- M1 Status
- 1/24 - TSC 2019-01-24
- 16 out of 30 projects passed
- 16 out of 30 projects passed
- 1/31 -TSC 2019-01-31
- Project M1 Review. TSC Recommendations: Approved except Doc/Integration (additional information to be provided) - Project Status in Dublin Release
- M1 Scorecard Review: Dublin Release Requirements
- 1/24 - TSC 2019-01-24
- M2 Status -
- 2/14 - Please use the augmented checklist here: Deliverables for Functionality Freeze Milestone Checklist Template
- 2/28 - M2 Project Review. TSC Recommendations: Approved - Project Status in Dublin Release
- M3 Status
- 3/5 - Please use the augmented checklist here: Deliverables for API Freeze Milestone Checklist Template
- 3/14 - TSC Recommendations: Approved - https://wiki.onap.org/display/DW/TSC+2019-03-14
- M3 Project Review- Project Status in Dublin Release
- M3 Scorecard Review: Dublin Release Requirements
- M4 Status
- 4/4 - M4 milestone moved to 4/11 to avoid overlap with ONS
- 4/11- TSC 2019-04-11
- 9 out of 29 projects passed. Documentation is now tracked differently
- M4 scorecard not completed by the Owners
- 4/18 - TSC 2019-04-18
- Dublin M4 Milestone (Code Freeze) was passed on April 18th with gating exceptions that will be reviewed on April 25th 2019
- 4/26
- M4 Gating exceptions have been cleared
- RC0/RC1/RC2 Status
- Not all components were ready - took 1 week to get a phased delivery of components
- RC1 Status
- RC2 Status
- 5/30 - No Go - day2day shift
- approved on 6/6 by TSC
- Sign-off
- 6/6 - No Go
- 6/13 - No Go but Excellent progress
- 6/21 - ONAP Dublin release is now certified. Release note to be finalized.
Dublin Milestones Status
Open high
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Remaining Defect(s)
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
CLAMP R4 - M1 Deliverables for Planning Milestone Checklist
CLAMP R4 - M3 Deliverables for API Freeze Milestone Checklist
Checklist complete - no swagger API doc
CLAMP R4 - M4 Deliverable for Code Freeze Milestone Checklist
CLAMP R4 - RC2 Milestone Checklist
CCSDK : Dublin M2 : Functionality Freeze Milestone Checklist
Condition: All repos unit test coverage > 55% by M3 |
, non-root post Dublin |
Conditions: Unmet Sonar goal: passes as of 2019-04-09
CCSDK : Dublin M4 : Code Freeze Milestone Checklist
CCSDK : Dublin RC0 : Deliverables for RC0 Milestone Checklist
Open high
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Remaining Defect(s)
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
DCAE R4 M3 Deliverables for API Freeze Milestone Checklist
Waiver requested, defer coverage goal (55%) for several items until M4:
DCAE R4 M4 Code Freeze Milestone Checklist
DCAE R4 RC0 Milestone Checklist
DCAE R4 RC1 Milestone Checklist
1 Doc Jira Ticket
DCAE R4 RC2 Milestone Checklist
DMaaP R4 - M1 Milestone Checklist
DMaaP R4 - M3 API Freeze Milestone Checklist
Gerrit- Review
https://gerrit.onap.org/r/#/c/79574/
Modeling request for data model: "waiting on modeling team."
DMaap R4 - M4 Code Freeze Milestone Checklist
Swagger docs by RC2
DMaaP R4 - RC0 Milestone Checklist
DMaaP R4 - RC2 Milestone Checklist
MS2 Deliverables for Functionality Freeze Milestone Checklist Template
Condition: Followup to document the doc deliverables overtime so that rel_mgmt can support the deliverables
Moving to weekly documentation report... no checklist
M1 Checklist
[ExtAPI] Dublin M3 API Freeze Milestone Checklist
ExtAPI Dublin M4 Code Freeze Milestone Checklist
Project needs help getting signed certificates
Holmes Release Planning for Dublin
Holmes Deliverables for Planning Milestone Checklist for Dublin
Condition: holmes-common @55% by M3 (TBC) Non-root by 2019-02-28
Moving some stories to next release due to lack of resource. No impact existing func.
