Date

Attendees: Shankar, Sandeep, Swami, George, Krishna, Ben, Devendra, Ferri, Kingsly, Matt, Melanie, Saravanan

Agenda:


1.Dublin Test Status: 

OOF-PCI test status is now COMPLETE !! Appreciate all the hard work, and especially from our 

test lead Krishna Moorthy. We have dependency on two CCSDK JIRA items (code already merged but not in Windriver)

2. SDN-R integration for Policy -> SDN-R -> RAN-Sim flow & SDN-R implementation for DMaaP producer

SDN-R Netconf mount still an open issue. Sandeep in touch with Saravanan.
SDN-R code has been merged. Waiting for Windriver (SB-04) to complete test.
Netconf notification still under development (code needed in both RAN-SIM and CCSDK)

RAN-SIM: have requested more VMs than Casablanca, expect to have more netconf servers.
e.g. 67 servers for 1000 cells. (we had 27 servers in Casablanca)
Plans to add functionality in RAN-SIM to also address other use cases.
Jeff's netconf server work is also likely to use same Honeycomb netconf server technology from OFF-PCI work.


3. Winlab status

Winlab status from Krishna - Hanif has redeployed in Winlab. ONAP setup is fully up.
Cloned OOM from master branch. Redeployed on Wed.
ConfigDB is up and running. RAN-SIM is being installed.


4. Demos:

OOF-PCI presentation/demo as part of ONAP/ONAP joint demos on June 28 10-12

OOF-PCI full demo: week of July 8th or July 15 (date will be decided next week)

Also added to ONAP demo list wiki page

ONAP Community Awards: Dublin Release (Demos Only) 


5. El Alto -> DCAE work, check-in ConfigDB and SDN-R updates into official ONAP?

  • did not discuss


6. Frankfurt items - discussed timeline on Wed use case realization call. Need to discuss and finalize by Sept M1 date.