- APPC Meeting Minutes
- 6/21/17 - APPC Project Weekly Minutes
- APPC Model Driven Approach - PMiller 6-22-17.mp4
- APPC Meeting Minutes
- 07/06/17 - APPC Restart Overview slides
- APPC Meeting Minutes
- APPC Meeting Minutes
- APPC Meeting Minutes
- APPC Meeting Minutes
- APPC Meeting Minutes
- 08/11/17 - APPC/CDP-PAL/MultVIM - Touch Base 1
- APPC Meeting Minutes
- APPC Meeting Minutes
- APPC Meeting Minutes
- APPC Meeting Minutes
- APPC Meeting Minutes
- APPC Meeting Minutes
- APPC Meeting Minutes
- APPC Meeting Minutes
- 09/20/17 - APPC Project Weekly Minutes
- APPC Meeting Minutes
- APPC Meeting Minutes
- APPC Meeting Minutes
- APPC Meeting Minutes
- APPC Meeting Minutes
- APPC Meeting Minutes
- APPC Meeting Minutes01
- /10/18 - APPC Project Weekly APPC Meeting Minutes
6/19/17 - APPC Project Kick-Off
...
Participants: Randa Maher, Aaron Hay, Patrick Brady, Skip Wonnell, Shubhada Vaze, Takamune Cho, Linda Horn, Veer Rajasekar, Tomasz Kaminski
Notes:
- Review Beijing Milestones again (https://wiki.onap.org/display/DW/Release+Planning#ReleasePlanning-ONAPBeijingReleasePlanning)
- 1/8 - Project Planning closure
- M1 - 1/18 - M1 review
- Materials for M1:
- Release Planning Template:
- Release Planning Checklist: To be filled out by Jan 17
- Materials for M1:
- M2 - Functionality Freeze - 2/12
- no new visible functionality is to be added to the current ONAP release
- Each Project team has defined and documented their Functional Test Cases
- A stable document describing the API is documented and available in wiki.
- M3 - API Freeze - 3/8
- Mark the end of API and Data Model change. API and Data Model are now Frozen
- 50% of Functional Test Case are automated.
- M4 - Code Freeze - 3/29 - 4/5/18
- Mark the end of the Features coding
- 100% of Functional Test Case are automated
- RC0 - Integration - 4/19
- RC1
- RC2
- Release Delivery - 5/24 - Signoff
- Review Current Dev resources
- Patrick Brady (Committer) - Dev/test - 100%
- Skip Wonnell
(Committer) - Dev/test - what %? - Marcus Williams (Committer) % ? awaiting feedback
- Ryan Young - Dev/tes - 100%
- Takamune Cho - Dev/test - 100%
- Atul Shegokar - Dev/test - 50%
- Shubhada Vaze - Dev/test - 70-100%
- Aaron Hay (test/csit/deployment pairwise lab) - 100%
- Hector Anapan-Lavalle (test/deployment documentation) - ?
- Paul Miller (architect) -
- Scott Seabolt (architect/doc support)
- Review Scope
- Remove references and use of openecomp and replace with onap APPC-13 - In progress
- Action: Need to follow-up with Michael Lando on his concern….
- Platform Maturity (or S3P)
- Performance - cannot commit anything at this point; too many questions and ambigiuty on what needs to be done. Awaiting input from Benchmarking committee
- Stability - 1 - 72 hours soak test on component level.
- Resiliency - this item needs clarification - is 1 for local or geo-red manual failover? Regardless, we will align with CCSDK/SNDC since we get our ODL & DB dockers from them. We will work with SDNC team.
- Security = 1 - CII Passing badge + 50% Test Coverag
- Scalability -1 - APPC uses ODL distribution from CCSDK project. Scaling is a function of ODL capabilities - adding nodes to an existing cluster or adding a new cluster
- Manageability - 1- APPC supports EELF already.
- Usability - 1
- Remove references and use of openecomp and replace with onap APPC-13 - In progress
...
- CDT Tool - an APP-C Design Tool enabling VNF owners to create templates and other artifacts for APP-C Configure command (used to apply a post-instantiation configuration) as well as other life cycle commands. Missing piece of functionality for Test Action
- Documentation updates for Beijing
- On-going requirements discussion during Beijing to fleshout requirement for vDNS scaling use case for Casablanca… Pam/Brian/Paul/etc..
...
- .
...
- .
...
- 1/8 - Project Planning closure
- M1 - 1/18 - M1 review
Materials for M1:
- Release Planning Template:
• To be filled out by Jan 8. 10 days for review prior to TSC approval on Jan 18.
• Focus on scope and project dependencies
- Release Planning Checklist: To be filled out by Jan 17
- M2 - Functionality Freeze - 2/12
- no new visible functionality is to be added to the current ONAP release
- Each Project team has defined and documented their Functional Test Cases
- A stable document describing the API is documented and available in wiki.
- M3 - API Freeze - 3/8
- Mark the end of API and Data Model change. API and Data Model are now Frozen
- 50% of Functional Test Case are automated.
- M4 - Code Freeze - 3/29 - 4/5/18
- Mark the end of the Features coding
- 100% of Functional Test Case are automated
- RC0 - Integration - 4/19
- RC1
- RC2
- Release Delivery - 5/24 - Signoff
...