MSB Deliverables for RC1 |
Milestone for Dublin |
MSB Deliverables for |
RC2 Milestone for Dublin |
MSB Deliverables for |
Release Sign-Off Milestone Checklist for Dublin |
14 |
Modeling |
Dec 3, 2018 | Modeling Dublin Planning Modeling Dublin |
Deliverables for Planning Milestone Checklist |
Condition: unit test coverage > 55% by M3 |
Need to understand if Integration has sufficient lab capacity for Dublin and a quick to follow maintenance release.
Condition: meet 55% coverage goal by M4 Sonar reporting warning: modeling-toscaparsers-javatoscachecker |
Modeling Dublin Deliverables for RC1 Milestone Checklist |
Logging Dublin
Modeling Dublin Deliverables for RC2 Milestone Checklist |
Including POMBA
New PTL: Prudence Au
Modeling Dublin Deliverables for Release Sign-Off Milestone Checklist Template | ||||
15 | Multi VIM/Cloud | Dec 3, 2018 |
Modeling Dublin Deliverables for Functionality Freeze Milestone Checklist
Logging Dublin M3 Deliverables for API Freeze Milestone Checklist Template
Checklist complete. No swagger API data
Logging Dublin M4 Deliverable for Code Freeze Milestone Checklist Template
Logging Dublin RC0 Deliverables for RC0 Milestone Checklist
Logging Dublin RC1 Deliverables for RC1 Milestone Checklist
Logging Dublin RC2 Deliverables for RC2 Milestone Checklist
Documentation to be finalized
MSB Release Planning for Dublin
MSB Deliverables for Planning Milestone Checklist for Dublin
MSB Deliverables for API Freeze Milestone Checklist for Dublin
MSB Deliverables for Code Freeze Milestone Checklist for Dublin
Modeling Dublin Deliverables for Planning Milestone Checklist
| MultiCloud R4 Deliverables for API Freeze Milestone Checklist Conditional: Need to add Modeling checklist item Review gerrit (stale merges) | MultiCloud R4 Deliverable for Code Freeze Milestone Checklist | MultiCloud Deliverables for RC0 Milestone Checklist TSC waiver for Dublin release sought: Sonar multicloud-azure below target | MultiCloud R4 Deliverables for RC1 Milestone Checklist TSC waiver for Dublin release sought: Sonar multicloud-azure below target | ||
16 | MUSIC | Yes, per default | MUSIC Dublin M1 Deliverables for Planning Milestone Checklist | MUSIC Dublin M2 Deliverables for Functionality Freeze Milestone Checklist Template |
Condition: unit test coverage > 55% by M3. |
MUSIC Dublin M3 Deliverables for API Freeze Milestone Checklist |
Condition: meet 55% coverage goal by M4
Sonar reporting warning: modeling-toscaparsers-javatoscachecker
MUSIC Dublin M4 Code Freeze Milestone Checklist |
https://wiki.onap.org/display/DW/MUSIC+Dublin+RC1+Milestone+Checklist | MUSIC Dublin RC2 Milestone Checklist | MUSIC Dublin Deliverables for Release Sign-Off Milestone Checklist | |
17 | ONAP CLI |
MUSIC Dublin M1 Deliverables for Planning Milestone Checklist
Dec 3, 2018 |
Deliverables for Functionality Freeze Milestone Checklist
- Conditions: Get all remaining unit test code coverage > 55% by M3
- Plan to design container(s) as non-root: M3 Dublin
MultiCloud R4 Deliverables for API Freeze Milestone Checklist
Conditional:
Need to add Modeling checklist item
Review gerrit (stale merges)
MultiCloud R4 Deliverable for Code Freeze Milestone Checklist
MultiCloud Deliverables for RC0 Milestone Checklist
TSC waiver for Dublin release sought: Sonar multicloud-azure below target
