M1

Charts

Project Status
Closed T:
Active and Available Inventory 11 11
Application Authorization Framework 1 1
Clamp 11 11
Command Line Interface 11 11
Common Controller SDK 11 11
Data Collection, Analytics, and Events 11 11
Data Movement as a Platform 11 11
Documentation 6 6
External API Framework 11 11
Holmes 11 11
Integration 6 6
Microservices Bus 11 11
Modeling 11 11
Multicloud 11 11
Network Controller 11 11
ONAP Operations Manager 6 6
Optimization Framework 11 11
Policy Framework 11 11
Portal 11 11
Service Design and Creation 11 11
Service Orchestrator 11 11
Use Case UI 11 11
VNF Requirements 6 6
VNF Validation Program 11 11
Virtual Function Controller 11 11
Virtual Infrastructure Deployment 11 11
Vnfsdk 11 11
Total Unique Issues: 267 267
Showing 27 of 27 statistics.
View in Jira
Total: 267 . Chart by: Status

M1 Feedback to Projects (7/15) -  98% Completion

Congratulations to AAI, CLAMP, CCSDK, DCAE, DMaaP, DOC, ExternalAPI, Holmes, Integration, Modeling, Mutli-Cloud, SDNC, OOM, OOF, POLICY, PORTAL, SDC, SO, UUI, VNFREQS, VVP, VFC, VID

June 19 - M1 release management issues published

July 9 - APPC, MUSIC and Logging/Pomba, ESR, AAF are no more part of any ONAP release. These are moving under maintenance

July 15 - The following projects will need to follow the Exception process if the remaining activities are not finalised prior the next TSC call (7/16)

  • CLI - Missing information about TSC MUST HAVE Commitment and no risk has been opened
  • MSB - additional updates are required - project life cycle review / waiting for confirmation on 1 TSC MUST HAVE
  • VNFSDK -Missing information about TSC MUST HAVE Commitment and no risk has been opened
  •  