Please find below the Minutes of Meetings and recording for the SECCOM meeting that was held on 19th of September 2023.

Jira No
SummaryDescriptionStatusSolution

Oparent

Update from 2023-08-21 PTL meeting

-CPS (Toine Siebelink): will test building CPS without oparent/pom.xml (results 2023-10-01)

-Integration (Marek Szwałkiewicz): will perform a test build with the profiles commented out

2023-08-15 SECCOM notes

-Only 2 PTLs responded to Amy’s e-mail

-No objections on Oparent retirement, we have no volunteer to maintain it up to date

-pom.xml contains more than cross project common package dependencies

2023-09-05 SECCOM notes

-Pawel to contact Marek Szwałkiewicz 

-Toine Siebelink will provide feedback in early October

-decision on path forward - potentially remove package info - deferred to October


Recommendation:

-retain oparent/pom.xml

-Make Andreas Geissler a committer and ask the integration or OOM team to update the file per release

-Proposal:

  • Option 1 (short term): ask the integration or OOM team to update the file per release
  • Option 2 (long term): split into multiple pieces that could be independently maintained: dependencies, build directives, profiles

-Byung will discuss with Andreas and OOM team and report at 8/22 SECCOM (pushed to 8/29 SECCOM meeting)

-Amy will contact Liam Fallon  and Pam for history


AAF Certificate Expiration

AAF-1217 - Getting issue details... STATUS

Review work around proposed by Andreas Geissler - deferred until Andreas Geissler returns from holiday




Container Signing

Review next steps:

-select signing software (SECCOM + LFIT)

-perform POC with friendly projects (ONAP)

-integrate into build process (LFIT)




No PTL for AAI, DCAE, OOF

-Andreas Geissler and Thomas Kulik made committers

-They will do the work necessary for the projects to participate in the release

-TSC approved streamlining process (7 September)

-SECCOM will create package upgrade recommendations

-TSC will recruit resources to perform upgrades for AAI, DCAE, OOF


-Byung will discuss with Andreas and Thomas to coordinate release tasks such as backlog prioritization

-Muddasar: someone needs to take backlog management role

-Muddasar: no mandated best practice to manage technical debt; call for a statement about code quality – all code will be secure

-Muddasar & Amy: bring mandate for code quality to LFN TAC 2023/8/16


ONAP Streamlining

-TSC approved streamlining (7 September)

-Prioritization of vulnerability fixes (see above)

-Prioritization of security enhancements

-Proposal: ONAP projects work with latest version of common components such as Istio, KeyCloak, Kafka

ONAP Streamlining - The Process

Deck shared with TSC: ONAP - Streamlining the process Report-2023-8-3-v2.pptx (live.com)




TSC meeting (September 7th)





LFN-TAC (September 13th)

Any SECCOM recommendations for the TAC




NEXT SECCOM MEETING CALL WILL BE HELD ON ? of September 2023. 