- M1 Status
- 1/24 - TSC 2019-01-24
- 16 out of 30 projects passed
- 16 out of 30 projects passed
- 1/31 -TSC 2019-01-31
- Project M1 Review. TSC Recommendations: Approved except Doc/Integration (additional information to be provided) - Project Status in Dublin Release
- M1 Scorecard Review: Dublin Release Requirements
- 1/24 - TSC 2019-01-24
- M2 Status -
- 2/14 - Please use the augmented checklist here: Deliverables for Functionality Freeze Milestone Checklist Template
- 2/28 - M2 Project Review. TSC Recommendations: Approved - Project Status in Dublin Release
- M3 Status
- 3/5 - Please use the augmented checklist here: Deliverables for API Freeze Milestone Checklist Template
- 3/14 - TSC Recommendations: Approved - https://wiki.onap.org/display/DW/TSC+2019-03-14
- M3 Project Review- Project Status in Dublin Release
- M3 Scorecard Review: Dublin Release Requirements
- M4 Status
- 4/4 - M4 milestone moved to 4/11 to avoid overlap with ONS
- 4/11- TSC 2019-04-11
- 9 out of 29 projects passed. Documentation is now tracked differently
- M4 scorecard not completed by the Owners
- 4/18 - TSC 2019-04-18
- Dublin M4 Milestone (Code Freeze) was passed on April 18th with gating exceptions that will be reviewed on April 25th 2019
- 4/26
- M4 Gating exceptions have been cleared
- RC0 Status
- RC1 Status
- RC2 Status
- /RC1/RC2 Status
- Not all components were ready - took 1 week to get a phased delivery of components
- 5/30 - No Go - day2day shift
- approved on 6/6 by TSC
- Sign-off
- 6/6 - No Go
- 6/13 - No Go but Excellent progress
- 6/21 - ONAP Dublin release is now certified. Release note to be finalized.
Dublin Milestones Status
Project Name | Project Tech. Lead | M0 Kick-Off/Intention Submission | M1 Planning | M2 Functionality freeze | M3 API Freeze | M4 Code Freeze | RC0 Release Candidate 0 | RC1 Release Candidate 1 | RC2 Release Candidate 2 | Sign-Off Release Delivery | |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | A & AI | Dec 3, 2018 | AAI R4 M2 Deliverables for Functionality Freeze Milestone Checklist | AAI R4 Deliverables for RC1 Milestone Checklist 4 Docs jiras - recently updates |
Check on portal test results for AAI-2411
Open high7 | DMaaP | Mandar Sawant | Yes, per default | DMaaP R4 - M1 Release Planning DMaaP R4 - M1 Milestone Checklist | DMaaP R4 - M2 Functionality Freeze Milestone Checklist Condition: All repos unit test coverage > 55% by M3, non-root post Dublin | DMaaP R4 - M3 API Freeze Milestone Checklist Gerrit- Review https://gerrit.onap.org/r/#/c/79574/ Modeling request for data model: "waiting on modeling team." | DMaap R4 - M4 Code Freeze Milestone Checklist Swagger docs by RC2 |
DMaaP R4 - RC1 Milestone Checklist | DMaaP R4 - RC2 Milestone Checklist | DMaaP R4 - Release Sign- |
Off Milestone Checklist Template | |||||||||||
8 | Documentation | Yes, per default | MS2 Deliverables for Functionality Freeze Milestone Checklist Template Condition: Followup to document the doc deliverables overtime so that rel_mgmt can support the deliverables | Moving to weekly documentation report... no checklist | |||||||
9 | External API Framework | Dec 5, 2018 | Planning worksheet M1 Checklist | [ExtAPI] Dublin M3 API Freeze Milestone Checklist | ExtAPI Dublin M4 Code Freeze Milestone Checklist Project needs help getting signed certificates |
. | Integration Dublin M4 Deliverable for Code Freeze Milestone Checklist | Integration Dublin RC0 Milestone Checklist | Integration Dublin RC1 Milestone Checklist | Integration Dublin |
RC2 Milestone Checklist |
M2 | MSB Deliverables for API Freeze Milestone Checklist for Dublin |
MSB Deliverables for |
RC1 Milestone |
for Dublin | MSB Deliverables for |
RC2 Milestone for Dublin | MSB Deliverables for |
MUSIC Dublin RC2 Milestone Checklist | MUSIC Dublin Deliverables for Release Sign-Off Milestone Checklist |
