Release Schedule 

Approved by the TSC on May 6, 2021


Change Log

DateEvent or UpdateMilestones Affected
Jun 23M2 approved by TSC, with exceptions, by email vote.M2
May 20M1 approved by TSC, with exceptions.  Details here.M1
May 10Added ONESummit dates to the schedule (r4) for reference.  (No changes to Istanbul release milestones from r3)None
May 6Approved by the TSC (r3)ALL
May 4

New proposal (r3) in response to feedback at May 3 PTL meeting

  • Collapsed 3 RCs into a single RC
  • Added more time from M4 to RC
  • Added an additional week between RC and sign off
  • Corrected dates for China National Day holiday. Should be 10/1 -8, instead of 9/27 - 10/1.
RC0, RC1, RC2
Apr 28New proposal (r2) in response to feedback from original proposal.M1 - Sign Off
Mar 18Proposal presentation to TSC.  Requested approval of just the kickoff date of April 1.  Other milestones to be discussed at a later date.  TSC approved kickoff date ONLY.M0
Mar 11Proposal presentation to TSC. TSC expressed concerns about the second half of the release occurring during the summer, which could conflict with summer holidays.  Proposal not approved.ALL
Mar 10Second draft
  • Added a new milestone  before M3
  • Previous "M3" becomes M4
  • Added event in June
  • Moved Honolulu sign off to April 8
Mar 4Initial draft postedN/A