Sub-components are repositories and are consolidated in a single centralized place. Edit the Release Components name for your project in the centralized page.
Deliverable | repo | Files Structure of repo |
VNF Guidelines: | vnfrqts/guidelines | File per chapter |
VNF Requirements: | vnfrqts/requirements | File per chapter |
VNF Use Cases: | vnfrqts/usecases | File per Use Case |
VNF Test Descriptions: | vnfrqts/testcases | File Per Test Case DscriptionDescription |
VNF EPICs: | vnfrqts/epics | not used in Casablanca Release |
...
Risk identified | Mitigation Plan | Contingency Plan |
---|---|---|
ONAP supporting multiple onboarding formats | work with VNF SDK, VVP and SDC to minimize the risk. | Document the desired direction in the forward looking VNF Guidelines |
Inconsistency between published VNF Requirements and ONAP Platform |
| document discrepancy in release notes |
Resources
Fill out the Resources Committed to the Release centralized page.
Release Milestone
The milestones are defined at the Release Level and all the supporting project agreed to comply with these dates.
Milestone | Deliverable | Date |
---|---|---|
M0 | Intent to Participate | June 14, 2018 |
M1 | Release Plan M1 Checklist | June 28, 2018 |
M2 | M2 Checklist | July 26, 2018 |
M3 M3 | M3 Checklist | August 23, 2018 |
M4 M4Checklist | M4 Checklist | September 20, 2018 |
RC0 RC0 | RC0 Checklist | October 11, 2018 |
RC1 | RC1ChecklistRC1Checklist | October 25, 2018 |
RC2 RC2 | RC2 Checklist | November 8, 2018 |
Signoff Signoff | Signoff Checklist | November 15, 2018 |
...