Date

Attendees

  • Ramesh Jeyaraman, Bobby Mander, Tarun, Jorge, Charles, Kevin, Saryu, Ritu, Drew, Joseph, Ali and Daniel.

Goals

Discussion items

TimeItemWhoNotes
Joseph

Story 103 : Reached out to Chenfei to understand and where to put the code and to understand the ONAP code

Will be continuing the development today

   Tarun

Story 154 : Will be submitting the fix today

Story 88 : Will be working on today 

   Ali

Story 102 : VM set up completed.

                 : Will be continuing the operation manager template and testing. Almost completed  

  Charles Story 101 : Made the required code changes and was doing testing. Will be focussing today to complete. 
  Temoc 

Story 158 : Finished merging the changes and testing

Story 116 : Started working on and need to test to make sure dint break anything. 

  Drew 

Story 108 : Pushed some code for integrated monitor project.   

                : Manually close the SONAR issues for integrated audit and put some comments, will be completed today. 

   DanielStory 104 : continue working on app-c changes and junit (and make sure it's working fine) 
  Kevin 

Story 156 : Wroked on DB stuff and tried testting. Trying to get build

           : Kevin and Jorge will be discussing today 

  Jorge 

Story 66 : Work in progress

Story 145 : Completed the testing what Tarun changes 

  Ritu Story 57 : Implemented the model code and working on Junit 
  Saryu Story 137 : Reached out to Bobby's team and Pam for feedback. Work is in progress 

Action items

  •