July 19 Update: Scope Change. From a Casablanca scope perspective, there are 2 additional functional requirements added:
...
View file name ONAP Casablanca M2 Status Summary Version1.pdf page TSC 2018-07-26 space Meetings height 250
View file name ONAP Casablanca Release Checklist V2.pdf page TSC 2018-07-26 space Meetings height 250
M3 Status
M3 review took place on August 23, 2018.Main
M3 Outcome:
AAF, ExtAPI, VVP and VNFRQTS are conditionally approved until they undergo Architecture review which is scheduled on Tuesday, August 28.
...
View file | ||||||||
---|---|---|---|---|---|---|---|---|
|
View file | ||||||||
---|---|---|---|---|---|---|---|---|
|
M4 Status
M4 review took place on Sept 20, 2018.
Materials:
View file | ||||||||
---|---|---|---|---|---|---|---|---|
|
View file | ||||||||
---|---|---|---|---|---|---|---|---|
|
M4 Outcome
TSC approved the TSC is currently in the process approving the Release Manager Recommendations. Link to approval.
Release Manager recommendation (as per slide # 35)
- Pass projects who have submitted checklist on time (specifically all project but SDC and UseCase UI)
- Get Action Items addressed within 1 week
Action Items:
- Michael Lando to to review Bugs impacting HPA
1 SDC defect fixed, one still in WIP. ETA: planned for beg next week.Status colour RedGreen title No Update Done Slide #4: - Vimal Begwani to to provide status on 5 G implementation STATUS
Status colour Yellow title WIP
5G Plug & Play: Brian Freeman Follow up on PRH HealthCheck within DCAEStatus colour Green title Done
5G/PNF: Lifecycle Managament Support: Tracy Van Brakle and Jorge Hernandez to confirm that the necessary Ansible playbooks were delivered,
and the necessary directed graph updates were made to invoke those playbooks
5G: Bulk PM: Vimal Begwani File collector WIP. ETA Oct 4.Status colour Green title Done Slide 7-12: - Slide 12: Sarat Puthenpura to provide ETA on 5G Performance Analysis and Optimization STATUS
Status colour Green title Done - Slide #16: PTLs to update Casablanca Platform Maturity table at https://wiki.onap.org/display/DW/Casablanca+Release+Platform+Maturity.
AAI, AAF, DMAAP, Modeling,USECASE UI, SDC, VID Modeling (Hui Deng), VID (Ofir Sonsino)Status colour Red title Missing - Slide #16: Gildas to add Platform Maturity table in M4 checklist. STATUS
Status colour Green title Done - Slide #23: Catherine Lefevre Lefèvre to update status on OSAM/PNF (postpone to Dublin or not) STATUS:
OSAM postpone to Dublin. Best effort for PNF Onboarding.Status colour Yellow title Postponed - Slide #25: Impacted PTLs to fix CSIT Failure. STATUS
for DCAE, Multicloud, VFC, ExtAPI.Status colour Green title Done
AAI, OOF, DMAAP (LF Ticket 59951 ), DMAAP,OOF.Status colour Red title Failure - Slide #27: Jonathan Gathman and Michael lando Lando to increase code coverage for aaf-auth and sdc master and provide update on repos for which there is no report in Sonar. STATUS
STATUS:
Status | ||||
---|---|---|---|---|
|
...
SDC on sdc/dcae-d/tosca-lab Status colour Yellow title WIP
sdc/dcae-d/dt-be-main
reach 51% Status colour Green title Done
sdc/dcae-d/dt-be-property Status colour
...
Yellow title
...
WIP
sdc/dcae-d/ci : Automation repo. Won't be covered by Code Coverage.
...
- Slide #28: Impacted PTLs to publish Vulnerability report. Steven Wright to follow up with Gildas Lanilis for VVP. STATUS
for VVP, Multicloud. , Modeling, MUSICStatus colour Green title Done
Modeling, MUSIC, UseCase UI UseCase UI (Tao Shen)Status colour Red title Missing - Failure Failure
Logging(Michael O'Brien)Status colour Red title FAILURE
for APPC,HOLMES, AAI, APPC, HOLMES, AAF. AAFStatus colour Green title Done Slide #29-30: Impacted PTLs: Clean or Fix Job - Slide #32: OOF team to ensure Healthcheck passes. STATUS
OOF pass on both Wind River OOM Release and Staging.Status colour Green title Done - Slide # 33 Risks: Jonathan Gathman and Manoop Talasila to address risks #3 on CADI. STATUS: Risk #3 closed.
Status colour Green title Done
RC0 Status
RC0 review took place on Oct 11, 2018.
Materials:
View file | ||||||||
---|---|---|---|---|---|---|---|---|
|
RCO Outcome:
Projects Passing RC0:
- CCSDK
- Doc
- Integration
- VNFRQTS
Action Items:
Conditional on all other Projects in addressing Orange and Red Items (in above slides) related to:
- Pair Wise Testing: MUST be completed by RC1
- HealthCheck, focus on OOM environment, to be addressed by Oct 15
- Docker artifacts: to be delivered by Friday, Oct 12 COB.
RC1 Status
RC1 review took place on Oct 25, 2018.
Materials:
View file | ||||||||
---|---|---|---|---|---|---|---|---|
|
RC1 Outcome:
Projects Passing RC1:
AAI
AAF
Clamp
Cli
Dmaap
Doc
ExtAPI
Integration
Pomba (sub project)
MSB
OOM
SO
VFC
VNFRQTS
VNFSDK
VVP
Update on RC1 on Nov 6:
Based on progress made since RC1 on Oct 25, and presented at PTL meeting on Nov 5, the following projects qualifies for passing RC1:
- APPC
- CCSDK
- DCAE
- Log
- Multivim
- Music
- Portal
- SDC
- Usecase UI
RC2 Status
By TSC decision on Nov 8, RC2 Milestone has been pushed to Tuesday, Nov 27 and Release Sign-Off to Friday, Nov 30.