Under investigation- junit tests are Orr
This page summarizes the projects participating into Dublin Release.
...
...
- M1 Status
- 1/24 - TSC 2019-01-24
- 16 out of 30 projects passed
- 16 out of 30 projects passed
- 1/31 -TSC 2019-01-31
- Project M1 Review. TSC Recommendations: Approved except Doc/Integration (additional information to be provided) - Project Status in Dublin Release
- M1 Scorecard Review: Dublin Release Requirements
- 1/24 - TSC 2019-01-24
- M2 Status -
- 2/14 - Please use the augmented checklist here: Deliverables for Functionality Freeze Milestone Checklist Template
- 2/28 - M2 Project M2 Review. TSC Recommendations: Approved - Project Status in Dublin Release
- M3 Status
- 3/5 - Please use the augmented checklist here: Deliverables for API Freeze Milestone Checklist Template
- M4 Status
- RC0 Status
- RC1 Status
- RC2 Status
Sign-off
- 3/14 - TSC Recommendations: Approved - https://wiki.onap.org/display/DW/TSC+2019-03-14
- M3 Project Review- Project Status in Dublin Release
- M3 Scorecard Review: Dublin Release Requirements
- 3/14 - TSC Recommendations: Approved - https://wiki.onap.org/display/DW/TSC+2019-03-14
- M4 Status
- 4/4 - M4 milestone moved to 4/11 to avoid overlap with ONS
- 4/11- TSC 2019-04-11
- 9 out of 29 projects passed. Documentation is now tracked differently
- M4 scorecard not completed by the Owners
- 4/18 - TSC 2019-04-18
- Dublin M4 Milestone (Code Freeze) was passed on April 18th with gating exceptions that will be reviewed on April 25th 2019
- 4/26
- M4 Gating exceptions have been cleared
- RC0/RC1/RC2 Status
- Not all components were ready - took 1 week to get a phased delivery of components
- 5/30 - No Go - day2day shift
- approved on 6/6 by TSC
- Sign-off
- 6/6 - No Go
- 6/13 - No Go but Excellent progress
- 6/21 - ONAP Dublin release is now certified. Release note to be finalized.
Dublin Milestones Status
...
M1
Planning
M2
Functionality freeze
M3
API Freeze
Code Freeze
RC0
Release Candidate 0
RC1
Release Candidate 1
RC2
Release Candidate 2
Sign-Off
Release Delivery
AAI R4 M3 Deliverables for API Freeze Milestone Checklist
Contingent on complete:
Jira | ||||||
---|---|---|---|---|---|---|
|
James Forsyth status 14 Mar - Merged - after retest should be complete.
AAF R4 - M1 Milestone Checklist
Condition: aaf-authz @55% by M3
AAF R4 -M3 Deliverables for API Freeze Milestone Checklist
Failing Sonar coverage: aaf-authz
Need to update the checklist including Modeling Checklist item
APPC Dublin M3 Deliverables for API Freeze Milestone Checklist Template
CLAMP R4 - M1 Deliverables for Planning Milestone Checklist
CLAMP R4 - M3 Deliverables for API Freeze Milestone Checklist
Checklist complete - no swagger API doc
CCSDK : Dublin M2 : Functionality Freeze Milestone Checklist
Condition: All repos unit test coverage > 55% by M3
CCSDK : Dublin M3 : API Freeze Milestone Checklist
Checklist partially complete
Check Jenkins jobs:
https://jenkins.onap.org/view/Merge-Jobs/job/ccsdk-apps-master-merge-java/
JENKINS ISSUE CORRECTED - PLEASE RECHECK
Conditions: Unmet Sonar goal: https://sonar.onap.org/dashboard?id=org.onap.ccsdk.dashboard%3Accsdk-app-parent
- This repo was recently re-added after being dormant. There are test cases, but they appear not to being executed. Request permission to bring to 55% by M4.
DCAE R4 M3 Deliverables for API Freeze Milestone Checklist
Waiver requested, defer coverage goal (55%) for several items until M4:
DMaaP R4 - M1 Milestone Checklist
Condition: All repos unit test coverage > 55% by M3 |
Gerrit- Review
https://gerrit.onap.org/r/#/c/79574/
Modeling request for data model: "waiting on modeling team."
