Agenda:
- Check readiness of new CSIT team (Sireesh) on Robot test plan - Portal R2 Beijing Functional Test Cases
- Portal JUnit code coverage 50% target (Hari team)
- Review status on items assigned to dev team
- Go over JIRA list assigned for Beijing release
Attendees:
Sireesh, Girish, Lorraine, Saravanan
Discussion Items:
1.Sireesh started setting up local environment for robot test and reviewing test cases from previous release.
will contact Leimeng to know new features;Hima will help setup the Portal in local testers machine.set up new test casesfound some bugs, to work out with the development teamenvironment set up; scheduled call on this for this afternoon- For PORTAL-173 : 24 test cases from before, added 12 more , will check in test case scripts this week into gerrit
- JIRA ticket is in progress state
2.vm11 test environment to check the bugs and to perform testing - Sunder/Leimeng discovered issue where new function code introduced, but not in DML script. - Lorraine will check
new JIRA ticket - PORTAL-209 was opened to replace Portal-175. - in submitted state
3. AAF integration with SDC - help Micheal Lando - Sunder/Leimeng Leimeng will send document to partners (check with Sunder too) ASDC descoped AAF integration
4. Portal-182 - CLI integration help - Leimeng to setup a working session - Sunder Tattavarada/user-67d6f
- Start working on Jan 31st – Leimeng will organize a call with Sunder/CLI team on Wed 9:00am (Sunder could not join the meeting, when is the next meeting?)
- Another working call was made and Making progress - check with Sunder
- this ticket is in reopened state
5. Portal-155 - security issues scan - Nexus IQ and Coverity scans
Need Access on Nexus IQ - Farhan/SCoverity scan followup with Stephen.terrill@ericsson.com - Farhanmany user stories created regarding this big item, pending to assign to developer. (assigned to Sudeep)
6. Security issues status from CLM (Nexus IQ) - Sudeep - this is Portal-155
- pull request made, fixed in portal; but not SDK, new pull request for SDK will be made for what is working
- ETA today for pull request - SDK
- merged in portal/sdk - done
- sdk onap issue working
- this ticket is in open state
7. Plan to release SDK 2.1.0 version and then communicate to partners to update their poms - Sunder/Leimeng - ETA 1/19. ==> update ETA to 1/25 - Sunder need help to find
Sunder emailed to LF team - however, LF team asked for latest build reference as the last build is 2 weeks old.completed SDK 2.1.0 released
8. Extend Portal-119 to split DB for Portal and SDK - Robert - design session pending and ETA on dev tasks. - Robert working on it now
- Robert is using VM3 for this effort. → 70% done by Robert
- Update the deployment scripts with docker image name changes -
- demo repo (heat templates);
- integration repo (CSIT test deployment scripts);
- OOM deployment;
- JIRA ticket is in progress state
9. Sent grep scan on "master_dev" branch to check if "ecomp" appears in Portal - done - Hima will be cleaning up - ETA 1/10.
- ECOMP keyword in license text - followup with Catherine - Manoop ETA 2/16 ==>
still pending- resolved check email java class names - we can leave it as is- * ECOMP is a trademark and service mark of AT&T Intellectual Property. ---------- Can be removed
- Catherine suggested via email: I would suggest to remove it in the License.txt file posted on the root repo. Then later on, change in file you are updating
10. JUnit /Sonar coverage to 50% on SDK and Portal. - Deadline March 15th for SDK
- SDK - JUnit test coverage reached 19.7% - Hima (pending code review and push to gerrit) - Code need to push to gerrit - PORTAL-161 - Add the JUNIT plumbing for PortalSDK Delivered
- Shireesh will coordinate his team with Hima and Kishore Gujja - done
- Local version is up to 24-25%, planning on pushing today - Sitharaman
- 26.1%
- Saravanan now 37.7%
- JIRA ticket is in delivered state; I recommend reopening and putting in in progress state until 50% is reached
- SDK - JUnit test coverage reached 19.7% - Hima (pending code review and push to gerrit) - Code need to push to gerrit - PORTAL-161 - Add the JUNIT plumbing for PortalSDK Delivered
- Portal - target 30% to 50% - Girish/Hari team will continue from Gerrit - PORTAL-136 - Raise JUnit test coverage ONAP Portal to 50% for Beijing Open
- Hari is coordinating the remaining code coverage on Portal (right now it is at 48.7%) - Kishore,
Manoop to followup with Gildas on the Sonar upgrade issue which got 2% down for portal form 40 - 38% (this is due to change in sonar calculation with new upgrade).- 50.2 close ticket
- now 50.5 Portal-136 should be Closed, it is still in open state
11.Discussed remaining JIRA items in great details → portal-151
a.(assign priority from items in wiki page to JIRA by Leimeng)
b. JIRA ticket is in open state
12. MUSIC integration - add JIRA epic/US - Sunder to provide the % complete
- Development is targeting to complete by 02/28
- Leimeng to coordinate a meeting to share the MUSIC integration details with testing teams to plan the test strategy for these features.
- on-track, couple days to wrap up development
- Robert 80% finished ; needs more testing
- need update
13. AAF, if AAF is not ready for testing by 2/15, then Portal will not integrated with AAF for Beijing release - Leimeng send email to Sai - Is the AAF instance ready in LAB env to test the integration?
- Sunder to followup with Sai - ask Sunder
- need update
14. Defect tracking of Critical and Highs - Naveen and Shireesh to coordinate with Leimeng/Lorraine to test and close them and raise as concern if cannot be closed.
- automated testing making progress on VM11
- Sunder will refresh VM11 environment
- looking at test cases
- will set up separate meeting (if needed) for critical and high issues
- will contact Lorraine if there are any road blocks to closing any
- Naveen not getting updates from team - Sunder should set up call with Sireesh and Naveen if possible; Sireesh says they need help with local setup - having call on it with Sunder
15.
- Beijing Release Planning:
M0 - dev kick-off, Nov 16M1 - planning Jan 16M2 Functionality Freeze→ fill in the contents by Manoop & Leimeng - doneM3 API/Data Model Freeze- M4 Code Freeze