DescriptionComments / Follow-up
1

Simplify documentation tracking table


2

Track repositories not documents in the document tracking table


3Create separation between completion of code reviews and container delivery by adding another milestone
4Reconsider time between RCs.  One week seems too tight.
5Reconsider RCs altogether.  What do they contribute? Are they necessary? (Kenny)
6Better tracking of OOM / integration status.   Gerrit filter that Krzysztof created was helpful.
7xtesting dockers (tests) and xtesting-onap (test launchers) should have been frozen before RC0..so next time we have to think to that..Integration shall guarantee a stable testing baseline to OOM to gate confortably. (Morgan https://lists.onap.org/g/onap-tsc/message/7653)