The page is intended to summarize all the requirements for Frankfurt Release.
These requirements have been prioritized by the TSC to realistically fit within the Frankfurt Release Timeline.
The Release Scope should be finalized during the M1 Release Planning milestone on November 7th, 2019
TSC Prioritization (Ranking)
- RANK #0 – Special GO - quick wins, fully covered by involved companies
- RANK #1 – TSC Must Have – Mandatory for the release
- RANK #2 – Continuity - Items continued from previous releases
- RANK #3 – PTL Go – items that PTLs is OK to include since team has bandwidth
- RANK #4 – NO GO – items not approved for various reasons
Requirements Milestones Summary
See also Documenting Release Requirements in JIRA
Epic Link | Fix For Versions (all) | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Frankfurt Release | Guilin Release | Honolulu Release | Istanbul Release | Jakarta Release | Kohn Release | London Release | Montreal Release | New Delhi Release | Istanbul Maintenance Release 1 | Unscheduled | T: | |
5G / OOF SON Enhancement | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3 |
5G / ORAN & 3GPP Standards Harmonization | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3 |
5G OOF SON use case requirements for Guilin release | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 |
5G Service Modeling in R8 | 0 | 0 | 15 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 2 | 17 |
5G SON use case enhancements for Istanbul release | 0 | 0 | 0 | 13 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 13 |
5G SON use case enhancements for Jakarta release | 0 | 0 | 0 | 0 | 14 | 0 | 0 | 0 | 0 | 0 | 0 | 14 |
5G SON use case enhancements for Kohn release | 0 | 0 | 0 | 0 | 0 | 14 | 0 | 0 | 0 | 0 | 0 | 14 |
5G SON use case enhancements for London release | 0 | 0 | 0 | 0 | 0 | 0 | 14 | 0 | 0 | 0 | 2 | 16 |
5G SON Usecase R8 | 0 | 0 | 16 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 2 | 18 |
A1 Adapter Extension & A1 Policy Management | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 |
A1 Policy Functions Extension - Istanbul | 0 | 0 | 0 | 12 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 12 |
A1 Policy Functions Extension - Jakarta | 0 | 0 | 0 | 0 | 12 | 0 | 0 | 0 | 0 | 0 | 0 | 12 |
A1 Policy Functions Extension - Kohn | 0 | 0 | 1 | 1 | 1 | 13 | 0 | 0 | 0 | 1 | 0 | 13 |
A1 Policy Functions Extension - London | 0 | 0 | 0 | 0 | 0 | 0 | 13 | 0 | 0 | 0 | 0 | 13 |
Add VSP Compliance and Verification Check feature Phase 2 | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3 |
Akraino Distributed Analytics use case | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3 |
All Control Loop Policy Models should be TOSCA Compliant | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3 |
APPC Ansible automation with VNF-C LCM support | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3 |
Architecture - modelling alignment | 7 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 7 |
ASD onboarding package IM / DM | 0 | 0 | 0 | 0 | 12 | 0 | 0 | 0 | 0 | 0 | 0 | 12 |
Bulk PM / PM Data Control Extension | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 |
Bulk PM / PM Data Control Improvements | 0 | 0 | 11 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 11 |
Bulk PM / PM Data Control Improvements | 0 | 0 | 0 | 12 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 12 |
Bulk PM / PM Data Control Improvements | 0 | 0 | 0 | 0 | 13 | 0 | 0 | 0 | 0 | 0 | 0 | 13 |
CCVPN-E-LINE Service over OTN NNI | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3 |
Total Unique Issues: | 196 | 22 | 248 | 184 | 189 | 107 | 187 | 1 | 1 | 1 | 84 | 1216 |
Use Cases
Release 6 (Frankfurt) proposed use cases and functional requirements
M1 Scorecard:
- Green: Use Case will be fully implemented and tested
- Yellow: Use Case will be partially implemented. It is possible to identify capabilities for this use case that can be tested (phasing approach).
- Red: Use Case can not be partially delivered, min. requirements can not be met in order to define a testing strategy.
