You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 2 Next »

Agenda:

  1. Review status on items assigned to dev team
  2. Go over JIRA list assigned for Beijing release
  3. Discuss M1 planning and check list for Beijing release

Attendees:

Chris Lott, Giri, Wei-Ting LoLeimeng ShiSunder Tattavarada, Hima, Farhan Mir

Discussion Items:

  1. Plan to release SDK 2.1.0 version and then communicate to partners to update their poms - Sunder/Leimeng - ETA 1/17.
  2. Extend Portal-119 to split DB for Portal and SDK - Robert - provide ETA by 1/11
  3. Sent grep scan on "master_dev" branch to check if "ecomp" appears in Portal - done - Hima will be cleaning up - ETA 1/10.
  4. SDK will be next to scan - Lorraine - ETA 1/11
  5. Split Portal-19 to Hima and Robert (based on Lorraine's scan output)  - create tasks based on the scan - Robert to analyze the font "Omnes-ECOMP-W02".
  6. JUnit /Sonar coverage to 50% on SDK and Portal. (
    1. SDK - JUnit test coverage from 4% to 50% - Hima (pending code review and push to gerrit)
    2. Portal - target 30% to 50% - Giri (to coordinate with Hima to find the right code modules)
  7. Discussed remaining JIRA items in great details
  8. M1 due on 1/8/2018 (same template as Amsterdam) - Manoop/Leimeng
  9. Check with IBM team members - Manoop/Abbas/Sunder
  10. Beijing Release Planning:
    1. M0 - dev kick-off, Nov 16
    2. M1 - planning Jan 16
    3. M2 -  functionality freeze Feb 15
    4. M3 - API freeze Mar 1
    5. M4 - code freeze Apr 5


  • No labels