Conditions: Unmet Sonar goal: passes as of 2019-04-09 | CCSDK : Dublin RC1 : Deliverables for RC1 Milestone Checklist | ||||
6 | DCAE |
MS2 Deliverables for Functionality Freeze Milestone Checklist Template
Condition: Followup to document the doc deliverables overtime so that rel_mgmt can support the deliverables
Moving to weekly documentation report... no checklist
Dec 5, 2018 |
DCAE R4 M2 Functionality Freeze Milestone Checklist |
Holmes Release Planning for Dublin
Holmes Deliverables for Planning Milestone Checklist for Dublin
Condition: holmes-common @55% by M3 (TBC) Non-root by 2019-02-28
Holmes Deliverables for API Freeze Milestone Checklist for Dublin
Waiver requested, defer coverage goal (55%) for several items until M4: | DCAE R4 RC0 Milestone Checklist | DCAE R4 RC1 Milestone Checklist 1 Doc Jira Ticket | |||
7 | DMaaP | Mandar Sawant |
Yes, per default |
DMaaP R4 - M1 Release Planning DMaaP R4 - M1 Milestone Checklist |
DMaaP R4 - M2 Functionality Freeze Milestone Checklist |
Provide status on the plan to close the blocker(s).
Integration Dublin M3 Deliverables for API Freeze Milestone Checklist
Need to understand if Integration has sufficient lab capacity for Dublin and a quick to follow maintenance release.
Including POMBA
Logging Dublin Deliverables for Planning Milestone Checklist
Logging Dublin M3 Deliverables for API Freeze Milestone Checklist Template
Checklist complete. No swagger API data
MSB Release Planning for Dublin
MSB Deliverables for Planning Milestone Checklist for Dublin
Condition: All repos unit test coverage > 55% by M3, non-root post Dublin | DMaaP R4 - M3 API Freeze Milestone Checklist Gerrit- Review https://gerrit.onap.org/r/#/c/79574/ Modeling request for data model: "waiting on modeling team." | DMaap R4 - M4 Code Freeze Milestone Checklist Swagger docs by RC2 | DMaaP R4 - RC0 Milestone Checklist | DMaaP R4 - RC1 Milestone Checklist | DMaaP R4 - RC2 Milestone Checklist | DMaaP R4 - Release Sign-Off Milestone Checklist Template |
8 | Documentation | Yes, per default |
MSB Deliverables for API Freeze Milestone Checklist for Dublin
No plans to address the architecture review issue: https://jira.onap.org/browse/ONAPARC-253
Modeling Dublin Deliverables for Planning Milestone Checklist
Modeling Dublin Deliverables for Functionality Freeze Milestone Checklist
Condition: unit test coverage > 55% by M3
Modeling Dublin Deliverables for API Freeze Milestone Checklist
Sonar reporting warning: modeling-toscaparsers-javatoscachecker
Condition: Followup to document the doc deliverables overtime so that rel_mgmt can support the deliverables | Moving to weekly documentation report... no checklist | ||||||||||
9 | External API Framework | Dec 5, 2018 | Planning worksheet M1 Checklist | [ExtAPI] Dublin M3 API Freeze Milestone Checklist | ExtAPI Dublin M4 Code Freeze Milestone Checklist Project needs help getting signed certificates | External API Deliverables for Dublin R4 Release Sign-Off Milestone Checklist | |||||
10 | Holmes |
Dec 3, 2018 |
Holmes Release Planning for Dublin Holmes Deliverables for Planning Milestone Checklist for Dublin | Holmes Deliverables for Functionality Freeze Milestone Checklist for Dublin |
- Conditions: Get all remaining unit test code coverage > 55% by M3
- Plan to design container(s) as non-root: M3 Dublin
Condition: holmes-common @55% by M3 (TBC) Non-root by 2019-02-28 |
Conditional:
Need to add Modeling checklist item
Review gerrit (stale merges)
https://gerrit.onap.org/r/#/c/76324/
https://gerrit.onap.org/r/#/c/75851/
Holmes Deliverables for Code Freeze Milestone Checklist Template for Dublin Moving some stories to next release due to lack of resource. No impact existing func. | Holmes Deliverables for RC0 Milestone for Dublin | Holmes Deliverables for RC1 Milestone for Dublin | Holmes Deliverables for RC2 Milestone for Dublin | Holmes Deliverables for Release Sign-Off Milestone Checklist for Dublin | |
11 | Integration Project |
Yes, per default |
Integration Dublin M2 Deliverables for Functionality Freeze Milestone Checklist |
