PriorityM1 ScorecardTSC M1 ApprovalM3 ScorecardM3 TSC ApprovalM4 ScorecardTSC M4 ApprovalFunctional RequirementOwnerProject ImpactedLink(s) to HLD/LLD if anyDependency (from/to) another project(s)T-Shirt Size (XS, S, M, L, XL) (star)Project's Impact: Test Only (TO), Code (C)Committed (C)/Partially Committed (P) or not (N) per Impacted projectsIf Partially or not Committed, what are gaps/ project (people/FTEs; HLD/LLD; etc)Company EngagementNotes
2

Status
colourGreen

YY

Consistent ID of a Cloud Region (Dublin)Bin YangSDNC & APPC , VID, SO, UUI, VFC, OOFConsistent ID of a Cloud Region (Dublin)

APPC(TO, code already exists),

SDN-C: test support only

SO: Support testing effort, changes are likely in.

VFC:Committed

UUI:Committed

VID: Committed based on ATT resources


AT&T

China Mobile


2

Status
colourGreen

Y

Status
colourGreen

M3 Gate (Dublin HPA)


Y

Status
colourYellow

Pending code review and integration


Continuation of HPA (Dublin)Alexander VulVNFSDK, SDC, SO, VF-C, OOF, AAI, Policy, Multi-CloudContinuation of HPA (Dublin)SDC - Jira bugs open, OL001 compatibility requirements addressed.

AAI: TO

SO: Code Hardening, Expansion of use-case support, testing


AAI: assuming schema/model changes only contributed by community. Also depends on AAI modelling SME availability

Intel

ARM(???)

Development t resources from ARM are required to test HPA support on ARM hardware
2

Status
colourGreen

Y

Status
colourGreen

M3 Gate (Dublin Scaling)

Y

Status
colourGreen
titleGreen


Scaling Use Case (Dublin)Scott BlandfordMain focus on DCAE/CLAMP & PolicyScaling Use Case (Dublin)

DCAE: TO

CLAMP: Committed (Based on TechM resource commitment)

Policy: Committed (Based on TechM Resource Commitment)




0

Status
colourGreen

Y

Y

Status
colourGreen
titleGreen

Code delivered in SDC, SO and MultiCloud. Pending Integration.


K8S based Cloud Region SupportMulti-Cloud, AAI, SDC, SOK8S based Cloud Region Support

AAI: TO

SDC & SO: Committed based on Intel/VMWare contribution

AAI: Partially committed

AAI: assuming schema/model changes only contributed by community. Also depends on AAI modelling SME availability

Intel, VMWareTesting confirmed by INTEL
3

Status
colourGreen

POC for Dublin under Multi-Cloud umbrella


Y


Y

Status
colourYellow

Day-2 Configuration and Visualization package is pending.


Distributed Analytics as a Service (Dublin Summary) - Edge Automation

Demo


Distributed Analytics as a Service (Dublin Summary) - Edge Automation

Demo (C)Only demo repositoryDay-2 Configuration and Visualization package is pending. Planning to complete this by RC0.VMware, Intel

Testing confirmed by INTEL

2

Status
colourGreen

SO (AT&T) and VID

(Nokia) Testing confirmed by CM Team (AT&T)

Y

Status
colourGreen

Y

Status
colourYellow

VID functionality completed; SO blocked by SDC issue in deploying workflow into SO


Change Management Dublin Extensions - Flexible designer/orchestratorSO, VIDChange Management Dublin Extensions

SO (C),

VID (C)

SO: Committed (AT&T)

VID: pending final decision from Nokia (stretch goal)


AT&T

Nokia



2

Status
colourGreen

Testing confirmed by Orange and AT&T

YY

Status
colourYellow

Functionality completed; Working on code coverage; code is yet to be merged


Change Management Dublin Extensions - Traffic Migration
APPC, OOFChange Management Dublin Extensions

APPC (C),

OOF (C),

A&AI (TO)

APPC: Committed (Orange)

OOF: Committed (Orange)


Orange


2

Status
colourGreen

Testing confirmed by AT&T

Y

Status
colourGreen

New CMSO APIs in Dublin

Y

Status
colourYellow

Feature completed; working on code coverage


Change Management Dublin Extensions - Schedule OptimizationOOFChange Management Dublin Extensions

OOF (C),

Policy (TO)

OOF: Committed (AT&T)
AT&T
3

Status
colourGreen

Testing confirmed by AT&T

Y

Y
Status
colourGreen
titleGreen

Model Driven Control Loop Design (Close Loop sub-committee)DCAE, CLAMP, Policy

Model driven Control Loop Design





DCAE: AT&T Committed

CLAMP: Committed

Policy: Committed

AT&T commits to finding the required resources

AT&T, Nokia
3

Status
colourGreen

SO Only

Testing confirmed by SO Team

Y


Status
colourGreen

Y

Status
colourGreen


Modularity

SO, SDC, VFC, APPC, SDNC

https://wiki.onap.org/download/attachments/45293323/2018-12%20Virt%20F2F%20-%20%20Dublin%20Architecture%20Requirements-pa3.pptx?version=1&modificationDate=1544650581000&api=v2


https://jira.onap.org/browse/CCSDK-575




SDC: Not committed

APPC: Not committed

SO: Committed based on the code from R3

SDNC: Not committed

VFC: Partially committed

SDC: no resources, not enough info

APPC: no resources

SDNC: no resources

VFC: optimize DB microservice

CDS project will provide Resource assignment functionality



3

Status
colourGreen

ETSI Alignment

SOOL003 plug-in to SO

Ericsson confirmed the integration testing resource for the ETSI SOL003-plugin support


Y

Status
colourGreen

Y

ETSI Alignment

SO plugin to support SOL003 to connect to an external VNFM

SO, SDC, AAI,https://wiki.onap.org/download/attachments/45293323/2018-12%20Virt%20F2F%20-%20%20Dublin%20Architecture%20Requirements-pa3.pptx?version=1&modificationDate=1544650581000&api=v2


SDC: Partially committed (based on Ericsson contribution)

SO: Committed (SOL003) based on contribution from Nokia and Ericsson

AAI: Not Committed

SDC: no resources

.AAI: no resources (detailed impact to be discussed) Action Byuong




4

Status
colourRed

Architecture did not approve

N



OSAM/PNF??????






4

Status
colourRed

N



TOSCA Task Force???https://wiki.onap.org/download/attachments/45293323/2018-12%20Virt%20F2F%20-%20%20Dublin%20Architecture%20Requirements-pa3.pptx?version=1&modificationDate=1544650581000&api=v2


OOF: Policy Tosca model API and ONAP CLI integrationIntel

4

Status
colourRed

N



Alloted Network Function??????






 3

Status
colourGreen

Prabhu Balan – (prabhu.balan1@vodafone.com) from Vodafone.

Sean Joseph (sjoseph1@iconectiv.com)  from iconnectiv.

Y

Status
colourGreen

Y

Status
colourGreen


Phase 1 - VSP Compliance Check

 SDC

CLI/VNFSDK

 VSP Compliance Check within SDC (Dublin)   SDC: Committed based on contribution from VF, Huawei and iconectiv

Vodafone, iconectiv, huawei

  

...