This centralized page, for all Guilin projects, is aimed at identifying the risks as they are foreseen within the release life cycle.
A Risk that materialized becomes an Issue.
Status:
- Identified: a risk that has been identified, but has not yet been analyzed / assessed yet
- Assessed: an identified risk which currently has no risk response plan
- Planned: an identified risk with a risk response plan
- In-Process: a risk where the risk response is being executed
- Closed: a risk that occurred and is transferred to an issue or the risk was solved/avoided
- Not occurred: a risk that was identified but that did not occur
- Rejected: created and kept for tracking purposes but considered not to be used yet
Risk ID | Project Team or person identifying the risk | Identification Date | Risk (Description and potential impact) | Team or component impacted by the risk | Mitigation Plan (Action to prevent the risk to materialize) | Contingency Plan - Response Plan (Action in case of the risk materialized) | Probability of occurrence (probability of the risk materialized) High/Medium/Low | Impact High/Medium/Low | Status |
---|---|---|---|---|---|---|---|---|---|
1 | ESR | July 1st 2020 | The REQ-341 has dependency on ESR for updating the K8s cluster information. | REQ-341 | To have the freinds from Aarna network to help us in this functionality. | In case ESR does not make it to Guilin, we will use the postman for updating the AAi with the detais | High | Med | In progress. |
2 | SDC | July 6th 2020 | The REQ-349 - Coverage of 55% | SDC | Minimize impact of changes to limit breakage of coverage metrics | will request an exception for Guilin | Low | Low | Current metrics are at 54.8%, some sonar metrics do not show up on main page but are visible in details. In Progress for improvments |
3 | SDC | July 6th 2020 | REQ 351 - Migration to Java 11 | SDC | Try to get commitments from more companies to help on finishing the migration | will request an exception for Guilin | Medium | Low | Migration to Java 11 is well under way on main SDC project, still the complexity of project implies that there are several unknowns in completing this change |