Architecture:
- Pink - NO GO
- Purple - GO
- Green - Considered OK not requiring architecture review
- Black - Architecture not yet performed
Use Case | JIRA link (REQ) One issue per requirement. | Owner(s) | TSC Ranking | M1 Scorecard | TSC M1 Approval | Link(s) to HLD/LLD if any | Dependency (from/to) another project(s) | T-Shirt Size | Project's Impact: Test Only (TO), Code (C) | Committed (C)/ Partially Committed (P) or not (N) per impacted project | If Partially or not Committed, what are gaps/ project (people/FTEs; HLD/LLD; etc) | Integration Lead | Company Engagement | Notes |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Third Party Operational Domain Manager | RANK #0 | Third-party Operational Domain Manager | S | SDC (C) SO (TO) AAI (TO) | Changes being done in local setup SDC: Committed based on Telstra contribution [TSC]: What does it mean? No SDC contribution to the ONAP Community. [Atif]:Changes were temporarily done locally, when the ElAlto branch wasn't cut and we couldn't commit to master | Will commit after review discussion with SDC PTL [TSC]:What's the status? PTL OK? [Atif] PTL is OK. Code commit started. | Telstra | Complete company commitment for delivery of Frankfurt Scope for this use case | ||||||
Service Resolver Features | rene.robert@orange.com | RANK #4 | Service Resolver | SDC (C), SO (C), AAI (TO) | No SO decision | MISSING INFO | MISSING INFO | Orange | ||||||
CMPv2 CA Plugin for AAF | RANK #3 | XL - | AAF (C) Integration (C) | AAF: (C) Integration:(C) | See notes | AT&T Ericsson Nokia | Note: Nokia and Ericsson volunteered to work this. As PTL, I approved the path forward (create Client, build plugin, etc) but was unable to create actual REQ. Please consider this working item until them. (update : - REQ-140Getting issue details... STATUS created, at the moment we do not expect multiple release impacts but it has to be further checked) ALSO... This MAY be a multi-release effort, which will not affect normal Operations in anyway, if CMPv2 isn't completed within Frankfurt. | |||||||
CCVPN: E-LINE Service over OTN NNI | LIN MENG | RANK #2 | XL (Multiple releases) | TO: SO; C: U-UI, A&AI, OOF, SDN-C | U-UI committed by ChinaMobile; A&AI committed by Huawei; OOF committed by Huawei; SDN-C committed by Huawei | China Mobile, Huawei | ||||||||
End to End Layer 1 Service Management. Modeling the Optical Service | RANK #3 | Multi-domain Optical Network Services | CCVPN use-case alignment | XL (Multiple releases) | TO: SDC, ExtAPI C: UUI, SO, A&AI, SDN-C | SO - C A&AI - C SDN-C - C UUI - C SDC - TO ExtAPI - TO TSC: Which company will develop this? Code will be committed by Fujitsu | Have gained PTL agreement & JIRA epics have been created under SO, SDNC, A&AI | Xin Miao | AT&T Orange Fujitsu | Working with CCVPN team to align towards common modelling for OTN | ||||
Deploying Distributed External functions | RANK #0 | Depends on development progress of Multi-Cloud K8S work. | XL (Multiple releases) | TO: Multi-Cloud | Intel will contribute to this. There is no code development and it is for testing the work being done in MC project. | Intel, Aarna, TM |
T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team
- XS - <4 Man/Weeks;
- S - ~6 Man/Weeks;
- M - ~8 Man/Weeks;
- L - ~12 Man/Weeks;
- XL - > 12 Man/Weeks.
Requirements
M1 Scorecard:
- Green: The requirement will be fully implemented and tested
- Yellow: The requirement will be partially implemented. It is possible to identify capabilities for this functional requirement that can be tested (phasing approach).
