This page summarizes the projects participating into Dublin Release.
...
...
- M1 Status
- 1/24 - TSC 2019-01-24
- 16 out of 30 projects passed
- 16 out of 30 projects passed
- 1/31 -TSC 2019-01-31
- Project M1 Review. TSC Recommendations: Approved except Doc/Integration (additional information to be provided) - Project Status in Dublin Release
- M1 Scorecard Review: Dublin Release Requirements
- 1/24 - TSC 2019-01-24
- M2 Status -
- 2/14 - Please use the augmented checklist here: Deliverables for Functionality Freeze Milestone Checklist Template
- 2/28 - M2 Project M2 Review. TSC Recommendations: Approved - Project Status in Dublin Release
- M3 Status
- 3/5 - Please use the augmented checklist here: Deliverables for API Freeze Milestone Checklist Template
- M4 Status
- RC0 Status
- RC1 Status
- RC2 Status
Sign-off
- 3/14 - TSC Recommendations: Approved - https://wiki.onap.org/display/DW/TSC+2019-03-14
- M3 Project Review- Project Status in Dublin Release
- M3 Scorecard Review: Dublin Release Requirements
- 3/14 - TSC Recommendations: Approved - https://wiki.onap.org/display/DW/TSC+2019-03-14
- M4 Status
- 4/4 - M4 milestone moved to 4/11 to avoid overlap with ONS
- 4/11- TSC 2019-04-11
- 9 out of 29 projects passed. Documentation is now tracked differently
- M4 scorecard not completed by the Owners
- 4/18 - TSC 2019-04-18
- Dublin M4 Milestone (Code Freeze) was passed on April 18th with gating exceptions that will be reviewed on April 25th 2019
- 4/26
- M4 Gating exceptions have been cleared
- RC0/RC1/RC2 Status
- Not all components were ready - took 1 week to get a phased delivery of components
- 5/30 - No Go - day2day shift
- approved on 6/6 by TSC
- Sign-off
- 6/6 - No Go
- 6/13 - No Go but Excellent progress
- 6/21 - ONAP Dublin release is now certified. Release note to be finalized.
Dublin Milestones Status
...
M1
Planning
M2
Functionality freeze
M3
API Freeze
Code Freeze
RC0
Release Candidate 0
RC1
Release Candidate 1
RC2
Release Candidate 2
Sign-Off
Release Delivery
AAI R4 M3 Deliverables for API Freeze Milestone Checklist
Contingent on complete:
Jira | ||||||
---|---|---|---|---|---|---|
|
AAF R4 - M1 Milestone Checklist
Condition: aaf-authz @55% by M3
AAF R4 -M3 Deliverables for API Freeze Milestone Checklist
Failing Sonar coverage: aaf-authz
Need to update the checklist including Modeling Checklist item
APPC Dublin M3 Deliverables for API Freeze Milestone Checklist Template
CLAMP R4 - M1 Deliverables for Planning Milestone Checklist
CLAMP R4 - M3 Deliverables for API Freeze Milestone Checklist
Checklist complete - no swagger API doc
CCSDK : Dublin M2 : Functionality Freeze Milestone Checklist
Condition: All repos unit test coverage > 55% by M3
CCSDK : Dublin M3 : API Freeze Milestone Checklist
Checklist partially complete
Check Jenkins jobs:
https://jenkins.onap.org/view/Merge-Jobs/job/ccsdk-apps-master-merge-java/
- JENKINS ISSUE CORRECTED - PLEASE RECHECK
Unmet Sonar goal: https://sonar.onap.org/dashboard?id=org.onap.ccsdk.dashboard%3Accsdk-app-parent
- This repo was recently re-added after being dormant. There are test cases, but they appear not to being executed. Request permission to bring to 55% by M4.
DCAE R4 M3 Deliverables for API Freeze Milestone Checklist
Waiver requested, defer coverage goal (55%) for several items until M4:
DMaaP R4 - M1 Milestone Checklist
DMaaP R4 - M3 API Freeze Milestone Checklist
Gerrit- ReviewModeling request for data model: "waiting on modeling team."
MS2 Deliverables for Functionality Freeze Milestone Checklist Template
Condition: Followup to document the doc deliverables overtime so that rel_mgmt can support the deliverables
Moving to weekly documentation report... no checklist
M1 Checklist
[ExtAPI] Dublin M3 API Freeze Milestone Checklist
Holmes Release Planning for Dublin
Holmes Deliverables for Planning Milestone Checklist for Dublin
Condition: holmes-common @55% by M3 (TBC) Non-root by 2019-02-28
Holmes Deliverables for API Freeze Milestone Checklist for Dublin
Integration Dublin M1 Deliverables for Planning Milestone Checklist
Integration Dublin M2 Deliverables for Functionality Freeze Milestone Checklist
Provide status on the plan to close the blocker(s).
Integration Dublin M3 Deliverables for API Freeze Milestone Checklist
Need to understand if Integration has sufficient lab capacity for Dublin and a quick to follow maintenance release.
