The integration testing was done in Winlab at Rutgers University.

Important Note: All Regression flows (=>test cases) which have no relevance/interaction to the enhancements done in Guilin release have been deferred from the official Integration Testing scope for Guilin. They may be considered for automation in H-release.  We may test some of the scenarios for a formal use case demo after Guilin release, but it has no bearing on Guilin Integration Test completion.

S. No.DescriptionInvolved componentsStatusRemarks
1Successful Control Loop trigger for PCI collision/confusion (Regression Test)SON-Handler MS, VES, OOF, Policy, SDN-R, RAN-Sim, Config DB

DEFERRED

Regression test, not critical for Guilin. Testing will continue beyond Guilin for a demo.

Note: Actual testing is in progress, but has no impact for Guilin scope.

2Successful Control Loop trigger for ANR update based on PM data (Regression Test)SON-Handler MS, VES, OOF, Policy, SDN-R, RAN-Sim, Config DB

DEFERRED

Guilin enhancements don't have any interaction with this functionality. Testing will be done completion of Guilin integration test for a demo.

Note: Actual testing is in progress, but has no impact for Guilin scope.

3

SON-Handler MS and SDN-R to include the relevant fields in the control loop request/response messages for Policy to correlate the request and the response

(Regression Test)

SON-Handler MS, Policy, SDN-R, RAN-Sim

DEFERRED

Guilin enhancements don't have any interaction with this functionality. Testing will be done completion of Guilin integration test for a demo.
4

After execution of the Control Loop (CL) and getting (N)ACK from SDN-R, Policy to successfully send back the result of the CL execution (success or failure, with relevant details) to SON-Handler MS In DCAE

(Regression Test)

SON-Handler MS, Policy, SDN-R, RAN-Sim


DEFERRED

Regression test, Guilin enhancements don't have any interaction with this functionality. So it will be tested with the complete flow, after completion of Guilin integration test
5Successful storage of PM data reported by RAN-Sim onto Mongo DBRAN-Sim, DFC, VES Collector, Mongo DB

COMPLETED

Completed by storing it manually. Fully automated flow will depend on Data Lake Feeder MS, which will be considered for Honolulu (no impact to this use case).
6Define the required sql templates in DES MS that are needed for fetching PM data by OOFDES MS

COMPLETED


7When triggered for PCI optimization, OOF (OSDF) to fetch the required PM data from datalake (Mongo DB) using the DES MS APIOOF, SON-Handler MS, DES MS, Mongo DB

COMPLETED


8When triggered for PCI optimization, OOF (OSDF) to employ (offline trained) ML model to update the list of cells whose PCI values should be fixed during PCI optimizationOOF, SON-Handler MS

COMPLETED


9End-to-end flow for PCI optimization involving MLSON-Handler MS, VES, OOF, Policy, SDN-R, RAN-Sim, Config DB

DEFERRED

Major part should be covered by previous test cases 1, 4-8. This is just an e2e test, and will be done for the e2e demo after Guilin release.


  • No labels