  • No Modeling Presence

    • Add Modeling Swim Lane

    • Add Modeling Artifacts for appropriate milestones to Modeling Swim Lane

  • MO

    • Modeling team does MODEL PLANNING. The planning develops into “High Level Info-model Requirements”. These High level info-model requirements fall into 3 categories:
      • #1: NEW USE CASES - items from the expected Use Cases in the release (Scope of modeling, continuing, introducing, standards updates).
      • #2: REFINING EXISTING MODEL - There are also Existing high level info-model requirements and the current release is focused on continuing or refining the model. Existing in a component that hasn't made it to the information model. Previously at design build-level that needs to be added into information model. For example, a need might have arisen in development but wasn't formalized. Long-lead, multi-release items might fall into this category. coded previously but no Use Case.
      • #3: FORWARD LOOKING WORK (FLW) - Forward thinking requirement. For example, suppose there were a very large use case/requirement or project that is expected to come down the pipe, but if no advanced modeling work were done on it, it wouldn't make the current release. Thus, a model might be proposed in advance of the actual use case/requirement.
    • Use Case Team (evaluating U/C proposals) presents their modeling needs. Each of the Use Case teams needs to come to the modeling S/C meetings to present their expected modeling needs and open a dialogue about potential model impacts so that they can be developed.
    • Architecture understanding reference model. Modeling S/C members should be aware of any updates to the current release's reference model so that potential can be known.
    • PTL- High level release scope from PTLs (understand from ONAP components what updates)
    • PTL - Joint PTL sync meeting


  • M1

    • Modeling team The info-model plan is established. The model planning follows a template that is worked. For example in R6 (Frankfurt) it was here: ONAP R6 Modeling High Level Requirements.
      • #1: MODELING REQUIREMENTS - A description of the modeling requirements are given in more detail.
      • #2: Use Cases Relevance - The relevance use cases are identified and Use Case teams can give more detailed explanation for use case requirements and how they tie to the high-level requirements. This allows for experts in Info-model team to identify what fields of existing info model could be enhanced and become aware of where the impacts are. 
      • #3: Impacted Projects - The impacted projects (e.g. SO, VID, SDC etc) are identified and how they tie to the high level modeling requirements
      • #4: Overlapping proposals - Overlapping proposals from different use cases or forward looking work (FLW) are identified.
      • #5: Model Reuse - During this time, overlap from different proposals that are evaluated can also lead to identifying where model reuse can occur.
      • #6: Owner - The owner(s) for the item are identified
      • #7 Priority - A priority is identified for the info model requirements. A suggested High/Medium/Low is sufficient at this stage.
      • #8 Lower priority - Lower priority requirements are generally considered as "nice to haves".
      • #8 Documentation after implemented - When the model plan is established, modeling requirements documentation after implemented can be worked on.
      • #9 FORWARD LOOKING WORK (FLW) - FLW is another class of requirements which are intended to recognize future needs. This is separate from the ASAMI stereotype view "Experimental" because you can get consensus from the modeling team and the PTL.
    • Use Case Txeveloped.
    • Architecture uxn be known.
    • PTL- Hixl
    • Project Planning / Functional Architecture Defined / Architecture Approved

    • Add “Infomodel Plan Established”

    • Note:  Infomodel Updates Begin / Data Model Refinements Begin (M1.5)

    • Note:  Development Commitments for Infomodel Requirements?
  • M2

    • Functionality Freeze

    • Add “Infomodel Freeze” (Approval)

    • Add “Data Model Freeze” (Approval)

    • Note:  Feed to Data Dictionary??

  • M3

    • API Freeze

    • Add “Infomodel Final”

    • Add “Component Data Model Final” (Approval – Design Level Compliance)

  • M4

    • Code Freeze

    • Kickoff Information Model Requirements for Next Release

  • RCx

    • Runtime Compliance

  • Observations

    • Establishes and Evolves a Common Model

    • Project (Component) Team Involvement in Modeling Solution

    • Governance of Common Model and Corresponding Component Models

    • Update possible in M3 and M4 (bug fixes) per exception process

...