Date

Attendees

Goals

Discussion items

TimeItemWhoNotes

Review status of work items
  • Robot 80% done
    • Dmitry will contact the Integration team to make them aware of the contributions he is planning to bring to support multi-platform.
  • SO 100% done
  • Portal 100% done
  • AAI is work in progress
  • VID 100% done
  • SDNC 100% done
  Use of Alpine 
  •  The use of Alpine was discussed at the TSC meeting.
  • Alpine continues to be the recommended base image.

Collaboration

Khemendra requested assistance from the team to get started with some images.

Sylvain offered to collaborate with Khemendra

  • Action items