MultiCloud R4 Deliverables for RC1 Milestone Checklist
TSC waiver for Dublin release sought: Sonar multicloud-azure below target
MultiCloud R4 Deliverables for RC2 Milestone Checklist
TSC Waiver for Sonar granted
Remaining Defect(s)
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Dublin-M2-Checklist | Need to update the checklist including Modeling and additional Integration Checklist item | Dublin M4 Code Freeze Milestone Checklist | Dublin-RC0 Milestone Checklist | Dublin-RC1 Milestone Checklist Old version in Dublin -
| Dublin-RC2 Milestone Checklist | Dublin-Release Sign-Off | |||||||||
18 | ONAP Operations Manager | Dec 3, 2018 | OOM - Deliverables for Planning Milestone Checklist OOM Dublin Release Planning Template | OOM Dublin - M2 Functionality Freeze Milestone Checklist | OOM Dublin - M3 API Freeze Milestone Checklist | OOM Dublin - RC0 Milestone Deliverables Checklist | OOM Dublin - RC1 Milestone Deliverables Checklist | ||||||||
19 | ONAP Optimization Framework | Dec 3, 2018 | OOF Dublin M1 Deliverables for Planning Milestone Checklist OOF Dublin M1 Release Planning | OOF Dublin M2 Functionality Freeze Milestone Checklist |
Condition: unit test coverage > 55% by M3 |
OOF Dublin M3 Deliverables for API Freeze Milestone Checklist |
Checklist complete. Conditional: Complete unit test coverage goal by M4 for HAS and CMSO OOM-CSIT BY M4 |
OOF Dublin RC0 Milestone Checklist |
https://wiki.onap.org/display/DW/MUSIC+Dublin+RC1+Milestone+Checklist
Below Sonar goal (no waiver): MUSIC
Doc completion risk - focus on release notes & install docs | |||||||
20 | ONAP Usecase UI | Yes, per default | Usecase-UI Beijing Release Planning Dublin Release M1 Deliverables for Planning Milestone Checklist | UUI Dublin M2 Functionality Freeze Milestone Checklist | Dublin Release M3 Deliverables for API Freeze Milestone Checklist |
Need to update the checklist including Modeling and additional Integration Checklist item
Dublin M4 Code Freeze Milestone Checklist |
Release Deliverables for RC0 Milestone Checklist |
Old version in Dublin -
Jira | ||||||
---|---|---|---|---|---|---|
|
2x Doc Jira Tickets | ||||
21 | Policy Framework | Dec 3, 2018 |
OOM Dublin Release Planning
Policy R4 Dublin |
M2 Deliverables for Functionality Freeze Milestone Checklist Template |
OOM Dublin - RC1 Milestone Deliverables Checklist
OOM Dublin - RC2 Milestone Deliverables Checklist
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Doc completion risk
P-W testing | Policy R4 Dublin RC1 Deliverables for RC1 Milestone Checklist Template 1xDoc Jira Ticket | ||||||||||
22 | Portal Platform | Nov 30, 2018 | Portal R4 M1 Release Planning (Dublin Release) Portal R4 M1 Deliverables for Planning Milestone Checklist (Dublin Release) | Portal R4 M2 Deliverables for Functionality Freeze Milestone Checklist Dependency on OOM for non-root testing; other dependencies articulated in the risks | Portal R4 M3 Deliverables for API Freeze Milestone Checklist Need to update the checklist including Integration & Modeling Checklist items | Portal R4 M4 for Code Freeze Milestone Checklist | Portal R4 RC0 Milestone Checklist |
Remaining Defect(s)
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
OOF Dublin M1 Release Planning
OOF Dublin M3 Deliverables for API Freeze Milestone Checklist
Checklist complete.
