1

M4 milestone update (M4 scheduled for March 24th)

  • Documentation of integration test tasks - need link to documentation of CCVPN closed loop tests
  • Preliminary documentation - Input and feedback would be needed
2Integration Testing - TIM Contribution Ahila P , Alessandro Gerardo D'Alessandro 
  • Ahila to have an offline discussion with Alessandro on TIM testing contribution
3Network Slicing enhancements - E2E Network Slicing use case - Enhancements
  • Inputs received from Swami
  • To have an offline review and discussion for enhancements 
4Lab logistic issueAhila P 
  • There are 3 different testing options with 3 different templates but current Winlab can only support 2 setups in parallel. A third setup is needed.
  • Kevin to ask for support, e.g., from CMCC lab, so that 3 options can be tested in parallel.