Thanks everyone for attending the weekly meeting, where I listed todo items and followed with a name who suppose to be the owner of the correspondence item according to the conference status but any volunteer will be welcome!

1 On this meeting, we went through the basic release planning: https://wiki.onap.org/display/DW/Multi-Cloud+Release+1+Planning
2 Team members shared the progress on the different dependent project communication about compatible API design/integration in R1:
todo: 

  • Identify instantiation process with SO team (Xinhui)
  • Continue discussion with APP-C team on interfaces for R1 use cases (Andrew/Bin Yang/Danny)
  • Confirm with A&AI team for model change (Brain/Ethan)
  • DCAE for controller service deployment scenario and dependency on designate (Danny/Bin Hu)
  • SDN-C to understand if related to multi-vim in R1 (Danny/Margaret Chiosi/Maopeng/Robert Tao)


3 Went through the pros and cons of designate enabling, different options are available from rich support of underlying cloud if not only OpenStack centric
4 Clarify VolTE use case from multi-vim perspective(Xinhui/Gil)


Please pay attention to below high risks for our R1 delivery:
(1) identify interfaces with dependent projects, please help item 2 with priority;
(2) cover Integration check discussion with the dependent projects, e.g. how to do the check tests between two parties, resource/time/test case.

  • No labels