- Red: The requirement can not be partially delivered, min. requirements can not be met in order to define a testing strategy
Architecture:
- Pink - NO GO
- Purple - GO
- Green- Considered OK not requiring architecture review
- Black - Architecture not yet performed
Requirement | JIRA link (REQ) One issue per requirement. | Owner | TSC Ranking | M1 Scorecard | TSC M1 Approval | Link(s) to HLD/LLD if any | Dependency (from/to) another project(s) | T-Shirt Size (XS, S, M, L, XL) | Project's Impact: Test Only (TO), Code (C), Documentation Only (DO) | Committed (C)/Partially Committed (P) or not (N) per Impacted projects | If Partially or not Committed, what are gaps/ project (people/FTEs; HLD/LLD; etc) | Integration Lead | Company Engagement | Notes |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Self Serve Control Loops | RANK #2 | Self Serve Control Loops v2 | CLAMP | XL | CLAMP - C DCAE - C POLICY - C | CLAMP - C DCAE - C POLICY - C committed by AT&T | AT&T Ericsson | |||||||
All Control Loop Policy Models should be TOSCA Compliant Operational, Guard Policies | RANK #2 | TOSCA Compliant Policy Types | SDC | M | CLAMP - C POLICY - C | CLAMP - C POLICY - C committed by AT&T & Ericsson | AT&T Ericsson | |||||||
Policy Update Notifications | RANK #2 | Policy Update Notifications | S | DCAE - C POLICY - C | DCAE - C POLICY - C committed by AT&T | AT&T Wipro | DCAE: Commitment based on Wipro | |||||||
CLAMP Deployment of Policies to PDP Groups | RANK #3 | CLAMP Deployment of Policies to PDP Groups | M | CLAMP - C POLICY- C | CLAMP - C POLICY - C committed by AT&T | AT&T Ericsson | ||||||||
Integration of CDS as Actor in Control Loops | RANK #3 | CDS actor support in Policy | L | CLAMP - C POLICY - C CDS - C Integration - C | CLAMP - C POLICY - C CDS - C Integration - C | Partial commitment from Bell Canada to support Policy+CDS integration. Partial commitment from Huawei to support | AT&T Bell Canada Ericsson Huawei Orange | |||||||
Control Loop Tutorial Documentation | RANK #3 | CLAMP, DCAE, POLICY | M | Documentation - DO Integration - TO | DOC - C POLICY - C DCAE - C CLAMP - C TSC: Which companies will cover this - per component? | Morgan Richomme | Bell Canada, AT&T, Orange | |||||||
Component Upgrades to new Policy Lifecycle API | RANK #2 ------------ What's the side effect if no company will develop SDNC, SO? Can still use legacy API - but those components will be removed in the G Release. So they must upgrade in the G-release. | M | SO - C SDNC - C OOF - C POLICY - C | POLICY - C (AT&T & Intel) OOF - C (Intel) Need commitments from SDNC and SO | AT&T, Intel | |||||||||
Modeling: Enhanced Nested and Shared Service Information Model - 5G / E2E Network Slicing modeling | TSC: Replaced by new E2E Network Slicing Scope No commitment to cover ExtAPI | NETWORK SLICING PoC in R6 Frankfurt (Obsolete) | L | SDC-C AAI-C External API | Company commitment per component SDC - C (Amdocs) AAI - C (Amdocs) | *Note: Not sure integration lead is needed for modeling | CMCC Amdocs AT&T Wiprc Huawei | |||||||
5G / OOF SON Enhancement | RANK #3 | OOF (SON) in R5 El Alto, OOF (SON) in R6 Frankfurt | L | POLICY - C OOF - C DCAE - C SDN-C - C Runtime DB - C Integration (Demo VNFs) - C | POLICY - C OOF - C DCAE - C SDN-C - C Runtime DB - C Integration (Demo VNFs) - C Policy, DCAE, Integration - Wipro commits OOF, Policy - AT&T commits SDN-C, Runtime DB - IBM commits | AT&T Wipro IBM | RAN-Simulator will be submitted as part of Demo VNFs repository | |||||||
