  • Release, Security and Documentation scopes are now tracked via JIRA
  • Adoption to “Do not break the build” principle
  • No Vendor equipment is required for this release
  • No new VNF requirement identified by the project team
  • Jenkins Jobs Failures are monitored and fixed by the project team
  • Health check and regression tests issues are reported by the Integration Team
  • Project Team defines their Sprint content based on TSC prioritization to meet the delivery deadlines
  • Inform TSC about any descope content post-M1 before changing FixVersion


JIRA Template

Note that these Epics and Tasks are cloned into the JIRA project for each individual ONAP project.

Jira
serverONAP JIRA
columnskey,summary,type,created,updated,due,priority,status,resolution,epic name
maximumIssues20
jqlQueryproject = CIMAN AND labels = relman AND issuetype = Epic ORDER BY updated DESC
serverId425b2b0a-557c-3c0c-b515-579789cceedb

...

  • All high/highest priority jira tickets addressed
  • Remaining License scan, security critical issues addressed
  • Update Release note and documentation
  • Docker images “Release” dues 
  • Project specific test plan for El Alto completed
  • Update Risk Register
  • Integration Weather Board complete
  • Review of release notes and documentation
  • Versioning at the project level
  • Check the certification expiry of your application. It should be valid for the next 9 months after RC0.

Sign-off

  • Remaining high/highest priority jira tickets addressed or workaround documented
  • Close/move all open/in-process jiras to a future release
  • Integration "Sign-Off" on Docker images “Release” 
  • Release notes and documentation completed
  • OOM tag release and version in helm chartUpdate Manifest