DRAFT PROPOSAL FOR COMMENTS

The following items are expected to be completed for the project to Pass the Release Candidate Milestone.

This template must be filled out for every Release Candidate Milestone (RC0, 1, 2, x)

RC Release Candidate Milestone overview is available in wiki.



Practice AreaCheckpointYes/NoEvidencesHow to?
Product ManagementAre all tasks associated with the release been marked as "Done" in Jira?NoOutstanding tasks remain for fixing the dependency security vulnerabilites - they will be complete by RC1

Have all findings from previous milestones been addressed?YesProvide link to JIRA findings
DevelopmentHave all Defects of priority Highest and High been in status "Done" in Jira?No, but they are being worked

Provide link to JIRA issue (type bug) of priority Highest and High. 

Getting issues...


Are all JIRA issues used as a reference in a commit in status "Done" in Jira?Yes
Very often, some JIRA issue remains in status "Todo" in JIRA while the commit they are referenced to is successful.
Is there any pending commit related to Highest and High priority issues older than 36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours.NoAAI in Gerrit
Are all the Jenkins jobs successfully passed (verify + merge jobs)?Yes

Provide link to "Merge job" as evidence in Jenkins project tab

Jenkins Merge Jobs


Has the team delivered all their release artifacts in Nexus Release or Nexus Staging repo?

There should be at least ONE version of each artifacts available in Nexus Release or Nexus Staging repo.

YesOn the AAI weekly call 2018-04-11 it was agreed that AAI will request a release of all artifacts for RC0 Wednesday 18 April and remove references to -STAGING artifactsRefer to Independent Versioning and Release Process for procedure
Integration and TestingHave all CSIT Use Cases (created by each project team) passed?YesProvide link to evidence. As things are moving fast, we want to ensure CSIT are still "green".
Is there a Docker images available for each repository?YesNexus docker repo
Has the project code successfully passed the Daily Build process?Yes
Goal is to ensure the latest project commit has not broken the Integration Daily Build 
Has the OOM deployment passed?YesEnsure in Jenkins External Labs all Health Check pass.
Has the Heat deployment passed?YesEnsure in Jenkins External Labs all Health Check pass.
Documentation

For RC0, for project delivering binaries, has the team populated and validated all the sections of either the Platform Component or SDK template?


WIP

Most teams have already created the high level file structures in readthedocs, and populated some actual documentation. However, the remaining sections of the appropriate teamplate must be completed.

Platform: A&AI, APP-C, CLAMP, CLI, DCAE, DMaaP, Holmes, MSB, OOM, Policy, Portal, SDN-C SDC, SO, UseCase UI, VFC, VID

SDKs: AAF, CCSDK, External API Framework, Multi VIM/Cloud, VNFSDK

For RC1, has the team addressed any issue (recorded in JIRA) provided by the Documentation team?




For RC2, for project delivering binaries, has the team populated and validated all the sections of the Release Notestemplate?




For RC2, has the Documentation Team provided the final approval for your project documentation?