- M1 Status
- 1/24 - TSC 2019-01-24
- 16 out of 30 projects passed
- 16 out of 30 projects passed
- 1/31 -TSC 2019-01-31
- Project M1 Review. TSC Recommendations: Approved except Doc/Integration (additional information to be provided) - Project Status in Dublin Release
- M1 Scorecard Review: Dublin Release Requirements
- 1/24 - TSC 2019-01-24
- M2 Status -
- 2/14 - Please use the augmented checklist here: Deliverables for Functionality Freeze Milestone Checklist Template
- 2/28 - M2 Project Review. TSC Recommendations: Approved - Project Status in Dublin Release
- M3 Status
- 3/5 - Please use the augmented checklist here: Deliverables for API Freeze Milestone Checklist Template
- 3/14 - TSC Recommendations: Approved - https://wiki.onap.org/display/DW/TSC+2019-03-14
- M3 Project Review- Project Status in Dublin Release
- M3 Scorecard Review: Dublin Release Requirements
- M4 Status
- 4/4 - M4 milestone moved to 4/11 to avoid overlap with ONS
- 4/11- TSC 2019-04-11
- 9 out of 29 projects passed. Documentation is now tracked differently
- M4 scorecard not completed by the Owners
- 4/18 - TSC 2019-04-18
- Dublin M4 Milestone (Code Freeze) was passed on April 18th with gating exceptions that will be reviewed on April 25th 2019
- 4/26
- M4 Gating exceptions have been cleared
- RC0/RC1/RC2 Status
- Not all components were ready - took 1 week to get a phased delivery of components
- RC1 Status
- RC2 Status
- 5/30 - No Go - day2day shift
- approved on 6/6 by TSC
- Sign-off
- 6/6 - No Go
- 6/13 - No Go but Excellent progress
- 6/21 - ONAP Dublin release is now certified. Release note to be finalized.
Dublin Milestones Status
Open high
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
4 | CLAMP | Yes, per default | CLAMP R4 - M1 Release Planning |
CLAMP R4 - M1 Deliverables for Planning Milestone Checklist | CLAMP R4 - M2 Functionality Freeze Milestone Checklist | CLAMP R4 - M3 Deliverables for API Freeze Milestone Checklist Checklist complete - no swagger API doc | CLAMP R4 - RC0 Milestone Checklist | CLAMP R4 - RC1 Milestone Checklist | CLAMP R4 - RC2 Milestone Checklist | CLAMP R4 - Deliverables for Release Sign-Off Milestone Checklist | ||||
5 | Common Controller SDK | Yes, per default | CCSDK : Dublin M2 : Functionality Freeze Milestone Checklist Condition: All repos unit test coverage > 55% by M3 | CCSDK : Dublin M3 : API Freeze Milestone Checklist Conditions: Unmet Sonar goal: passes as of 2019-04-09 | CCSDK : Dublin RC1 : Deliverables for RC1 Milestone Checklist |
Open high
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
6 | DCAE |
Dec 5, 2018 | DCAE R4 M2 Functionality Freeze Milestone Checklist | DCAE R4 M3 Deliverables for API Freeze Milestone Checklist Waiver requested, defer coverage goal (55%) for several items until M4: | DCAE R4 RC0 Milestone Checklist | DCAE R4 RC1 Milestone Checklist 1 Doc Jira Ticket |
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
7 | DMaaP |
External API Deliverables for Dublin R4 Release Sign-Off Milestone Checklist | |
10 | Holmes |
Integration |
Dublin |
Below Sonar goal (no waiver): MUSIC
MUSIC Dublin Deliverables for Release Sign-Off Milestone Checklist | |
17 |
ONAP CLI | Dec 3, 2018 | Dublin-M2-Checklist | Need to update the checklist including Modeling and additional Integration Checklist item | Dublin M4 Code Freeze Milestone Checklist | Dublin-RC0 Milestone Checklist | Dublin-RC1 Milestone Checklist Old version in Dublin -
| Dublin-RC2 Milestone Checklist | Dublin-Release Sign-Off | ||||||||||
18 | ONAP Operations Manager | Dec 3, 2018 | OOM - Deliverables for Planning Milestone Checklist OOM Dublin Release Planning Template | OOM Dublin - M2 Functionality Freeze Milestone Checklist | OOM Dublin - M3 API Freeze Milestone Checklist | OOM Dublin - RC0 Milestone Deliverables Checklist | OOM Dublin - RC1 Milestone Deliverables Checklist |
