Agenda:

  1. ONAP project news:
    • RocketChat replaced by Slack (onapproject.slack.com)
  2. Guilin Maintenance Release status:
    • For CCSDK/SDNC, Guilin maintenance release contains fixes for transport slicing use case:
    • Release builds created for CCSDK and SDNC, and helm charts have been updated. 
    • Only remaining item is certificate refresh for cds-ui
      • OOM has a pending change to generate cert using init container.  However, need to confirm that certificate is being installed properly.
  3. Honolulu Release status
    • CCSDK and SDNC were both approved as passed M2 (Spec Freeze) milestone at special TSC meeting 1/25.  Release planning templates :
    • ODL Aluminum port complete
      • Currently, using Aluminum SR1
      • SR2 is available, but has a  security vulnerability in restconf project that will be addressed in SR3
      • SR3 should be available later this month, per OpenDaylight community.  When available, we'll want to upgrade in order to pick up security vulnerability fix.
    • Next project milestone is M3 - Feature Freeze:
      • TSC vote scheduled for  
        • M3 criteria includes that all release builds must be complete and helm chart changes must be submitted to OOM to deliver released dockers
          • Note: original plan assumed that helm chart changes needed to be MERGED by M3.  However, all that is required is that changes be SUBMITTED by M3. 
        • To allow time for code reviews, release builds and OOM review, final code reviews for CCSDK and SDNC Honolulu should be submitted no later than
          • Note: this is a week later than our original plan, which allocated about a week for helm chart changes to be merged before M3.  Since that is no longer a requirement, we were able to relax our date for final code submissions.
  4. Open Discussion