5G / Run-time Data Persistency (RunTime Config DB) and VES Model relations, VES CM model (CM Notify). | RANK #3 | 5G CONFIGURATION (RunTime DB) | CM Notify VES Event (defined by Harmonized U/C) this U/C will actually use the CMNotify VES event and DCAE development to use the Event. | L | A&AI - TO SDC - TO Controller - C RunTime DB (new component) - C DCAE - C | A&AI - C SDC - C Controller - C RunTime DB (new component) - C DCAE - C Controller, RunTimeDB, - IBM commits SDC (TO) - AmDocs will commit DCAE - Nokia commits A&AI Testing - IBM will do testing. | Sandeep Shah | Nokia AT&T | Will be a new component, presented at Architecture S/C. | |||||
Modeling: GeoLocation Model (and standards harmonization) | Modeling work only | RANK #0 | PNF PLUG and PLAY in R6 Frankfurt | AAI | M | N/A | N/A | N/A | Ericsson Nokia | |||||
PNF / PNF Software Upgrade using direct Netconf/Yang interface with PNF | RANK #2 | PNF software upgrade in R6 Frankfurt | XL | SDC: C SO: C CDS: C VID: C Integration: C/DO VNFRQTS: DO | SDC: (C) SO: (C) CDS: (C) VID: (C) Integration: (C) Integration, SDC, SO, VID, CDS, and VNFRQTS are committed by Ericsson. SO is committed by Huawei | Ericsson Huawei | ||||||||
PNF / Enable Schema Update once PNF software is updated | RANK #2 | PNF software upgrade in R6 Frankfurt | M | SDC: C Integration: C VNFRQTS: DO | SDC: C Integration: C SDC, Integration and VNFRQTS are committed by Ericsson | Ericsson | ||||||||
LCM API Evolution | TSC: Please merge with REQ-84 | https://wiki.onap.org/download/attachments/50202249/2019-07-02%20ONAP_R6_Controller_Evolution_LCM_APIs.pptx?api=v2 | N/A | Development in R6 will be part of REQ-84 | N/A | N/A | Ericsson | Main goals:
| ||||||
PNF / Enhancement on PNF Software Upgrade with EM with Ansible | RANK #2 | PNF software upgrade in R6 Frankfurt | LCM API Evolution | M | SO: C CCSDK: C Integration:C | SO: C CCSDK: C Integration:C Huawei commitment to SO,CCSDK,Integration | Huawei | |||||||
PNF / PNF Software Upgrade with EM with Netconf | yaoguang wang | RANK #2 | PNF software upgrade in R6 Frankfurt | PNF Software Upgrade using direct Netconf/Yang interface with PNF | M | SO: C CDS: C Integration:C | SO: C CDS: C Integration:C Huawei commitment to SO, CDS, Integration | Enbo Wang | Huawei | |||||
Modeling: 5G / ORAN & 3GPP Standards Harmonization | RANK #0 | MOBILITY STANDARDS HARMONIZATION WITH ONAP | M | SDNC: C DCAE: C | SDN-C: C DCAE: C SDN-C (A1 adaptor) committed by Ericsson & IBM DCAE committed by Nokia | Sandeep Shah (A1, O1) | AT&T Nokia Ericsson | DCAE: Impact for adopting new VES domain; Committed based on Nokia support. | ||||||
5G / License Management | RANK #0 ANSWER: There is no S/W development in R6. Company Commitment is commitment to work on Modeling & Architecture work for R6. Most of this U/C will be modeling development. | LICENSING MANAGEMENT | SDC | M | Modeling: DO VNFRQTS, after UCs agreed: DO
( *) No code or test impact expected in R6 as an outcome of the proposed UCs | Nokia and Ericsson commit to: | N/A | AT&T Nokia Ericsson Orange | No development. Activity driven by Nokia and Ericsson is Use Case development. The UCs and modeling are done in synch. | |||||
5G / Bulk PM / PM Control | RANK #2 | 5G Bulk PM in Frankfurt/R6 | CLAMP/Policy/CDS (REQ-33) | XL | SO: C DCAE: C Integration: C | SO: C DCAE: C Integration: C SO, DCAE and Integration committed by Ericsson | user-3784d | Ericsson | DCAE: Committed based on Ericsson support | |||||