17 | ONAP CLI | Dec 3, 2018 | Dublin-M2-Checklist | Need to update the checklist including Modeling and additional Integration Checklist item | Dublin M4 Code Freeze Milestone Checklist | Dublin-RC0 Milestone Checklist | Dublin-RC1 Milestone Checklist Old version in Dublin -
| Dublin-RC2 Milestone Checklist | Dublin-Release Sign-Off | ||||||||||
18 | ONAP Operations Manager | Dec 3, 2018 | OOM - Deliverables for Planning Milestone Checklist OOM Dublin Release Planning Template | OOM Dublin - M2 Functionality Freeze Milestone Checklist | OOM Dublin - M3 API Freeze Milestone Checklist |
OOM Dublin - RC1 Milestone Deliverables Checklist |
19 | ONAP Optimization Framework | Dec 3, 2018 | OOF Dublin M1 Deliverables for Planning Milestone Checklist OOF Dublin M1 Release Planning | OOF Dublin M2 Functionality Freeze Milestone Checklist Condition: unit test coverage > 55% by M3 | OOF Dublin M3 Deliverables for API Freeze Milestone Checklist Checklist complete. Conditional: Complete unit test coverage goal by M4 for HAS and CMSO OOM-CSIT BY M4 | OOF Dublin RC0 Milestone Checklist |
Docs still under development
POLICY-167622 | Portal Platform | Nov 30, 2018 | Portal R4 M1 Release Planning (Dublin Release) Portal R4 M1 Deliverables for Planning Milestone Checklist (Dublin Release) | Portal R4 M2 Deliverables for Functionality Freeze Milestone Checklist Dependency on OOM for non-root testing; other dependencies articulated in the risks | Portal R4 M3 Deliverables for API Freeze Milestone Checklist Need to update the checklist including Integration & Modeling Checklist items | Portal R4 M4 for Code Freeze Milestone Checklist | Portal R4 RC0 Milestone Checklist | ||||
23 | SDN-C | Yes, per default | SDNC : Dublin M2 : Functionality Freeze Milestone Checklist | SDNC : Dublin RC0 : Deliverables for RC0 Milestone Checklist Update certificate in RC1 | SDNC : Dublin RC1 : Deliverables for RC1 Milestone Checklist 2 high in Submitted state Certificate is updated |
24 | Service Design & Creation | Dec 4, 2018 | SDC R4 Deliverables for Functionality Freeze Milestone Checklist Condition: unit test coverage > 55% by M3 | SDC R4 Deliverables for API Freeze Milestone Checklist Condition: Meet 55% coverage goal by M4 Sonar (52+%) https://sonar.onap.org/dashboard?id=org.onap.sdc.sdc-distribution-client%3Asdc-main-distribution-client%3Amaster (49+%) https://sonar.onap.org/dashboard?id=org.openecomp.sdc%3Asdc-main%3Amaster Risks #20/21 | SDC R4 Deliverable for Code Freeze Milestone Checklist | SDC R4 Deliverables for RC0 Milestone Checklist Sonar below goal: sdc master | SDC R4 Deliverables for RC1 Milestone Checklist Waiver requested: Sonar below goal: sdc master | SDC R4 Deliverables for RC2 Milestone Checklist Waiver granted: Sonar below goal: sdc master, sdc dublin, sdc-sdc-distribution-client master, dcae-d dt-be-main dublin, dcae-d dt-be-main master |
25 | Service Orchestrator | Dec 2, 2018 | SO Dublin RC0: Deliverables for RC0 Milestone Checklist Template |
26 | VF-C: Virtual Function Controller | Dec 2, 2018 | VF-C Dublin: Deliverables for Functionality Freeze Milestone Checklist Template | VF-C Dublin: Deliverables for API Freeze Milestone Checklist Template Checklist complete. Missing swagger API info | VF-C Dublin: Deliverables for RC0 Milestone Checklist Template DEPRECATED: Sonar warning (46%) on vfc-nfvo-driver-vnfm-svnfm-nokia |
VF-C Dublin: Deliverables for RC1 Milestone Checklist Template |
RC2 Milestone Checklist Template | VF-C Dublin: Deliverables for |
Release Sign-Off Milestone Checklist Template |
27 | VID project | Dec 4, 2018 | VID R4 M2 Deliverables for Functionality Freeze Milestone Checklist | VID R4 M3 Deliverables for API Freeze Milestone Checklist Missing swagger API info In -process Integration blockers:
| VID R4 M4 Deliverable for Code Freeze Milestone Checklist | VID R4 RC0 Milestone Checklist |
RC0 images available. Build broken while converting to global-jjb