  1. June 28, 2017 Workflow review

Chengli Wang and Lingli Deng from China Mobile presented VoLTE use case. They went through the work flow for service design, instantiation, auto healing/auto scaling and termination. 31 Participants joined the meeting and discussion. The meeting recording can be accessed here: https://zoom.us/recording/play/zClGuWa2cFq-g3YEWC-sZ74V9iJaHAx2Iw7ePKuhh1q1ttjSSFXRyoJhYxpmk8bC

...

5. Depend on the interface and capability of SDN local controller, we will decide in the next meeting how modules (MultiVIM, Neutron, SDN local controller, SDN WAN controller, DC-GW) work together to provide VXLAN overlay between data centers via EVPN.


July 20, 2017 DC Gateway Local Controller Interface

During the meeting, we discussed local DC gateway controller sample APIs to manage EVPN VXLAN overlay network between two data centers. 

  1. Explained one option of how DC gateway controller interacts with DC gateway, Neutron and compute node.
  2. Discussed DC gateway controller sample APIs to create L2&L3 EVPN VXLAN overlay network between DCs. Other APIs to support read, update and delete EVPN VXLAN overlay network are also available. SDN-C team agreed that the APIs looked good.   
  3. VIM team and Multi-VIM team also described other options for DC network to support VXLAN overlay. We will have further discussions of those options after R1.

The action items:

  1. Have a table to define the source for the parameters (import route target, export route target, networks, etc.) used in controller APIs. The source can be from vendor or SDC, etc. 
  2. Should make decision on whether L2, L3 or L2&L3 VXLANs are required for R1.   

The slides used in the meeting: volte-overlay-dist.pptx


July 28, 2017 VoLTE Use Case Status Update

We reviewed the following topics during the meeting, and the details are in the attached slides: 

1) The use case current status

2) The blocking issues raised during virtual developer event, see July Virtual Developers Event Blockers

3) The next steps

4) Testing strategy for VoLTE use case. One comment was g-vnfm driver from VFC can be used as base for developing mock vnfm driver.   

The slides used in the meeting: VoLTE Use Case Status Update 07-28-2017.pdf. Recording: Status update and testing strategy 07-28-2017.mp4


August 4, 2017 VoLTE TOSCA Template and Network Service Discussion

We reviewed the following topics and some details are in the attached slides: 

1) Reviewed the latest SDC and SO plans to support VoLTE

2) Looked into VoLTE TOSCA template example from Open-O, with focus on Network Service template

3) Proposed an approach for Virtual Link implementation in WAN scenario

The slides used in the meeting: VoLTE TOSCA Template and Network Service.pdf


August 7, 2017 Discussion of Two Blocking Issues Raised by DCAE Team

Two issues regarding ONAP service url registration and discovery were raised by DCAE, see B26 and B27 on July Virtual Developers Event Blockers

Through the discussion it became clear how the parameters are passed to DCAE when ONAP components are installed by HEAT as VMs. When ONAP components are deployed as containers directly by OOM through Kubernetes, further discussion is needed with OOM team.

Here is the meeting recordings: Meeting with DCAE Team on Two Blocking Issues.mp4


August 15, 2017 VoLTE Draft Test Cases Review

We reviewed the draft of VoLTE Test Cases. Here is the recording: VoLTE Draft Test Cases Review.mp4 


September 6, 2017 A&AI Portal App Demo 

Arul Nambi gave a demo of A&AI portal app. The new portal app visualizes the nodes and connections between nodes. The meeting recording is here: A&AI Portal App Demo.mp4


September 27, 2017 VoLTE Service Creation

David gave a demo of VoLTE Service Creation in Paris F2F conference. VoLTE Service Creation Demo.mp4