Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  1. Review status on items assigned to dev team
  2. Go over JIRA list assigned for Beijing release
  3. Discuss M1 planning and check list for Beijing release

Attendees:

Chris Lott, Lorraine Welch GiriWei-Ting LoLeimeng ShiSunder Tattavarada, Hima, Garima, Farhan Mir

Discussion Items:

  1. Plan to release SDK 2.1.0 version and then communicate to partners to update their poms - Sunder/Leimeng - ETA 1/17.
  2. Extend Portal-119 to split DB for Portal and SDK - Robert - provide ETA by 1/11
  3. Sent grep scan on "master_dev" branch to check if "ecomp" appears in Portal - done - Hima will be cleaning up - ETA 1/10.
  4. SDK will be next to scan - done- Lorraine - ETA 1/11
  5. Split Portal-19 to Hima and Robert (based on Lorraine's scan output)  - create tasks based on the scan - Robert to analyze the font "Omnes-ECOMP-W02".
  6. JUnit /Sonar coverage to 50% , assigned to Himaon SDK and Portal. (
    1. SDK - JUnit test coverage from 4% to 50% - Hima (pending code review and push to gerrit)
    2. Portal - target 30% to 50% - Giri (to coordinate with Hima to find the right code modules)
  7. Discussed remaining JIRA items in great details
  8. M1 due on 1/8/2018 (same template as Amsterdam) - Manoop/Leimeng
  9. Check with IBM team members - Manoop/Abbas/Sunder
  10. Beijing Release Planning:
    1. M0 - dev kick-off, Nov 16
    2. M1 - planning Jan 16
    3. M2 -  functionality freeze Feb 15
    4. M3 - API freeze Mar 1
    5. M4 - code freeze Apr 5

...