These requirements have been prioritized by the TSC to realistically fit within the Dublin Release Timeline.
This is not yet the Dublin Release scope. Release Scope will be The Release Scope was finalized during the M1 Release Planning .
Projects intended to participate within Dublin release are posted in wiki.
New projects proposal are posted here. These projects need to be reviewed and approved by TSC.
Some of the Use Cases, Functional and non functional requirements are carried over from previous releases as they required multiple releases to be implementedmilestone at the TSC on January 31st.
The Requirements extracted from SP lists of priorities for Dublin are covered either by the Use Case, the functional requirements, the non functional requirement or within a project scope of work.
- Use Cases
- Functional Requirements
- Non Functional Requirements
TSC Prioritization (Ranking)
- RANK #0 – Special GO - fully covered by involved companies
- RANK #1 – GO “Must Have”
- RANK #2 - GO “Continuity of previous releases”
- RANK #3 – GO if PTLs are OK since the impacted applications are less “stretched” i.e. CLAMP, Policy, DCAE etc.
- RANK #4 – NO GO – Mostly new requirements/features/projects
Use Cases
M1 Scorecard:
- Green: Use Case will be fully implemented and tested
- Yellow: Use Case will be partially implemented. It is possible to identify capabilities for this use case that can be tested (phasing approach).
- Red: Use Case can not be partially delivered, min. requirements can not be met in order to define a testing strategy.
Priority | M1 Scorecard | TSC M1 Approval | Use Case | Owner | Projects or functional requirements impacted for Dublin | Link(s) to HLD/LLD if any | Dependency (from/to) another project(s) | T-Shirt Size | Project's Impact: Test Only (TO), Code (C) | Committed (C)/ Partially Committed (P) or not (N) per impacted project | If Partially or not Committed, what are gaps/ project (people/FTEs; HLD/LLD; etc) | Company Engagement | Notes | M4 Status | ||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1-regression 3-enhancements |
| Y | vFW | Policy/(APPC) HPA | vFirewall Use Case Upgrade | XS | All: Test Only except Policy APPC(TO) | Policy: Committed | Policy: Committed | AT&T | HPA Testing confirmed by INTEL | |||||||||
1 |
| Y | vDNS | Integration Team | HPA | All: Test Only | N/A - part of regression tests | N/A - part of regression tests | HPA Testing confirmed by INTEL | |||||||||||
1 |
| Y | vCPE (Heat) | Integration Team | HPA | All: Test Only | N/A - part of regression tests | N/A - part of regression tests | HPA Testing confirmed by INTEL | |||||||||||
2 |
#Action Davide/Lin to review and provide final feedback | Yes with Condition: Need final inputs from Davide/Lin | CCVPN Use Case (Dublin) High priority:1, SD-WAN Multi-site to Multi-site service creation; 2, Service change: add or delete a site;3, close loop intelligent surveillance | SDC, SO, SDN-C,OOF,ExternalAPI, UUI, ESR,Modeling,MultiVIM/Cloud, VFC, Modeling, DCAE, Policy, Holmes, Consistent ID of a cloud region | CCVPN Use Case (Dublin) | AAI: M | AAI: TO DCAE: TO ExtAPI: TO Multi-VIM: Test support Holmes: C | SDC: Partially committed based on Chinamobile/ZTE/Vodafone contribution SO: Committed based on the contributions from CMCC, ZTE and VDF for the main flows SDN-C/CCSDK : Committed based on contributions from Huawei and ZTE VF-C: Committed Modeling: Committed Usecase-UI: Committed Holmes: Committed based on Huawei and ZTE contribution Multi-VIM/Cloud: Committed based on VMware contribution Policy: Committed base on Huawei contribution ExtAPI: Committed as long as a serviceOrder is created, either for service creation or modification with full service characteristics and values. ExtAPI can not read service characteristic and service state from AAI which does not expose those informations. | SDC: not enough resources | Dev/Test provided by Chinamobile, Vodafone, Huawei, ZTE, WindRiver, VMWare, Intel, Lenovo, ChinaTelecom, Fujitsu | ||||||||||
2 |
| Y | 5G: PNF Pre-onboarding Onboarding | SDC, VNFSDK, VNFRqmt (Docs) | 5G - PNF Pre-Onboarding & Onboarding | BBS | SDC: C VNFSDK: C | SDC: Committed based on Nokia/Ericsson contribution VNFSDK: Committed | AT&T, Huawei, Ericsson, Nokia | PNF POB/OB U/C is now in development, requirements and architecture stage with high corporate commitment. | ||||||||||
2 |
| Y | 5G: Bulk PM | DCAE, DMaaP, VNFRqmt | 5G - Bulk PM (Casablanca carry-over items) | 5G: PM Dictionary | DCAE: C DMaaP: C | DCAE: Committed based on Ericsson contribution DMaaP: Committed | AT&T, Ericsson, Nokia | Bulk PM is in development with high corporate commitment. | ||||||||||
2 |
