January

1/3 TSC Call

  • TSC agrees to defer any VNF Certification discussion to the VNFRQTS Project.


1/10 TSC Call

  • TSC only approves the CDI projet as POC for the Dublin Release, under the Multicloud project umbrella
  • TSC approves the Committer promotion (AAF): Sai Gandham


1/16

1/17 TSC Call

  • TSC approves the proposed M1 Security milestone checklist as presented by Amy Zwarico. oParent checklist is informational for the Dublin release.
  • TSC approves DataLake  projet as POC only for the Dublin Release under DCAE project umbrella


1/24 TSC Call


1/29


1/31 TSC Call

  • The Casablanca Maintenance Release has been signed-off on 1/31.
  • TSC approves the Dublin Release Plan (M1) for all the projects. Documentation/Integration are conditionally passed.
  • TSC approves v207 of the Dublin Release Requirements GREEN M1 scorecard items and conditional passed on YELLOW items. RED items will be descoped or move to POC depending on feedback collected on 1/31

February

2/4


2/13


2/21 TSC Call

  • TSC did not approve M2/M3 Modeling Checklist add-ons for the Dublin Release. Follow-up discussions with PTLs are required to consider them as part of El-alto release. Suggestion is to prototype these checklists with few projects.
  • Mariusz Wagner committer’s promotion has been approved by the TSC.


2/28 TSC Call

  • Dublin Functionality Freeze (M2) has been approved by the TSC
  • Integration Checklist has been approved by the TSC
  • Multi-VIM/Multi-Cloud Project Scope change has been approved by the Architecture subcommittee - https://lists.onap.org/g/onap-tsc-vote/message/819