The following items are expected to be completed for the project to Pass the M3 API Freeze Milestone.

M3 Release Architecture Milestone overview is available in wiki.


Practice AreaCheckpointYes/NoEvidencesHow to?
Architecture


Has the Project team reviewed the APIs with the Architecture Committee (ARC)?N/AVNFRQTS does not create APIs

Architecture walkthrough to understand how each project contributes on Release Use Case. ARC to organize the walkthrough.

Is there a plan to address the findings the API review?N/AVNFRQTS does not create APIsThe plan could be as simple as a Jira issue to track the implementation of findings or a documented plan within the wiki.
Does the team clearly understand that no changes in the API definition is allowed without formal TSC review and approval?N/AVNFRQTS does not create APIsIn the case some changes are necessary, bring the request to the TSC for review and approval.

Is there any changes in the scope, functionalities, deliverable, dependency, resources, API, repositories since M1 milestone?

YES

VNFRQTS <> Documentation Project Workflow

VNFRQTS <> Integration Project Workflow

VNFRQTS <> VNF Validation Project Workflow

VNFRQTS <> VNF SDK Project Workflow

Focus on creating VNF Requirements as prototype RFP text for release 1

other deliverables delayed to future releases

Release ManagementAre committed Sprint Backlog Stories been marked as "Done" in Jira board?YESLink to Project backlog
Are all tasks associated with Sprint Backlog Stories been marked as "Done" in Jira?YES Link to Project backlog
Have all findings from previous milestones been addressed?N/AProvide link to JIRA findingsNo blockers from previous milestonee
DevelopmentHas the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar)N/AVNFRQTS does not generate codeGuidance on Code Coverage and Static Code Analysis

Tools: Sonar

Goal: 30-50% for Incubation project

Is there any pending commit request older than 36 Business hours in Gerrit?YESproblem with VERIFY job in Jenkins
Are all the Jenkins jobs successfully passed ( Merge-Jobs)?NOsee aboveProvide link to evidence
Are all binaries available in Nexus?N/Aseed code loaded with errorsProvide link to evidence
Integration and Testing

Have 50 % of System Integration Testing Use Cases been implemented successfully in Jenkins?

N/AVNFRQTS does not generate code Provide link to evidence
Have you reviewed all the Test Case with Integration Team?N/A

VNFRQTS does not generate code

VNFRQTS <> Integration Project Workflow

Schedule a meeting with Integration Team to review the deliverable.
Has the project code successfully passed the Daily Build process?NOproblem with VERIFY job in JenkinsGoal is to ensure the latest project commit has not broken the Integration Daily Build 