Provide status on the plan to close the blocker(s). |
Need to update the checklist including Modeling and additional Integration Checklist item
Need to understand if Integration has sufficient lab capacity for Dublin and a quick to follow maintenance release. | Integration Dublin M4 Deliverable for Code Freeze Milestone Checklist | Integration Dublin RC0 Milestone Checklist | Integration Dublin RC1 Milestone Checklist | Integration Dublin RC2 Milestone Checklist | Integration R4 Deliverables for Release Sign-Off Milestone Checklist |
12 | Including POMBA | New PTL: Prudence Au | Nov 16, 2018 | Logging Dublin M1 Release Planning Logging Dublin |
Deliverables for Planning Milestone Checklist |
Logging Dublin M2 Deliverables for Functionality Freeze Milestone Checklist |
-Review gerrit: https://gerrit.onap.org/r/#/c/72189/
https://gerrit.onap.org/r/#/c/80030/
https://gerrit.onap.org/r/#/c/78353/
https://gerrit.onap.org/r/#/c/79268/
https://gerrit.onap.org/r/#/c/79990/
https://gerrit.onap.org/r/#/c/79347/
https://gerrit.onap.org/r/#/c/79989/
https://gerrit.onap.org/r/#/c/79330/
https://gerrit.onap.org/r/#/c/79985/
https://gerrit.onap.org/r/#/c/78873/
https://gerrit.onap.org/r/#/c/77439/
OOF Dublin M1 Release Planning
OOF Dublin M3 Deliverables for API Freeze Milestone Checklist
Checklist complete.
Conditional: Complete unit test coverage goal by M4 for HAS and CMSO
OOM-CSIT BY M4
Usecase-UI Beijing Release Planning
Dublin Release M1 Deliverables for Planning Milestone Checklist
Dublin Release M3 Deliverables for API Freeze Milestone Checklist
Please complete more of the checklist
Policy R4 Dublin M1 Release Planning
Policy R4 Dublin M1 Deliverables for Planning Milestone Checklist Template
Policy R4 Dublin M3 Deliverables for API Freeze Milestone Checklist Template
Portal R4 M1 Deliverables for Planning Milestone Checklist (Dublin Release)
Portal R4 M3 Deliverables for API Freeze Milestone Checklist
Need to update the checklist including Integration & Modeling Checklist items
Missing swagger API info
Not yet met: Unit test code coverage > 55% by M3
Supporting links not provided in checklist
SDC R4 Deliverables for Functionality Freeze Milestone Checklist
Condition: unit test coverage > 55% by M3
SDC R4 Deliverables for API Freeze Milestone Checklist
-Review gerrit:
(stale merge conflicts) -
https://gerrit.onap.org/r/#/c/77504/
-Sonar (52+%) https://sonar.onap.org/dashboard?id=org.onap.sdc.sdc-distribution-client%3Asdc-main-distribution-client%3Amaster
(49+%) https://sonar.onap.org/dashboard?id=org.openecomp.sdc%3Asdc-main%3Amaster
Risks #20/21
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
VF-C Dublin: Deliverables for API Freeze Milestone Checklist Template
Checklist complete. Missing swagger API info
VID R4 M3 Deliverables for API Freeze Milestone Checklist
Changes since M1?
Missing swagger API info28 | VNF SDK | Dec 2, 2018 | VNF SDK Dublin Release Planning (M1) VNF SDK Deliverables for Planning Milestone Checklist Template(M1) | VNFSDK Dublin M2 Deliverables for Functionality Freeze Checklist Conditional: Unit test coverage by M3 |
| VNF SDK Dublin Code Freeze (M4) | Dublin VNFSDK RC0 Checklist - Release Candidate 0 Milestone | Dublin VNFSDK RC1 Checklist - Release Candidate 1 Milestone | Dublin VNFSDK RC2 Checklist - Release Candidate 2 Milestone | ||
29 | VNF Requirements | Nov 16, 2018 | M2 Deliverables for Functionality Freeze Milestone Checklist VNFRQTS | M3 Deliverables for API Freeze Milestone Checklist | M4 Deliverable for Code Freeze Milestone Checklist VNFRQTS | RC0 Milestone Checklist Template - VNFRQTS | RC1 Milestone - Checklist VNFRQTS | RC2 Milestone checklist VNFRQTS | signoff checklist | ||
30 | VNF Validation (VVP) | Nov 16, 2018 | M2 Deliverables for Functionality Freeze Milestone Checklist Template | M3 Deliverables for API Freeze Milestone Checklist Template | M4 Code Freeze Milestone Checklist Template for VVP | RC1 Milestone Checklist -VVP | RC2 Milestone checklist VVP | Signoff |