5G / Bulk PM / Secure Communication between xNFs and ONAP | Pawel Baniewski | RANK #2 | 5G Bulk PM in Frankfurt/R6 | AAF (REQ-140) | S | DCAE: C | DCAE: C Nokia Commits to DCAE: C Development | Nokia | DCAE: Committed based on Nokia support | |||||
5G / PM dictionary | RANK #2 | FM META DATA & PM DICTIONARY in R6 Frankfurt | S | SDC: Update GAB Config File (no S/W update) DCAE: DOC DCAE: VES Event Reg Spec | SDC - C DCAE - C Nokia Commits to SDC, DCAE - C | Damian Nowak | AT&T Ericsson Nokia | DCAE: No code impact on VES reg yaml updates | ||||||
5G / 5G NRM Network Resource Model (Configuration Mgmt) | yaoguang wang | RANK #3 | 5G Network Resource Model (NRM) Configuration in R6 Frankfurt | M | SO: C CDS: C Modeling: DOC Integration: C | SO: C CDS: C Modeling: P Integration: C Huawei commitment to SO, CDS, Integration | yaoguang wang | Huawei | ||||||
5G / 5G Service Modeling: Modeling (exploratory) work for creating a 5G Service | Modeling Work Only (No REQ) | RANK #0 ANSWER: It is just modeling in R6. AT&T and Nokia commits to working with Modeling S/C work. | 5G RAN SERVICE MODELING & DEFINITION in R6 Frankfurt | N/A | Modeling: C | Modeling: C | N/A (No integration or testing impact) | Nokia AT&T | Modeling work only | |||||
PNF / Plug and Play | Benjamin Cheung | RANK #2 | PNF PLUG and PLAY in R6 Frankfurt | AAF (REQ-140) | M | DCAE: C SO: C VID: C | DCAE: C SO: C VID: C NOKIA Committed to DCAE, SO and VID Development | Nokia | DCAE: SDK Dmaap lib refactor; committed based on Nokia support | |||||
PNF / Configuration with NETCONF/ Secure Communication between xNFs and ONAP | RANK #3 | Configuration with NETCONF in Frankfurt/R6 | AAF (REQ-140) | M | SDNC: C Integration: C | SDNC: C Integration: C SDNC and Integration committed by Ericsson | Mariusz Sobucki | Ericsson | ||||||
PNF / PNF pre-onboarding onboarding | RANK #2 | PNF/VNF PREONBOARDING / ONBOARDING in R6 Frankfurt | S | VNFSDK: C Integration: TO | VNFSDK: C Integration: C Nokia Commits to VNFSDK and Integration - C | Nokia Ericsson | Integration will only be for VNF-SDK work, there is not full E2E POB/OB integration in R6. | |||||||
Modeling: Runtime instance model based on A&AI reverse engineering | RANK #0 | Reverse-engineering AAI data model to Papyrus information model | AAI | S | AT&T commits to the bug fix | N/A, producing a model file only, not a use case | AT&T Ericsson Huawei Orange | |||||||
Modeling: documentation of policy and allotted resource model | Modeling Work Only | Kevin Scaggs | RANK #0 | Policy SDC | M | Modeling only. No new implementation requirements | AT&T | |||||||
Scaling Extensions | RANK #2 | Scaling Use Case (Frankfurt) | APPC CCSDK/CDS SO | S-M | APPC - C CCSDK - TO SO - C | APPC - C CCSDK - C SO -C (Actor selection of CDS and APPC) APPC - Nokia Shanghai CCSDK - Tech Mahindra SO - Tech Mahindra | Marco Platania | AT&T Nokia/Shanghai Nokia/Poland Tech Mahindra Orange | ||||||
APPC Ansible automation with VNF-C LCM support / CHM | RANK #2 | Change Management Frankfurt Extensions | APPC Integration | S | APPC: C Integration: C | APPC and Integration Commited by Orange | @Lukasz Rajewski | Orange AT&T | ||||||
vFW Traffic Distribution with Software Upgrade / CHM | RANK #2 | Change Management Frankfurt Extensions | Integration | XS | Integration: C | Integration Commited by Orange | @Lukasz Rajewski | Orange AT&T | ||||||
Portal Security Enhancements | Manoop Talasila | RANK #1 | MUSIC | L | Policy: C VID: C SDC: C | Portal partially committed by AT&T, IBM | Partially committed by Samsung (to support OJSI tickets) | Dominik Mizyn (for OJSI tickets) | AT&T Samsung IBM | |||||
