The page is intended to summarize all the requirements for Frankfurt Release.

These requirements will be prioritized by the TSC  to realistically fit within the Frankfurt Release Timeline.

The Release Scope should be finalized during the M1 Release Planning milestone at the xxx.

TSC Prioritization (Ranking)

  • RANK #0  – Special GO - fully covered by involved companies
  • RANK #1  – GO “Must Have”
  • RANK #2 - GO “Continuity of previous releases”
  • RANK #3 – GO if PTLs are OK since the impacted applications are less “stretched”
  • RANK #4 – NO GO – Mostly new requirements/features/projects

Use Cases 

Release 6 (Frankfurt) proposed use cases and functional requirements

M1 Scorecard:

  • Green: Use Case will be fully implemented and tested
  • Yellow: Use Case will be partially implemented. It is possible to identify capabilities for this use case that can be tested (phasing approach).
  • Red: Use Case can not be partially delivered, min. requirements can not be met in order to define a testing strategy.
Use CaseOwner(s)Projects or functional requirements impacted for DublinPriority

M1

Scorecard

TSC M1 ApprovalM3 ScorecardM3 TSC ApprovalM4 ScorecardTSC M4 ApprovalLink(s) to HLD/LLD if anyDependency (from/to) another project(s)

T-Shirt Size (star)

Project's Impact: Test Only (TO), Code (C)Committed (C)/ Partially Committed (P) or not (N) per impacted projectIf Partially or not Committed, what are gaps/ project (people/FTEs; HLD/LLD; etc)

Company

Engagement

Notes
Third Party Operational Domain Manager

Divyang.Patel@team.telstra.com

Atif.Husain@team.telstra.com

nishi.mathur@team.telstra.com

SDC






Third-party Operational Domain Manager
S

SDC (C)

SO (TO)

AAI (TO)

Changes being done in local setup.Will commit after review discussion with SDC PTLTelstraComplete company commitment for delivery of Frankfurt Scope for this use case


(star) T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team

  • XS - <4 Man/Weeks;
  • S - ~6 Man/Weeks;
  • M - ~8 Man/Weeks;
  • L - ~12 Man/Weeks;
  • XL - > 12 Man/Weeks.

Requirements

M1 Scorecard:

  • Green: The requirement will be fully implemented and tested
  • Yellow:  The requirement will be partially implemented. It is possible to identify capabilities for this functional requirement that can be tested (phasing approach).
  • Red: The requirement can not be partially delivered, min. requirements can not be met in order to define a testing strategy
RequirementOwnerProject ImpactedPriorityM1 ScorecardTSC M1 ApprovalM3 ScorecardM3 TSC ApprovalM4 ScorecardTSC M4 ApprovalLink(s) to HLD/LLD if anyDependency (from/to) another project(s)T-Shirt Size (XS, S, M, L, XL) (star)Project's Impact: Test Only (TO), Code (C)Committed (C)/Partially Committed (P) or not (N) per Impacted projectsIf Partially or not Committed, what are gaps/ project (people/FTEs; HLD/LLD; etc)Company EngagementNotes



















(star) T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team

  • XS - <4 Man/Weeks;
  • S - ~6 Man/Weeks;
  • M - ~8 Man/Weeks;
  • L - ~12 Man/Weeks;
  • XL - > 12 Man/Weeks.

Dublin POC / Experimentation

POC Definition - (In Progress)

TypeRequirementOwnerProject ImpactedLink(s) to HLD/LLD if anyDependency (from/to) another project(s)T-Shirt Size (XS, S, M, L, XL) (star)Project's Impact: Test Only (TO), Code (C)Company EngagementNotesM4 Status











(star)T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team

  • XS - <4 Man/Weeks;
  • S - ~6 Man/Weeks;
  • M - ~8 Man/Weeks;
  • L - ~12 Man/Weeks;
  • XL - > 12 Man/Weeks.