Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • Integrate the AAF and upgrade the APIs to Https - ATT
  • ETSI alignment improvements - Ericcson, Huawei, Verizon
    • SOL005 adaptation
    • SOL003 adaptation
  • PNF orchestration Enhancements - Ericcson, Huawei, Nokia
    • PNF sotware upgradeupgrade  
    • PNF PNP enhancementenhancement  
  • CCVPN Enhancement
    • ODM support -  Fujitsu
    • Eline support - Bell, Huawei, CMCC
  • 5G Slicing - ATT, Amdocs, CMCC, Huawei, Wipro
  • CDS integration enhancement - ATT, Bell, Tech Mahindra
  • (SO Multi Cloud plugin improvements - Intel)
  • HPA -  Intel (Testing effort)


Release Requirements

Features Being considered for F release

...

Sub-components are repositories and are consolidated in a single centralized place. Edit the Release Components name for your project in the centralized page.

onap/so/api-handler-infra

onap/so/bpmn-infra

onap/so/catalog-db-adapter

onap/so/openstack-adapter

onap/so/request-db-adapter

onap/so/sdc-controller

onap/so/sdnc-adapter

onap/so/so-monitoring

onap/so/vfc-adapter

onap/so/vnfm-adapter

Architecture

High level architecture diagram

...

List the API this project is expecting from other projects.
Prior to Release Planning review, Team Leads must agreed on the date by which the API will be fully defined. The API Delivery date must not be later than the release API Freeze date.

Prior to the delivery date, it is a good practice to organize an API review with the API consumers.

Prior to the delivery date, it is a good practice to organize an API review with the API consumers.

API Name

API Description

API Definition Date

API Delivery date

API Definition link (i.e.swagger)

Interface Type
SDC
REST API

Currently Available

TBDAAIREST API

Currently Available

TBDCCSDKOpenDayLight, SLI, AAI Client, dblibEnd of MarchTBDDMaaPAPI  to publish/subscribe to  events sent for VNF/VM action requests.Currently AvailableTBDDMaaP APIAAFApplication Authorization FrameworkCurrently AvailableCurrently Available
  • API Outgoing Dependencies

API this project is delivering to other projects.

APIs for distribute service modelsDefined in AmsterdamDelivered in Amsterdam

SO interfaces


Incoming and Out going
A&AIAPIs for inventory dataDefined in AmsterdamDelivered in Amsterdam

SO interfaces


Out Going
SDN-CAPIs for network controllerDefined in AmsterdamDelivered in Amsterdam

SO interfaces


Out going
APP-CAPIs for application controllerDefined in AmsterdamDelivered in Amsterdam

SO interfaces


Out Going
VF-CAPIs for Network ServiceDefined in AmsterdamDelivered in Amsterdam

SO interfaces


Out Going
Multi-VIMAPIs for Multi-VIMDefined in CasablancaDelivered in Casablanca and enhancements expected in F release.

SO interfaces


Out Going
OOFAPIs for placement and homingDefined in BeijingDelivered in Beijing

SO interfaces


Out Going
DCAEFor PNF instantiation message from DCAE over DMaapDefined in CasablancaDelivered in Casablanca

SO interfaces


Incoming
SOL003ETS SOL003 interafces between SO and VNFMDefined in D releaseDelivered in D release

SO interfaces


Out Going
CDSgRPC APIs between SO and CDSDefined in D releaseDelivered in D release

06

Detailed doc in SO

Jira
serverONAP JIRA
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keySO-2504

Out Going
SOl005ETSI SOL005 interface between SO and NFVO (VFC / external)Defined in F releaseDelivered in F release

Jira
serverONAP JIRA
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keySO-2504

Out Going
API NameAPI DescriptionAPI Definition DateAPI Delivery dateAPI Definition link (i.e.swagger)NB InterfaceRESTful APIAPPC LCM API GUIDE


  • Third Party Products Dependencies

...

Jira
serverONAP JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQueryproject = "Application Controllerservice orchestrator" AND type = Bug AND fixVersion = "Frankfurt Release"
serverId425b2b0a-557c-3c0c-b515-579789cceedb

...

List the risks identified for this release along with the plan to prevent the risk to occur (mitigation) and the plan of action in the case the risk would materialized materialised (contingency).

Risk identifiedMitigation PlanContingency Plan
To fill outTo fill outTo fill out

...