This page summarizes the existing projects that are planning to participate into Casablanca Release. Date to announce intend to participate has been pushed to June 14, 2018projects participating into Casablanca Release.

Table of Contents

M1 Status

All projects along with Functional, Non-Functional and Uses Cases marked with a green checked mark passed M1. TSC approved M1 on July 5 (Topic 3, section g)

Deck as approved on July 5 is available in wiki.

View file
nameONAP Casablanca M1 Status Summary Version4.pdf
pageTSC 2018-07-05
spaceMeetings
height250

July 19 Update: Scope Change. From a Casablanca scope perspective, there are 2 additional functional requirements added:

  1. Change Management – Trafic Migration
  2. Change Management – PNF Software Upgrade

Slide deck has been updated accordingly. 

View file
nameONAP Casablanca M1 Status Summary Version5.pdf
height250

M2 Status

All projects passed M2 Functionality Freeze. TSC Approval (Topic #5, Section Y )

View file
nameONAP Casablanca M2 Status Summary Version1.pdf
pageTSC 2018-07-26
spaceMeetings
height250

View file
nameONAP Casablanca Release Checklist V2.pdf
pageTSC 2018-07-26
spaceMeetings
height250

M3 Status

M3 review took place on August 23, 2018.

M3 Outcome:

AAF, ExtAPI, VVP and VNFRQTS are conditionally approved until they undergo Architecture review which is scheduled on Tuesday, August 28.

TSC approved all other projects 

M3 Update: Thursday, August 30. AAF, ExtAPI, VVP and VNFRQTS have gone through the Architecture review. TSC approved M3 milestone (Topic 3, Item 2).

View file
nameONAP Casablanca M3 Status Summary Version2.pdf
pageTSC 2018-08-23
spaceMeetings
height250

View file
nameONAP Casablanca Release Checklist V3.pdf
pageTSC 2018-08-23
spaceMeetings
height250


M4 Status

M4 review took place on Sept 20, 2018.

Materials:

View file
nameONAP Casablanca M4 Status Summary Version1.pdf
pageTSC 2018-09-20
spaceMeetings
height250

View file
nameONAP Casablanca Release Checklist V41.pdf
pageTSC 2018-09-20
spaceMeetings
height400

M4 Outcome

TSC  approved the Release Manager Recommendations. Link to approval.

Release Manager recommendation (as per slide # 35)

  1. Pass projects who have submitted checklist on time (specifically all project but SDC and UseCase UI)
  2. Get Action Items addressed within 1 week

Action Items:

  •  Slide #4: Michael Lando to review Bugs impacting HPA 
    Status
    colourGreen
    titleDone
    1 SDC defect fixed, one still in WIP. ETA: planned for beg next week.
  •  Slide 7-12: Vimal Begwani to provide status on 5 G implementation STATUS 
    Status
    colourYellow
    titleWIP
     

               5G Plug & Play: Brian Freeman Follow up on PRH HealthCheck within DCAE 
    Status
    colourGreen
    titleDone

               5G/PNF: Lifecycle Managament Support: Tracy Van Brakle and Jorge Hernandez to confirm that the necessary Ansible playbooks were delivered,
               and the necessary directed graph updates were made to invoke those playbooks
               5G: Bulk PM: Vimal Begwani File collector WIP. ETA Oct 4. 
    Status
    colourGreen
    titleDone
  •  Slide 12: Sarat Puthenpura to provide ETA on 5G Performance Analysis and Optimization STATUS 
    Status
    colourGreen
    titleDone
  •  Slide #16: PTLs to update Casablanca Platform Maturity table at https://wiki.onap.org/display/DW/Casablanca+Release+Platform+Maturity
    Status
    colourRed
    titleMissing
       Modeling (Hui Deng), VID (Ofir Sonsino)
  •  Slide #16: Gildas to add Platform Maturity table in M4 checklist. STATUS 
    Status
    colourGreen
    titleDone
  •  Slide #23: Catherine Lefèvre to update status on OSAM/PNF (postpone to Dublin or not) STATUS:
    Status
    colourYellow
    titlePostponed
    OSAM postpone to Dublin.
  •  Slide #25: Impacted PTLs to fix CSIT Failure. STATUS 
    Status
    colourGreen
    titleDone
     for DCAE, Multicloud, VFC, ExtAPI, DMAAP,OOF.
  •  Slide #27: Jonathan Gathman and Michael Lando to increase code coverage for aaf-auth and sdc master and provide update on repos for which there is no report in Sonar. 

                           STATUS: 

Status
colourYellow
titleWon't reach 50% goal
Jonathan Gathman indicated that he won't be able to reach the 50% target got AAF by lack of resource.

