Name
Milestone or Requirements Exception?Milestone

Project or Requirement Name and JIRA

SO

Milestones affected

M3, RCX

Projects affected

so-cnf-adapter

so-nssmf-adapter
so-oof-adapter

so-vfc-adapter

Background description

SO project has refactored its existing code for better usability and maintainability. The refactored code is found not meeting the code coverage goals and is being worked upon.

Its targeted to meet the goals by the RC0.

Schedule impact

This does not break SO functionality so we believe this has no impact on schedule

Recovery planThis is being worked upon and is targeted to be met by RC0.
Milestone schedule changeNo schedule change, move this to next milestone.
Risk

SO code coverage meeting the goals by the M3.

StatusClosed
DecisionApproved

2 Comments

  1. Thank you for the information submitted.

  2. Seshu Kumar Mudiganti A milestone exception implies a milestone schedule change, so the statement is contradictory. Simply say that the task will be met by RC0.