jenkins.onap.org/view/sdc-sdc-titan/

https://jenkins.onap.org/view/sdc-sdc-tosca/

https://jenkins.onap.org/view/sdc-sdc-workflow/

docker base is failing at the moment.

not an issue because release versions have been created.

Jira
serverONAP JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keySDC-1222


Has the team delivered all their release artifacts in Nexus Release or Nexus Staging repo?

There should be at least ONE version of each artifacts available in Nexus Release or Nexus Staging repo.

Refer to Independent Versioning and Release Process for procedure

yes

the docker relase job is failing

ONAP Helpdesk #55386

Integration and TestingHave all CSIT Use Cases (created by each project team) passed?Provide link to evidence. As things are moving fast, we want to ensure CSIT are still "green".Yes

https://jenkins.onap.org/view/sdc/job/sdc-master-csit-nightly-testng/233/

https://jenkins.onap.org/view/sdc/job/sdc-master-csit-sanity-testng/596/

https://jenkins.onap.org/view/sdc/job/sdc-master-csit-uiSanity-testng/30/

Is there a Docker images available for each repository?Provide link to evidenceyes
https://nexus3.onap.org/#browse/search=keyword%3Dsdc%20AND%20version%3D1.2-STAGING-latest
Has the project code successfully passed the Daily Build process?Goal is to ensure the latest project commit has not broken the Integration Daily Build N\A


Has the OOM deployment passed?in progressEnsure in Jenkins External Labs all Health Check pass.

latest external deploy did not start the sdc dockers.

based on integration team inputs the sdc starts successfully using heat deployment in windreiver lab sb07.

Has the Heat deployment passed?in progressEnsure in Jenkins External Labs all Health Check pass.

latest external deploy successfully deployed sdc and it started correctly with no intervention.

however it looks like there is a timing issue between when the difrent pods start and the health check is exacuted.

based on integration team inputs the sdc starts successfully using OOM deployment win driver labs sb04.

Documentation

For RC0, for project delivering binaries, has the team populated and validated all the sections of either the Platform Component or SDK template?

Most teams have already created the high level file structures in readthedocs, and populated some actual documentation. However, the remaining sections of the appropriate teamplate must be completed.

Platform: A&AI, APP-C, CLAMP, CLI, DCAE, DMaaP, Holmes, MSB, OOM, Policy, Portal, SDN-C SDC, SO, UseCase UI, VFC, VID

SDKs: AAF, CCSDK, External API Framework, Multi VIM/Cloud, VNFSDK





For RC1, has the team addressed any issue (recorded in JIRA) provided by the Documentation team?

Yes

For RC2, for project delivering binaries, has the team populated and validated all the sections of the Release Notestemplate?




For RC2, has the Documentation Team provided the final approval for your project documentation?