- Status and Stucks
Current POMBA Dublin Stories (Logging Project) -
Current Code Inspections
- POMBA hourly healthcheck (CD deployment) - http://kibana.onap.info:5601/app/kibana#/dashboard/AWAtvpS63NTXK5mX2kuS
- General Status
- Casablanca (Maintenance)
- POMBA bug in the email chain - 915, 932, 950
Task
LOG-915
Reduce Logstash core limit to 1 from 3 until LOG-LS and AAI-CS perf issue on the same VM is determined
High
In Progress
Not POMBA Bug
LOG-932
pomba-data-router pod does not come up in Casablanca MR
High
Closed
Closed in Dublin or Casablanca? Bug
LOG-950
periodic pomba-pomba-networkdiscoveryctxbuilder pod in CrashLoopBackoff due to timing
Medium
Submitted
Assigned to Jmac, to look at - Note we said we were only fixing absolutely critical issues in Casablanca, are these them?
- Action Yong. Will reply later today
- Dublin
- Tasks to be closed off (just a technicality):
- Stories in progress: All 3 of them will be delivered by Feb-08.
Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-778 Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-763
: For network resource only and should be split into Network Discovery and ND context builder.Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key SDNC-475
- Stories to be formally verified before closure:
Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-768 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-779 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-404
- Stories closed:
Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-765 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-762 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-938 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-937 Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-764
- Bugs to enter:
- Latest security scan results show ~9 medium issues that should be recorded (but aren't severe enough to merit immediate work).
- Bugs entered in last week:
- none
- Bugs in progress:
Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-852 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-916
(high)Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-917
- Bugs to be verified:
Jira showSummary true server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-807
(Verify in OOM fails, assigned back to design)Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-803 Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-808
- Bugs closed off since last meeting:
Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-875 Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-897 Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-961 Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-935
- Casablanca (Maintenance)
- Technical Discussion
- Note OOM changes should be done when manifest changes are done. Should not wait for integration team to do this work for us.
we need to be careful about breaking POMBA when in the middle of incremental updates, where OOM isn't yet done.- Pulling OOM back into the project will fix this. This is currently not planned, and requires resources from OOM project to do this, so defer.
- both master and any MR
Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-950 - Sharon to create task for this for El Alto backlogWe will have to do this for Dublin in two months.
- Create task to track J. Ram Balasubramanian
- Done.
- Docker version update
- Moving from snapshot to proper release is part of workflow.
- If POMBA thinks they will have no more changes, they can do this earlier
This is covered. We can stop tracking this here.
- Note OOM changes should be done when manifest changes are done. Should not wait for integration team to do this work for us.
- Organizing Models and Swaggers between releases
- Basic navigation should take us to current
- It should also be possible to get Casablanca information
- Wiki needs some reorganization
- Consider demo schedules
- J. Ram Balasubramanian will forecast demos as development progresses
Data Dictionary & Network Discovery- Dec 20Done
- L2 Network data - beginning of Feb?
- Set a more specific date in January
- Let's demo with some rules. So probably Feb 14th or 21st.
- If we want validation run on new data, then Feb 21st makes more sense
- Additional enhancement - March 21st
- J. Ram Balasubramanian will forecast demos as development progresses
- Should ping the automation team on POMBA usage
- Chesla to ping Brian.
- Dublin
- Should look at milestones and ensure we are in good shape.
- Feature commitment Jan 17 → pushed one week. Jan 24th. (M1)
- Prudence is supporting Michael for this activity.
https://wiki.onap.org/display/DW/Logging+Dublin+M1+Release+Planning
- Functionality freeze Feb 14
- Not sure if this was impacted by M1 slip .- nope - still the 14th
- API freeze is March 14th.
- Feature commitment Jan 17 → pushed one week. Jan 24th. (M1)
- Should look at milestones and ensure we are in good shape.