- M1 Status
- 1/24 - TSC 2019-01-24
- 16 out of 30 projects passed
- 16 out of 30 projects passed
- 1/31 -TSC 2019-01-31
- Project M1 Review. TSC Recommendations: Approved except Doc/Integration (additional information to be provided) - Project Status in Dublin Release
- M1 Scorecard Review: Dublin Release Requirements
- 1/24 - TSC 2019-01-24
- M2 Status -
- 2/14 - Please use the augmented checklist here: Deliverables for Functionality Freeze Milestone Checklist Template
- 2/28 - M2 Project Review. TSC Recommendations: Approved - Project Status in Dublin Release
- M3 Status
- 3/5 - Please use the augmented checklist here: Deliverables for API Freeze Milestone Checklist Template
- 3/14 - TSC Recommendations: Approved - https://wiki.onap.org/display/DW/TSC+2019-03-14
- M3 Project Review- Project Status in Dublin Release
- M3 Scorecard Review: Dublin Release Requirements
- M4 Status
- 4/4 - M4 milestone moved to 4/11 to avoid overlap with ONS
- 4/11- TSC 2019-04-11
- 9 out of 29 projects passed. Documentation is now tracked differently
- M4 scorecard not completed by the Owners
- 4/18 - TSC 2019-04-18
- Dublin M4 Milestone (Code Freeze) was passed on April 18th with gating exceptions that will be reviewed on April 25th 2019
- 4/26
- M4 Gating exceptions have been cleared
- RC0 Status/RC1 Status/RC2 Status
- Sign-off
Dublin Milestones Status
- Not all components were ready - took 1 week to get a phased delivery of components
- 5/30 - No Go - day2day shift
- approved on 6/6 by TSC
- Sign-off
- 6/6 - No Go
- 6/13 - No Go but Excellent progress
- 6/21 - ONAP Dublin release is now certified. Release note to be finalized.
Dublin Milestones Status
Project Name | Project Tech. Lead | M0 Kick-Off/ |
---|
Intention Submission | M1 Planning | M2 Functionality freeze | M3 API Freeze | M4 Code Freeze | RC0 Release Candidate 0 | RC1 Release Candidate 1 | RC2 Release Candidate 2 | Sign-Off Release Delivery |
---|---|---|---|---|---|---|---|---|
1 | A & AI | Dec 3, 2018 | AAI R4 M2 Deliverables for Functionality Freeze Milestone Checklist |
AAI R4 Deliverables for RC1 Milestone Checklist 4 Docs jiras - recently updates | AAI R4 Deliverables for RC2 Milestone Checklist Docs in process | AAI R4 Deliverables for Release Sign-Off Milestone Checklist | ||||||
2 | Application Authorization Framework | Dec 3, 2018 | AAF R4 - M1 Release Plan AAF R4 - M1 Milestone Checklist | AAF R4 - M2 Functionality Freeze Milestone Checklist Condition: aaf-authz @55% by M3 | AAF R4 -M3 Deliverables for API Freeze Milestone Checklist Conditions: Obtain coverage goal by M4 - Failing Sonar coverage: aaf-authz Need to update the checklist including Modeling Checklist item Inprocess Gerrit: https://gerrit.onap.org/r/#/c/78520/ | AAF R4 (Dublin) - RC0 Milestone Checklist TSC waiver for Dublin release sought: Sonar goal miss: aaf-authz |
AAF R4 - RC2 Milestone Checklist TSC Waiver for Sonar granted | AAF R4 Deliverables for Release Sign-Off Milestone Checklist | |||
3 | APPC | Yes, per default |
2 high/highest - no update in last week | ||
4 | CLAMP |
Yes, per default | CLAMP R4 - M1 Release Planning CLAMP R4 - M1 Deliverables for Planning Milestone Checklist | CLAMP R4 - M2 Functionality Freeze Milestone Checklist | CLAMP R4 - M3 Deliverables for API Freeze Milestone Checklist Checklist complete - no swagger API doc | CLAMP R4 - RC0 Milestone Checklist | CLAMP R4 - RC1 Milestone Checklist | CLAMP R4 - RC2 Milestone Checklist | CLAMP R4 - Deliverables for Release Sign-Off Milestone Checklist | ||
5 | Common Controller SDK | Yes, per default | CCSDK : Dublin M2 : Functionality Freeze Milestone Checklist Condition: All repos unit test coverage > 55% by M3 | CCSDK : Dublin M3 : API Freeze Milestone Checklist Conditions: Unmet Sonar goal: passes as of 2019-04-09 |
CCSDK : Dublin RC1 : Deliverables for RC1 Milestone Checklist | |||