Portal Technology Stack Upgrade and New reporting features | Manoop Talasila | RANK #3 | XL | Policy: C VID: C SDC: C | Portal committed by AT&T, IBM | Partially committed by Samsung (to support Springboot upgrade on "portal" repo) Partially committed by IBM for test automation GAPS: No resources to support portal/sdk repo for Springboot upgrade. | Sireesh Chintamani (Overall Integration Lead) Sunder Tattavarada (for Angular upgrade) Dominik Mizyn (for Springboot upgrade on "portal" repo) Leimeng Shi (for reporting feature) | AT&T Samsung IBM | ||||||
ETSI Alignment Support | RANK #2 | ETSI Alignment Support | XL | SDC: C SO: C SOL003 Adapter: C SOL005 Adapter: C ETSI Catalog Mgr: C SOL002 Adapter: C | SDC (P): partially committed by Ericsson or others with scale back scope SO (C): committed by Ericsson and others with scale back scope ETSI Catalog Mgr (C): committed by CMCC OOF (P): partially committed by Intel SOL003 Adapter (C): committed by Ericsson or Nokia with scale back scope SOL005 Adapter (C): committed by Verizon with scale back scope SOL002 Adapter (C): committed by Samsung with scale back scope | SDC: who is doing what is under discussion between Ericsson and others. We have a scale-back workaround solution. SO: who is doing what is under discussion between Ericsson and others OOF: if OOF enhancement is not available for Frankfurt, a workaround would be applied (not critical for ETSI Alignment) | Andrew Fenner | Ericsson Verizon CMCC Samsung Nokia Intel | ||||||
Architecture - Modelling Alignment | Stephen Terrill | TSC: Remove from the Frankfurt tracking. Ongoing discussions | L | SDC Modelling | ||||||||||
Vertical Industry Oriented On-demand 5G Slice Service (this is merged with Network Slicing use case, and has become E2E Network Slicing) | LIN MENG | TSC: This requirement is now merged with Network Slicing. No more individual tracking | Modeling, U-UI, SO, DCAE | NA | China Mobile, Tencent, Huawei | Merged with E2E Network Slicing use case | ||||||||
E2E Network Slicing There are two parts:
The following is not approved:
| RANK #3 TSC:
This should limit the impacts to SO and External API for Frankfurt Please re-adjust the RED Cells accordingly. thanks <Swami> Updated Red cell entries on 4th Nov, 2019 | E2E Network Slicing Use Case in R6 Frankfurt | SDC | XL | SDC - C SO - C OOF - C UUI - C DCAE - C POLICY - TO (Stretch goals: EXT-API, AAI, Runtime DB, SDN-C - though implementation will proceed, code may not become official part of Frankfurt) AAI - C EXT-API - C SDN-C - C Runtime DB - C | (Commitments per component indicated in brackets) SDC, Modeling - C (Amdocs) SO - C (Wipro, China Mobile, Huawei) OOF - C (Wipro, China Mobile, Huawei) UUI - C (China Mobile, Huawei) DCAE - C (China Mobile, Huawei) POLICY- C (Wipro) Stretch goals commitment: AAI - C (Amdocs, Huawei) EXT-API -N SDN-C - C (Wipro) Runtime DB - N (Stretch Goal) | Runtime DB, SDN-C, EXT-API and AAI are stretch goals. We will discuss with resp. PTLs on possible options, anyhow they are not blocking scope of this use case for Frankfurt. | Wipro, AT&T, Amdocs, China Mobile, Huawei, Tencent, ZTE | DCAE: Review pending; cannot be committed for Frankfurt as of 10/23 For EXT-API and Runtime DB, to check with the respective PTLs for possible resource commitments, accordingly will take a final call (not blocking for Frankfurt though) | |||||
Remove Python2 dependencies | David McBride | RANK #1 | M | ALL projects using Python | ||||||||||