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Doc completion risk
19 | ONAP Optimization Framework | Dec 3, 2018 | OOF Dublin |
M1 Deliverables for Planning Milestone Checklist OOF Dublin M1 Release Planning | OOF Dublin M2 Functionality Freeze Milestone Checklist Condition: unit test coverage > 55% by M3 | OOF Dublin M3 Deliverables for API Freeze Milestone Checklist Checklist complete. Conditional: Complete unit test coverage goal by M4 for HAS and CMSO OOM-CSIT BY M4 | OOF Dublin RC0 Milestone Checklist |
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Doc completion risk - focus on release notes & install docs |
Docs still under development
22 | Portal Platform | Nov 30, 2018 | Portal R4 M1 Release Planning (Dublin Release) Portal R4 M1 Deliverables for Planning Milestone Checklist (Dublin Release) | Portal R4 M2 Deliverables for Functionality Freeze Milestone Checklist Dependency on OOM for non-root testing; other dependencies articulated in the risks | Portal R4 M3 Deliverables for API Freeze Milestone Checklist Need to update the checklist including Integration & Modeling Checklist items |
Portal R4 M4 for Code Freeze Milestone Checklist
Portal R4 RC0 Milestone Checklist
Portal R4 RC1 Milestone Checklist
Portal R4 RC2 Dublin Milestone Checklist
Portal R4 M4 for Code Freeze Milestone Checklist | Portal R4 RC0 Milestone Checklist |
23 | SDN-C | Yes, per default | SDNC : Dublin M2 : Functionality Freeze Milestone Checklist | SDNC : Dublin RC0 : Deliverables for RC0 Milestone Checklist Update certificate in RC1 | SDNC : Dublin RC1 : Deliverables for RC1 Milestone Checklist 2 high in Submitted state Certificate is updated |
24 | Service Design & Creation | Dec 4, 2018 | SDC R4 Deliverables for Functionality Freeze Milestone Checklist Condition: unit test coverage > 55% by M3 | SDC R4 Deliverables for API Freeze Milestone Checklist Condition: Meet 55% coverage goal by M4 Sonar (52+%) https://sonar.onap.org/dashboard?id=org.onap.sdc.sdc-distribution-client%3Asdc-main-distribution-client%3Amaster (49+%) https://sonar.onap.org/dashboard?id=org.openecomp.sdc%3Asdc-main%3Amaster Risks #20/21 | SDC R4 Deliverable for Code Freeze Milestone Checklist | SDC R4 Deliverables for RC0 Milestone Checklist Sonar below goal: sdc master | SDC R4 Deliverables for RC1 Milestone Checklist Waiver requested: Sonar below goal: sdc master | SDC R4 Deliverables for RC2 Milestone Checklist Waiver granted: Sonar below goal: sdc master, sdc dublin, sdc-sdc-distribution-client master, dcae-d dt-be-main dublin, dcae-d dt-be-main master | |||
25 | Service Orchestrator | Dec 2, 2018 | SO Dublin RC0: Deliverables for RC0 Milestone Checklist Template |
28 | VNF SDK | Dec 2, 2018 | VNF SDK Dublin Release Planning (M1) VNF SDK Deliverables for Planning Milestone Checklist Template(M1) | VNFSDK Dublin M2 Deliverables for Functionality Freeze Checklist Conditional: Unit test coverage by M3 |
| VNF SDK Dublin Code Freeze (M4) | Dublin VNFSDK RC0 Checklist - Release Candidate 0 Milestone | Dublin VNFSDK RC1 Checklist - Release Candidate 1 Milestone | Dublin VNFSDK RC2 Checklist - Release Candidate 2 Milestone | ||
29 | VNF Requirements | Nov 16, 2018 | M2 Deliverables for Functionality Freeze Milestone Checklist VNFRQTS | M3 Deliverables for API Freeze Milestone Checklist | M4 Deliverable for Code Freeze Milestone Checklist VNFRQTS | RC0 Milestone Checklist Template - VNFRQTS | RC1 Milestone - Checklist VNFRQTS | RC2 Milestone checklist VNFRQTS | signoff checklist | ||
30 | VNF Validation (VVP) | Nov 16, 2018 | M2 Deliverables for Functionality Freeze Milestone Checklist Template | M3 Deliverables for API Freeze Milestone Checklist Template | M4 Code Freeze Milestone Checklist Template for VVP | RC1 Milestone Checklist -VVP | RC2 Milestone checklist VVP | Signoff |