6 | DCAE |
Dec 5, 2018 | DCAE R4 M2 Functionality Freeze Milestone Checklist | DCAE R4 M3 Deliverables for API Freeze Milestone Checklist Waiver requested, defer coverage goal (55%) for several items until M4: | DCAE R4 RC0 Milestone Checklist | DCAE R4 RC1 Milestone Checklist 1 Doc Jira Ticket | |||||
7 | DMaaP | Mandar Sawant | Yes, per default | DMaaP R4 - M1 Release Planning DMaaP R4 - M1 Milestone Checklist | DMaaP R4 - M2 Functionality Freeze Milestone Checklist Condition: All repos unit test coverage > 55% by M3, non-root post Dublin | DMaaP R4 - M3 API Freeze Milestone Checklist Gerrit- Review https://gerrit.onap.org/r/#/c/79574/ Modeling request for data model: "waiting on modeling team." | DMaap R4 - M4 Code Freeze Milestone Checklist Swagger docs by RC2 |
Uncertain docs plans
109 Open Dublin Jira tickets
P-W testing status REDModeling Dublin PlanningModeling Dublin
MSB Deliverables for |
RC1 Milestone |
for Dublin |
Modeling Dublin Deliverables for RC2 Milestone Checklist | Modeling Dublin Deliverables for Release Sign-Off Milestone Checklist Template |
15 | Multi VIM/Cloud |
OOM Dublin Release Planning Template
Old version in Dublin - |
-Review gerrit: https://gerrit.onap.org/r/#/c/72189/
https://gerrit.onap.org/r/#/c/80030/
https://gerrit.onap.org/r/#/c/78353/
https://gerrit.onap.org/r/#/c/79268/
https://gerrit.onap.org/r/#/c/79990/
https://gerrit.onap.org/r/#/c/79347/
https://gerrit.onap.org/r/#/c/79989/
https://gerrit.onap.org/r/#/c/79330/
https://gerrit.onap.org/r/#/c/79985/
https://gerrit.onap.org/r/#/c/78873/
https://gerrit.onap.org/r/#/c/77439/
See mitigation efforts for 20+ reviews - 5 are pending manual HC/pods results, one merge conflict
| Dublin-RC2 Milestone Checklist | Dublin-Release Sign-Off | ||||||||
18 | ONAP Operations Manager | Dec 3, 2018 | OOM - Deliverables for Planning Milestone Checklist OOM Dublin Release Planning Template | OOM Dublin - M2 Functionality Freeze Milestone Checklist |
OOM Dublin - RC1 Milestone Deliverables Checklist | ||||||
19 | ONAP Optimization Framework | Dec 3, 2018 | OOF Dublin M1 Deliverables for Planning Milestone Checklist OOF Dublin M1 Release Planning | OOF Dublin M2 Functionality Freeze Milestone Checklist Condition: unit test coverage > 55% by M3 | OOF Dublin M3 Deliverables for API Freeze Milestone Checklist Checklist complete. Conditional: Complete unit test coverage goal by M4 for HAS and CMSO |
OOM-CSIT BY M4 | OOF Dublin RC0 Milestone Checklist |
OOM-CSIT BY M4
OOF Dublin M4 Code Freeze Milestone Checklist
OOF Dublin RC0 Release Deliverables for RC0 Milestone ChecklistJenkins daily verify job failed since April - portal-sdk-master-onap-sdk-verify-java23 | SDN-C | Yes, per default | SDNC : Dublin M2 : Functionality |
Freeze Milestone Checklist | SDNC : Dublin RC0 : Deliverables for RC0 Milestone Checklist Update certificate in RC1 | SDNC : Dublin RC1 : Deliverables for RC1 Milestone Checklist 2 high in Submitted state Certificate is updated |
Update certificate in RC1
24 | Service Design & Creation | Dec 4, 2018 | SDC R4 Deliverables for Functionality Freeze Milestone Checklist Condition: unit test coverage > 55% by M3 | SDC R4 Deliverables for API Freeze Milestone Checklist Condition: Meet 55% coverage goal by M4 Sonar (52+%) https://sonar.onap.org/dashboard?id=org.onap.sdc.sdc-distribution-client%3Asdc-main-distribution-client%3Amaster (49+%) https://sonar.onap.org/dashboard?id=org.openecomp.sdc%3Asdc-main%3Amaster Risks #20 |
/21 | SDC R4 Deliverable for Code Freeze Milestone Checklist | SDC R4 Deliverables for RC0 Milestone Checklist Sonar below goal: sdc master |
Waiver requested: Sonar below goal: sdc master |
Waiver granted: Sonar below goal: sdc master, sdc dublin, sdc-sdc-distribution-client master, dcae-d dt-be-main dublin, dcae-d dt-be-main |