| Y | 5G: Config w/ NetConf | Oskar Malm | SDC, (VID), SO, SDNC, CCSDK, VNFRQTS | 5G - Configuration with NETCONF | 5G: PNF PnP e2e automation | SDC: C (VID) SO: C SDNC: C CCSDK: C | SDNC: NETCONF/TLS support in controller committed from Ericsson Additional development (SDC, SO, CCSDK) for PNF configuration UC is coordinated with CDS / e2e automation. See separate row for details. PNF configuration testing: Ericsson SO: (not a separate initiative uses E2E automation) assign/config building block | AT&T, Ericsson | NetConf is in development with high corporate commitment | |||||||||
2 |
| Y | 5G: FM Meta PM Dictionary | SDC, VNFRqmt, VES Specification (Done) | 5G - FM Meta Data / 5G - PM Dictionary | 5G: Bulk PM 5G: PNF OB | SDC: C | SDC: Commit | AT&T, Ericsson, Nokia | FMPM Dictionary is in development with high corporate commitment | ||||||||||
2 |
| Yes with Condition: Need to confirm testing resource to Yang Xu and what the Integration Team will be able to test | 5G: OOF & PCI | SDC, APP-C, DCAE, OOF, Policy, VNFRqmt | 5G - OOF and PCI (Casablanca carry-over items) | 5G: PNF OB Control Loop U/C | SDC: C SDN-C: C DCAE: C OOF: C Policy: C | SDC: NEED REVIEW SDN-C: Commit DCAE: Committed based on Wipro contribution OOF: Commit Policy: Committed based on Wipro contribution | AT&T, Wipro, Tech Mahindra | OOF/PCI Enhancements is in development with high corporate commitment Dublin Release RequirementsScope I added policy because my understanding from Dublin Release RequirementsScope there are additions for 5G - OOF and PCI | ||||||||||
2 |
| Yes with Condition: Need to confirm testing resource to Yang Xu and what the Integration Team will be able to test | 5G: PNF Plug and Play & PNF Re-registration | Benjamin Cheung | SDC, Portal, VID, SO, A&AI, SDN-C, DCAE | 5G - PNF Plug and Play (Casablanca carry-over items) | BBS | SDC: C Port: C VID: C SO: C A&AI: C SDN-C: C DCAE: C AAF: C | Portal: Commit VID: Commit SO: Committed based on the contributions from Nokia (confirmed) A&AI: Commit CCSDK/SDN-C : Committed to Tosca ingest changes DCAE: Committed based on the contributions from Nokia AAF: Commit | AAI: schema / model changes. (Jan 30 James Forsyth has ok'ed A&AI commitment) PORTAL: Targets only the top menu integration required for 5G use case functions from VID and SDC/AAI VID: A&AI schema alignment (agreed) | AT&T, Huawei, Ericsson, Nokia | PNF PNP Enhancements is in development with high corporate commitment | ||||||||
2 |
| Y | 5G: Network Slicing | Borislav Glozman | SDC, Modeling Sub-committee | 5G - Slicing | SDC: C Model: TO | SDC: Commit Model: Commit | AT&T, Amdocs, Ericsson | Network Slicing has only modeling work that is being done in R4. | ||||||||||
0 |
| #action (Chaker): Add a risk concerning dependenecy with 5G Use Cases: Dublin Risks | BBS | David Perez Caparros | DCAE, ExternalAPI, Modeling, SDNC, SO | BBS Broadband Service Use Case (Dublin) | PRH - 5G Use Case | AAI: DCAE: C ExtAPI: C SDC: TO SO (using 5G use case PNF discovery and re-registration): TO Policy: TO CLAMP: TO SDNC: C Modeling: design | DCAE: Committed based on contribution from Huawei, TechM and Nokia ExternalAPI: Committed SO: 5G PNF Committed based on the contributions from Nokia /Huawei SDNC: Committed based on contributions from BBS team Modeling: contributions from Swisscom/Huawei/Nokia | AAI: assuming schema/model changes only contributed by community. Also depends on AAI modelling SME availability | Nokia, Swisscom, Huawei, |
...
- XS - <4 Man/Weeks;
- S - ~6 Man/Weeks;
- M - ~8 Man/Weeks;
- L - ~12 Man/Weeks;
- XL - > 12 Man/Weeks.
Functional Requirements
M1 Scorecard:
- Green: The functional requirement will be fully implemented and tested
- Yellow: The functional requirement will be partially implemented. It is possible to identify capabilities for this functional requirement that can be tested (phasing approach).
- Red: The functional requirement can not be partially delivered, min. requirements can not be met in order to define a testing strategy
...
- XS - <4 Man/Weeks;
- S - ~6 Man/Weeks;
- M - ~8 Man/Weeks;
- L - ~12 Man/Weeks;
- XL - > 12 Man/Weeks.
Non-Functional Requirements
M1 Scorecard:
- Green: The non-functional requirement will be fully implemented and tested
- Yellow: The non-functional requirement will be partially implemented. It is possible to identify capabilities for this non-functional requirement can be tested (phasing approach).
- Red: The non-functional requirement can not be partially delivered, min. requirements can not be met in order to define a testing strategy
...
- XS - <4 Man/Weeks;
- S - ~6 Man/Weeks;
- M - ~8 Man/Weeks;
- L - ~12 Man/Weeks;
- XL - > 12 Man/Weeks.
Dublin POC / Experimentation
POC Definition - (In Progress)
...