Release Schedule (Approved: TBD)
![](/download/attachments/93004814/ONAP%20Istanbul.png?version=3&modificationDate=1615427407000&api=v2)
Change Log
Date | Event or Update | Milestones Affected |
---|
Mar 18 | Proposal presentation to TSC. Requested approval of just the kickoff date of April 1. Other milestones to be discussed at a later date. TSC approved kickoff date ONLY. | M0 |
Mar 11 | Proposal presentation to TSC. TSC expressed concerns about the second half of the release occurring during the summer, which could conflict with summer holidays. Proposal not approved. | ALL |
Mar 10 | Second draft | - Added a new milestone before M3
- Previous "M3" becomes M4
- Added event in June
- Moved Honolulu sign off to April 8
|
Mar 4 | Initial draft posted | N/A |