Including POMBA
Logging Dublin Deliverables for Planning Milestone Checklist
Logging Dublin M3 Deliverables for API Freeze Milestone Checklist Template
Checklist complete. No swagger API data
MSB Release Planning for Dublin
MSB Deliverables for Planning Milestone Checklist for Dublin
MSB Deliverables for API Freeze Milestone Checklist for Dublin
No plans to address the architecture review issue: https://jira.onap.org/browse/ONAPARC-253
Modeling Dublin Deliverables for Planning Milestone Checklist
Modeling Dublin Deliverables for Functionality Freeze Milestone Checklist
Condition: unit test coverage > 55% by M3
Modeling Dublin Deliverables for API Freeze Milestone Checklist
Sonar reporting warning: modeling-toscaparsers-javatoscachecker
Deliverables for Functionality Freeze Milestone Checklist
- Conditions: Get all remaining unit test code coverage > 55% by M3
- Plan to design container(s) as non-root: M3 Dublin
MultiCloud R4 Deliverables for API Freeze Milestone Checklist
Conditional:
Need to add Modeling checklist item
Review gerrit (stale merges)
MUSIC Dublin M1 Deliverables for Planning Milestone Checklist
MUSIC Dublin M3 Deliverables for API Freeze Milestone Checklist
Need to update the checklist including Modeling and additional Integration Checklist item
OOM Dublin Release Planning Template
OOM Dublin - M2 Functionality Freeze Milestone Checklist
OOM Dublin - M3 API Freeze Milestone Checklist
-Review gerrit: https://gerrit.onap.org/r/#/c/72189/
https://gerrit.onap.org/r/#/c/80030/
https://gerrit.onap.org/r/#/c/78353/
https://gerrit.onap.org/r/#/c/79268/
https://gerrit.onap.org/r/#/c/79990/
https://gerrit.onap.org/r/#/c/79347/
https://gerrit.onap.org/r/#/c/79989/
https://gerrit.onap.org/r/#/c/79330/
https://gerrit.onap.org/r/#/c/79985/
OOF Dublin M1 Release Planning
OOF Dublin M3 Deliverables for API Freeze Milestone Checklist
Checklist complete.
Conditional: Complete unit test coverage goal by M4 for HAS and CMSO
OOM-CSIT BY M4
Usecase-UI Beijing Release Planning
Dublin Release M1 Deliverables for Planning Milestone Checklist
Dublin Release M3 Deliverables for API Freeze Milestone Checklist
Please complete more of the checklist
Policy R4 Dublin M1 Release Planning
Policy R4 Dublin M1 Deliverables for Planning Milestone Checklist Template
Policy R4 Dublin M3 Deliverables for API Freeze Milestone Checklist Template
Portal R4 M1 Deliverables for Planning Milestone Checklist (Dublin Release)
Portal R4 M3 Deliverables for API Freeze Milestone Checklist
Need to update the checklist including Integration & Modeling Checklist items
Missing swagger API info
Not yet met: Unit test code coverage > 55% by M3
- PLEASE RECHECK - Sonar shows all SDNC repos having > 55% line coverage.
Supporting links not provided in checklist
SDC R4 Deliverables for Functionality Freeze Milestone Checklist
Condition: unit test coverage > 55% by M3
SDC R4 Deliverables for API Freeze Milestone Checklist
-Review gerrit:
(stale merge conflicts) https://gerrit.onap.org/r/#/q/status:open+project:sdc
https://gerrit.onap.org/r/#/c/77504/
-Contingent on complete:
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
-Check Jenkins Job - failing since 12/28
https://jenkins.onap.org/view/Merge-Jobs/job/so-casablanca-merge-java/
VF-C Dublin: Deliverables for API Freeze Milestone Checklist Template
Checklist complete. Missing swagger API info
VID R4 M3 Deliverables for API Freeze Milestone Checklist
Changes since M1?
Missing swagger API info28 | VNF SDK | Dec 2, 2018 | VNF SDK Dublin Release Planning (M1) VNF SDK Deliverables for Planning Milestone Checklist Template(M1) | VNFSDK Dublin M2 Deliverables for Functionality Freeze Checklist Conditional: Unit test coverage by M3 |
| VNF SDK Dublin Code Freeze (M4) | Dublin VNFSDK RC0 Checklist - Release Candidate 0 Milestone | Dublin VNFSDK RC1 Checklist - Release Candidate 1 Milestone | Dublin VNFSDK RC2 Checklist - Release Candidate 2 Milestone | ||
29 | VNF Requirements | Nov 16, 2018 | M2 Deliverables for Functionality Freeze Milestone Checklist VNFRQTS | M3 Deliverables for API Freeze Milestone Checklist | M4 Deliverable for Code Freeze Milestone Checklist VNFRQTS | RC0 Milestone Checklist Template - VNFRQTS | RC1 Milestone - Checklist VNFRQTS | RC2 Milestone checklist VNFRQTS | signoff checklist | ||
30 | VNF Validation (VVP) | Nov 16, 2018 | M2 Deliverables for Functionality Freeze Milestone Checklist Template | M3 Deliverables for API Freeze Milestone Checklist Template | M4 Code Freeze Milestone Checklist Template for VVP | RC1 Milestone Checklist -VVP | RC2 Milestone checklist VVP | Signoff |