Conditional: Complete unit test coverage goal by M4 for HAS and CMSO
OOM-CSIT BY M4
OOF Dublin M4 Code Freeze Milestone Checklist
OOF Dublin RC1 Milestone Checklist
OOF Dublin RC2 Milestone Checklist
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Doc completion risk
Remaining Defect(s)
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Usecase-UI Beijing Release Planning
Dublin Release M1 Deliverables for Planning Milestone Checklist
Dublin Release M3 Deliverables for API Freeze Milestone Checklist
UUI Dublin M4 Code Freeze Milestone Checklist
Dublin Release Deliverables for RC0 Milestone Checklist
Dublin Release Deliverables for RC1 Milestone Checklist
2x Doc Jira Tickets
Policy R4 Dublin M1 Release Planning
Policy R4 Dublin M1 Deliverables for Planning Milestone Checklist Template
Policy R4 Dublin M3 Deliverables for API Freeze Milestone Checklist Template
Policy R4 Dublin M4 Deliverable for Code Freeze Milestone Checklist Template
Policy R4 Dublin RC0 Deliverables for RC0 Milestone Checklist Template
P-W testing
Policy R4 Dublin RC1 Deliverables for RC1 Milestone Checklist Template
1xDoc Jira Ticket
Policy R4 Dublin RC2 Deliverables for RC2 Milestone Checklist Template
Docs still under development
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Portal R4 M1 Deliverables for Planning Milestone Checklist (Dublin Release)
Portal R4 M3 Deliverables for API Freeze Milestone Checklist
Need to update the checklist including Integration & Modeling Checklist items
Portal R4 M4 for Code Freeze Milestone Checklist
Portal R4 RC0 Milestone Checklist
Portal R4 RC1 Milestone Checklist
Portal R4 RC2 Dublin Milestone Checklist
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Remaining Defect(s)
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
SDNC : Dublin M4: Deliverable for Code Freeze Milestone Checklist
SDNC : Dublin RC0 : Deliverables for RC0 Milestone Checklist
Update certificate in RC1
SDNC : Dublin RC1 : Deliverables for RC1 Milestone Checklist
2 high in Submitted state
Certificate is updated
SDNC : Dublin RC2 : Deliverables for RC2 Milestone Checklist
Remaining Defect(s)
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
SDC R4 Deliverables for Functionality Freeze Milestone Checklist
Condition: unit test coverage > 55% by M3
SDC R4 Deliverables for API Freeze Milestone Checklist
Condition: Meet 55% coverage goal by M4
Sonar (52+%) https://sonar.onap.org/dashboard?id=org.onap.sdc.sdc-distribution-client%3Asdc-main-distribution-client%3Amaster
(49+%) https://sonar.onap.org/dashboard?id=org.openecomp.sdc%3Asdc-main%3Amaster
Risks #20/21
SDC R4 Deliverable for Code Freeze Milestone Checklist
SDC R4 Deliverables for RC0 Milestone Checklist
Sonar below goal: sdc master
SDC R4 Deliverables for RC1 Milestone Checklist
Waiver requested: Sonar below goal: sdc master
SDC R4 Deliverables for RC2 Milestone Checklist
Waiver granted: Sonar below goal: sdc master, sdc dublin, sdc-sdc-distribution-client master, dcae-d dt-be-main dublin, dcae-d dt-be-main master
SO Dublin M4 Code Freeze Milestone Checklist
SO Dublin RC0: Deliverables for RC0 Milestone Checklist Template
SO Dublin RC1 Milestone Checklist Template
4 high/highest defects
SO Dublin - RC2 Milestone Checklist
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Remaining Defect(s)
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Remaining Defect(s)
28 | VNF SDK | Dec 2, 2018 | VNF SDK Dublin Release Planning (M1) VNF SDK Deliverables for Planning Milestone Checklist Template(M1) | VNFSDK Dublin M2 Deliverables for Functionality Freeze Checklist Conditional: Unit test coverage by M3 |
| VNF SDK Dublin Code Freeze (M4) | Dublin VNFSDK RC0 Checklist - Release Candidate 0 Milestone | Dublin VNFSDK RC1 Checklist - Release Candidate 1 Milestone | Dublin VNFSDK RC2 Checklist - Release Candidate 2 Milestone | ||
29 | VNF Requirements | Nov 16, 2018 | M2 Deliverables for Functionality Freeze Milestone Checklist VNFRQTS | M3 Deliverables for API Freeze Milestone Checklist | M4 Deliverable for Code Freeze Milestone Checklist VNFRQTS | RC0 Milestone Checklist Template - VNFRQTS | RC1 Milestone - Checklist VNFRQTS | RC2 Milestone checklist VNFRQTS | signoff checklist | ||
30 | VNF Validation (VVP) | Nov 16, 2018 | M2 Deliverables for Functionality Freeze Milestone Checklist Template | M3 Deliverables for API Freeze Milestone Checklist Template | M4 Code Freeze Milestone Checklist Template for VVP | RC1 Milestone Checklist -VVP | RC2 Milestone checklist VVP | Signoff |