                                SDC on sdc/dcae-d/tosca-lab 

Status
colourYellow
titleWIP

                                                               sdc/dcae-d/dt-be-main 

Status
colourGreen
titleDone
 reach 51%

                                                               sdc/dcae-d/dt-be-property

Status
colourYellow
titleWIP

                                                               sdc/dcae-d/ci : Automation repo. Won't be covered by Code Coverage.

  •  Slide #28: Impacted PTLs to publish Vulnerability report. Steven Wright to follow up with Gildas Lanilis for VVP. STATUS 
    Status
    colourGreen
    titleDone
     for VVP, Multicloud, Modeling, MUSIC 
                      
    Status
    colourRed
    titleMissing
       UseCase UI (Tao Shen)
  •  Slide #29-30: Impacted PTLs: Clean or Fix Job Failure
                     
    Status
    colourRed
    titleFAILURE
     Logging(Michael O'Brien
    Status
    colourGreen
    titleDone
     for APPC,HOLMES, AAI, AAF  
  •  Slide #32: OOF team to ensure Healthcheck passes. STATUS  
    Status
    colourGreen
    titleDone
    OOF pass on both Wind River OOM Release and Staging.
  •  Slide # 33 Risks: Jonathan Gathman and Manoop Talasila to address risks #3 on CADI. STATUS: Risk #3 closed
    Status
    colourGreen
    titleDone

RC0 Status

RC0 review took place on Oct 11, 2018.

Materials:

View file
nameONAP Casablanca RC0 Status Summary Oct11.pdf
pageTSC 2018-10-11
spaceMeetings
height250

RCO Outcome:

Projects Passing RC0:

  1. CCSDK
  2. Doc
  3. Integration
  4. VNFRQTS

Action Items:

Conditional on all other Projects in addressing Orange and Red Items (in above slides) related to:

  1. Pair Wise Testing: MUST be completed by RC1
  2. HealthCheck, focus on OOM environment, to be addressed by Oct 15
  3. Docker artifacts: to be delivered by Friday, Oct 12 COB.

RC1 Status

RC1 review took place on Oct 25, 2018.

Materials:

View file
nameONAP Casablanca RC1 Status Summary Oct25Version1.pdf
pageTSC 2018-10-25
spaceMeetings
height250

RC1 Outcome:

Projects Passing RC1:

  1. AAI

  2. AAF

  3. Clamp

  4. Cli

  5. Dmaap

  6. Doc

  7. ExtAPI

  8. Integration

  9. Pomba (sub project)

  10. MSB

  11. OOM

  12. SO

  13. VFC

  14. VNFRQTS

  15. VNFSDK

  16. VVP

Update on RC1 on Nov 6:

Based on progress made since RC1 on Oct 25, and presented at PTL meeting on Nov 5,  the following projects qualifies for passing RC1:

  1. APPC
  2. CCSDK
  3. DCAE
  4. Log
  5. Multivim
  6. Music
  7. Portal
  8. SDC
  9. Usecase UI

RC2 Status

By TSC decision on Nov 8, RC2 Milestone has been pushed to Tuesday, Nov 27 and Release Sign-Off to Friday, Nov 30.

Casablanca Milestones Status


Project NameProject Tech. LeadM0 Kick-Off/Intention Submission

M1

Planning

M2

Functionality freeze

M3

API Freeze

M4

Code Freeze

RC0

Release Candidate 0

RC1

Release Candidate 1

RC2

Release Candidate 2

Sign-Off

Release Delivery

1A & AI June 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
2Application Authorization FrameworkJune 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
3APPCJune 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
4CLAMPJune 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
5Common Controller SDKJune 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
6DCAEJune 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
7DMaaPJune 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
8Documentation
Gregory Glover
June 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklist

9External API FrameworkJune 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
10HolmesJune 13, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
11

Integration

June 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
12

Logging Enhancements Project

Including POMBA

June 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
13Microservices BusJune 14, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
14ModelingJune 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistNANANA
15Multi VIM/Cloud

Bin Yang (replacing xinhuili)

June 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
16MUSICJune 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
17ONAP CLIJune 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
18ONAP Operations ManagerJune 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
19ONAP Optimization FrameworkJune 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
20ONAP Usecase UI
Project Proposal
June 8, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
21Policy Framework
Project Proposal
June 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
22Portal Platform
Project Proposal
June 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
23SDN-CJune 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
24Service Design & CreationJune 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
25Service OrchestratorJune 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
26VF-C: Virtual Function ControllerJune 8, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
27VID projectMay 29, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
28VNF SDKJune 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
29VNF RequirementsJune 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist
30VNF Validation (VVP)June 7, 2018

Planning

Checklist

ChecklistChecklistChecklistChecklistChecklistChecklist

____________