Agenda:

  1. Review status on items assigned to dev team
  2. Go over JIRA list assigned for Beijing release
  3. Discuss M1 planning and check list for Beijing release

Attendees:

Giri, Hari, Vikram, Wei-Ting LoLeimeng ShiSunder Tattavarada, BINDU ELISETTY, HIMA (hbindu@research.att.com),

Farhan Mir, Chris Lott

Discussion Items:

  1. vm11 test environment to check the bugs and to perform testing - Sunder/Leimeng
  2. AAF integration with SDC - help Micheal Lando - Sunder/Leimeng
  3. Add Hari, Vikram, and Sireesh to resource list - Leimeng/Manoop
  4. Who is the replacement for testing lead? - Leimeng to followup - Done
  5. Session to be scheduled to plan for the JUnit and Robot tests for Beijing - Sireesh
  6. Portal-151 - followup with usecaseui and schedule a session to review the architecture - Leimeng - Done - scheduled at 4:30PM EST today.
  7. Portal-182 - CLI integration help - Leimeng to setup a working session - Sunder Tattavarada/user-67d6f - Start working on Jan 31st 
  8. Portal-155 - security issues scan - Nexus IQ and Coverity scans
    1. Need Access on Nexus IQ - Farhan/Sunder
    2. Coverity scan followup with Stephen.terrill@ericsson.com - Farhan
  9. Plan to release SDK 2.1.0 version and then communicate to partners to update their poms - Sunder/Leimeng - ETA 1/19.
  10. Extend Portal-119 to split DB for Portal and SDK - Robert - design session pending and ETA on dev tasks. 
  11. Sent grep scan on "master_dev" branch to check if "ecomp" appears in Portal - done - Hima will be cleaning up - ETA 1/10.
    1. ECOMP keyword in license text and java class names - followup with Catherine - Manoop ETA 1/17 
  12. SDK will be next to scan - Lorraine - ETA 1/11 - done
  13. Split Portal-19 to Hima and Robert (based on Lorraine's scan output)  - create tasks based on the scan 
    1. Robert to analyze the font "Omnes-ECOMP-W02".
    2. Analyze backend changes - Hima. 
  14. JUnit /Sonar coverage to 50% on SDK and Portal. 
    1. SDK - JUnit test coverage from 4% to 50% - Hima (pending code review and push to gerrit) - Code pushed to gerrit -  PORTAL-161 - Getting issue details... STATUS
    2. Portal - target 30% to 50% - Giri (to coordinate with Hima to find the right code modules) - PORTAL-136 - Getting issue details... STATUS
  15. Discussed remaining JIRA items in great details
  16. M1 due on 1/18/2018 (same template as Amsterdam) - Manoop/Leimeng - Done
    1. Portal Platform M1 Release Planning (Beijing Release)
    2. Portal Platform Deliverables for Planning Milestone Checklist (Beijing Release)
  17. Check with IBM team members - Manoop/Abbas/Sunder - Done
  18. Beijing Release Planning:
    1. M0 - dev kick-off, Nov 16
    2. M1 - planning Jan 16
    3. M2 -  functionality freeze Feb 15
    4. M3 - API freeze Mar 1
    5. M4 - code freeze Apr 5