- M1 Status
- 1/24 - TSC 2019-01-24
- 16 out of 30 projects passed
- 16 out of 30 projects passed
- 1/31 -TSC 2019-01-31
- Project M1 Review. TSC Recommendations: Approved except Doc/Integration (additional information to be provided) - Project Status in Dublin Release
- M1 Scorecard Review: Dublin Release Requirements
- 1/24 - TSC 2019-01-24
- M2 Status -
- 2/14 - Please use the augmented checklist here: Deliverables for Functionality Freeze Milestone Checklist Template
- 2/28 - M2 Project Review. TSC Recommendations: Approved - Project Status in Dublin Release
- M3 Status
- 3/5 - Please use the augmented checklist here: Deliverables for API Freeze Milestone Checklist Template
- 3/14 - TSC Recommendations: Approved - https://wiki.onap.org/display/DW/TSC+2019-03-14
- M3 Project Review- Project Status in Dublin Release
- M3 Scorecard Review: Dublin Release Requirements
- M4 Status
- 4/4 - M4 milestone moved to 4/11 to avoid overlap with ONS
- 4/11- TSC 2019-04-11
- 9 out of 29 projects passed. Documentation is now tracked differently
- M4 scorecard not completed by the Owners
- 4/18 - TSC 2019-04-18
- Dublin M4 Milestone (Code Freeze) was passed on April 18th with gating exceptions that will be reviewed on April 25th 2019
- 4/26
- M4 Gating exceptions have been cleared
- RC0 Status
- RC1 Status
- /RC1/RC2 Status
- Not all components were ready - took 1 week to get a phased delivery of components
- 5/30 - No Go - day2day shift
- approved on 6/6 by TSC
- Sign-off
- 6/6 - No Go
- 6/13 - No Go but Excellent progress
- 6/21 - ONAP Dublin release is now certified. Release note to be finalized.
Dublin Milestones Status
Milestone Checklist | |||||||||
6 | DCAE | Dec 5, 2018 | DCAE R4 M2 Functionality Freeze Milestone Checklist | DCAE R4 M3 Deliverables for API Freeze Milestone Checklist Waiver requested, defer coverage goal (55%) for several items until M4: | DCAE R4 RC0 Milestone Checklist | DCAE R4 RC1 Milestone Checklist 1 Doc Jira Ticket |
7 | DMaaP | Mandar Sawant | Yes, per default | DMaaP R4 - M1 Release Planning DMaaP R4 - M1 Milestone Checklist | DMaaP R4 - M2 Functionality Freeze Milestone Checklist Condition: All repos unit test coverage > 55% by M3, non-root post Dublin | DMaaP R4 - M3 API Freeze Milestone Checklist Gerrit- Review https://gerrit.onap.org/r/#/c/79574/ Modeling request for data model: "waiting on modeling team." | DMaap R4 - M4 Code Freeze Milestone Checklist Swagger docs by RC2 | DMaaP R4 - RC0 Milestone Checklist | DMaaP |
Modeling Dublin Deliverables for RC0 Milestone Checklist | Modeling Dublin |
Deliverables for |
RC1 Milestone Checklist | Modeling Dublin Deliverables for |
RC2 Milestone Checklist | Modeling Dublin Deliverables for |
MUSIC Dublin RC2 Milestone Checklist | MUSIC Dublin Deliverables for Release Sign-Off Milestone Checklist | ||||||||||||||||||
17 | ONAP CLI | Dec 3, 2018 | Dublin-M2-Checklist | Need to update the checklist including Modeling and additional Integration Checklist item | Dublin M4 Code Freeze Milestone Checklist | Dublin-RC0 Milestone Checklist | Dublin-RC1 Milestone Checklist Old version in Dublin -
| Dublin-RC2 Milestone Checklist | Dublin-Release Sign-Off | ||||||||||
18 | ONAP Operations Manager | Dec 3, 2018 | OOM - Deliverables for Planning Milestone Checklist OOM Dublin Release Planning Template | OOM Dublin - M2 Functionality Freeze Milestone Checklist | OOM Dublin - M3 API Freeze Milestone Checklist |
OOM Dublin - RC1 Milestone Deliverables Checklist |
19 | ONAP Optimization Framework | Dec 3, 2018 | OOF Dublin M1 Deliverables for Planning Milestone Checklist OOF Dublin M1 Release Planning | OOF Dublin M2 Functionality Freeze Milestone Checklist Condition: unit test coverage > 55% by M3 | OOF Dublin M3 Deliverables for API Freeze Milestone Checklist Checklist complete. Conditional: Complete unit test coverage goal by M4 for HAS and CMSO OOM-CSIT BY M4 | OOF Dublin RC0 Milestone Checklist |
25 | Service Orchestrator | Dec 2, 2018 | SO Dublin RC0: Deliverables for RC0 Milestone Checklist Template |
28 | VNF SDK | Dec 2, 2018 | VNF SDK Dublin Release Planning (M1) VNF SDK Deliverables for Planning Milestone Checklist Template(M1) | VNFSDK Dublin M2 Deliverables for Functionality Freeze Checklist Conditional: Unit test coverage by M3 |
| VNF SDK Dublin Code Freeze (M4) | Dublin VNFSDK RC0 Checklist - Release Candidate 0 Milestone | Dublin VNFSDK RC1 Checklist - Release Candidate 1 Milestone | Dublin VNFSDK RC2 Checklist - Release Candidate 2 Milestone | ||
29 | VNF Requirements | Nov 16, 2018 | M2 Deliverables for Functionality Freeze Milestone Checklist VNFRQTS | M3 Deliverables for API Freeze Milestone Checklist | M4 Deliverable for Code Freeze Milestone Checklist VNFRQTS | RC0 Milestone Checklist Template - VNFRQTS | RC1 Milestone - Checklist VNFRQTS | RC2 Milestone checklist VNFRQTS | signoff checklist | ||
30 | VNF Validation (VVP) | Nov 16, 2018 | M2 Deliverables for Functionality Freeze Milestone Checklist Template | M3 Deliverables for API Freeze Milestone Checklist Template | M4 Code Freeze Milestone Checklist Template for VVP | RC1 Milestone Checklist -VVP | RC2 Milestone checklist VVP | Signoff |