Agenda

  • Status and Stucks
  • Technical Discussion
  • Making the PTL Happy



Notes

  • Status and Stucks
    • Current POMBA Casablanca Stories (Logging Project) -

    • Current Code Inspections

    • POMBA hourly healthcheck (CD deployment) - http://kibana.onap.info:5601/app/kibana#/dashboard/AWAtvpS63NTXK5mX2kuS
    • General Status
      • Casablanca
        • Audit initiation bug lodged    LOG-793 - Getting issue details... STATUS
      • Dublin
        • SDNC Context Builder w/ Generic Resource API testing to be completed today (honest!)       LOG-520 - Getting issue details... STATUS   |   LOG-462 - Getting issue details... STATUS  
          • We hit a snag in closing the second story off last week with no example SDNC response data available
          • We tried to chase that down but will instead simply mock up a reasonable guess and use that going forward (until we somehow acquire real information on the API response structure)
          • Spec file updates are pretty simple so we can accommodate changes easily if bugs are raised for SDNC interoperability issues
        • Still waiting on OOM branch for SDNC Context Builder deployment. (~November/December)      LOG-426 - Getting issue details... STATUS
          • Story is deferred indefinitely; will be picked up whenever we can merge
          • Additional OOM-reliant work (e.g. validation rules) should be (and is being) deferred in schedule
        • SDNC Context Builder API Mapping + VNF API work merged; paperwork to complete before closure      LOG-421 - Getting issue details... STATUS
        • Updated Common Model development completed and code submitted for review      LOG-780 - Getting issue details... STATUS
    • Engagement with Integration Team
      • Have to check with Chesla on her interactions with the Integration team
      • It looks like they are using POMBA judging by the bug!
  • Technical Discussion
    • Chesla should provide an update on the TOSCA task force plan next week if there's anything new
  • Making the PTL Happy