Multicloud K8s Support (Continuation from R4) | RANK #2 | K8S based Cloud region support (Continue from R4) | Multi-Cloud : C | Code Multi-Cloud : Intel Testing of SO, Multicloud, SDC: Intel | vFirewall: EdgeXFoundry Akraino ICN Distributed Analytics | Intel Aarna Tech Mahindra | ||||||||
K8s CDS Support | RANK #3 | S-M | MULTICLOUD: C CDS: C Integration: C SO: TO SDC: TO | CDS commited by Orange and Samsung MULTICLOUD commited by Samsung, Orange and Intel Integration commited by Samsung, Orange and Intel | Orange Samsung Intel | |||||||||
K8s HPA Support | RANK #3 | S | MULTICLOUD: C OOF:TO Policy:TO AAI/ESR:TO SO: TO SDC: TO | Intel commits to coding in Multicloud and testing in OOF, Policy, AAI, SO, SDC | Marcus Williams | Intel | ||||||||
K8s Security and traffic controller | RANK #3 | Multicloud K8s | S - M | MULTICLOUD: C | Intel commits to coding/testing in Multicloud | Intel | ||||||||
VSP Compliance and Validation Check within SDC - Phase 2 | RANK #2 | VSP Compliance and Validation Check within SDC | SDC: C | ([Prabhu]: SDC PTL reviewed the design and Vodafone already committed the code in SDC and code review is in progress) | Prabhu Balan | Vodafone | ||||||||
OVP Testing and Certification Support Within SDC | RANK #3 | OVP Testing and Certification Support Within SDC (Frankfurt) | SDC - C VTP - C | SDC-iconectiv VTP-iconectiv | Vodafone iconectiv | |||||||||
SECCOM Code coverage | RANK #3 | All projects | ||||||||||||
SECCOM Containers configured per secure recommendation | RANK #3 | All projects using containers | ||||||||||||
SECCOM Java 11 and 13 migration from v8 | RANK #3 | All projects using java | ||||||||||||
SECCOM CII badging – meet targeted Silver and Gold requirements | RANK #3 | All projects | ||||||||||||
SECCOM Complete the OJSI backlog | RANK #3 | All relevant projects having an entry in OJSI | ||||||||||||
SECCOM HTTPS communication vs. HTTP | RANK #1 | All relevant projects still using http communication instead of https | ||||||||||||
SECCOM Password removal from OOM HELM charts | RANK #1 | All relevant projects | ||||||||||||
SECCOM Communication Matrix | RANK #3 | All relevant projects | ||||||||||||
SECCOM Containers and Kubernetes secure configuration recommendation | RANK #3 | All projects | ||||||||||||
SECCOM Coverity integration by end of Frankfurt | RANK #3 | All projects using containers | ||||||||||||
SECCOM Ingress controller | RANK #3 | All projects | ||||||||||||
SECCOM ISTIO POC – limited ONAP deployment scope | RANK #3 | All projects | ||||||||||||
SECCOM Secure communication for 5G – AAF contribution – CMPv2 protocol trial usage | Hampus Tjäder | RANK #3 | AAF + TBC | |||||||||||
SECCOM Perform Software Composition Analysis - Vulnerability tables | RANK #1 | All projects | ||||||||||||
Document current ugrade component strategy | David McBride | RANK #1 |
T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team
- XS - <4 Man/Weeks;
- S - ~6 Man/Weeks;
- M - ~8 Man/Weeks;
- L - ~12 Man/Weeks;
- XL - > 12 Man/Weeks.
POC / Experimentation
Type | Requirement | Owner | Link(s) to HLD/LLD if any | Dependency (from/to) another project(s) | T-Shirt Size (XS, S, M, L, XL) | Project's Impact: Test Only (TO), Code (C) | Company Engagement | Notes | M4 Status |
---|---|---|---|---|---|---|---|---|---|
POC | Acumos - DCAE Integration | M | DCAE - C | AT&T Orange (Integration/UC support) | Met withEric Debeau/Orange team on 10/25 and they commited to support. |
T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team
- XS - <4 Man/Weeks;
- S - ~6 Man/Weeks;
- M - ~8 Man/Weeks;
- L - ~12 Man/Weeks;
- XL - > 12 Man/Weeks.