The page is intended to summarize all the requirements for Frankfurt Release.
These requirements will be prioritized by the TSC to realistically fit within the Frankfurt Release Timeline.
The Release Scope should be finalized during the M1 Release Planning milestone at the xxx.
TSC Prioritization (Ranking)
- RANK #0 – Special GO - fully covered by involved companies
- RANK #1 – GO “Must Have”
- RANK #2 - GO “Continuity of previous releases”
- RANK #3 – GO if PTLs are OK since the impacted applications are less “stretched”
- RANK #4 – NO GO – Mostly new requirements/features/projects
Use Cases
Release 6 (Frankfurt) proposed use cases and functional requirements
M1 Scorecard:
- Green: Use Case will be fully implemented and tested
- Yellow: Use Case will be partially implemented. It is possible to identify capabilities for this use case that can be tested (phasing approach).
- Red: Use Case can not be partially delivered, min. requirements can not be met in order to define a testing strategy.
Use Case | Owner(s) | Projects or functional requirements impacted for this release | Priority | M1 Scorecard | TSC M1 Approval | M3 Scorecard | M3 TSC Approval | M4 Scorecard | TSC M4 Approval | Link(s) to HLD/LLD if any | Dependency (from/to) another project(s) | T-Shirt Size | Project's Impact: Test Only (TO), Code (C) | Committed (C)/ Partially Committed (P) or not (N) per impacted project | If Partially or not Committed, what are gaps/ project (people/FTEs; HLD/LLD; etc) | Company Engagement | Notes |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Third Party Operational Domain Manager | SDC | Third-party Operational Domain Manager | S | SDC (C) SO (TO) AAI (TO) | Changes being done in local setup. | Will commit after review discussion with SDC PTL | Telstra | Complete company commitment for delivery of Frankfurt Scope for this use case |
T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team
- XS - <4 Man/Weeks;
- S - ~6 Man/Weeks;
- M - ~8 Man/Weeks;
- L - ~12 Man/Weeks;
- XL - > 12 Man/Weeks.
Requirements
M1 Scorecard:
- Green: The requirement will be fully implemented and tested
- Yellow: The requirement will be partially implemented. It is possible to identify capabilities for this functional requirement that can be tested (phasing approach).
- Red: The requirement can not be partially delivered, min. requirements can not be met in order to define a testing strategy
Requirement | Owner | Project Impacted | Priority | M1 Scorecard | TSC M1 Approval | M3 Scorecard | M3 TSC Approval | M4 Scorecard | TSC M4 Approval | Link(s) to HLD/LLD if any | Dependency (from/to) another project(s) | T-Shirt Size (XS, S, M, L, XL) | Project's Impact: Test Only (TO), Code (C) | Committed (C)/Partially Committed (P) or not (N) per Impacted projects | If Partially or not Committed, what are gaps/ project (people/FTEs; HLD/LLD; etc) | Company Engagement | Notes |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Self Serve Control Loops | SDC DCAE POLICY | Self Serve Control Loops | CLAMP | XL | SDC - C DCAE - C POLICY - C | AT&T | |||||||||||
All Control Loop Policy Models should be TOSCA Compliant Operational, Guard Policies | CLAMP POLICY | TOSCA Compliant Policy Types | SDC | M | CLAMP - C POLICY - TO | ||||||||||||
Policy Update Notifications | DCAE POLICY | Policy Update Notifications | S | DCAE - C POLICY - C | |||||||||||||
CLAMP Deployment of Policies to PDP Groups | CLAMP POLICY | CLAMP Deployment of Policies to PDP Groups | M | CLAMP - C POLICY- C | |||||||||||||
T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team
- XS - <4 Man/Weeks;
- S - ~6 Man/Weeks;
- M - ~8 Man/Weeks;
- L - ~12 Man/Weeks;
- XL - > 12 Man/Weeks.
POC / Experimentation
POC Definition - (In Progress)
Type | Requirement | Owner | Project Impacted | Link(s) to HLD/LLD if any | Dependency (from/to) another project(s) | T-Shirt Size (XS, S, M, L, XL) | Project's Impact: Test Only (TO), Code (C) | Company Engagement | Notes | M4 Status |
---|---|---|---|---|---|---|---|---|---|---|
T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team
- XS - <4 Man/Weeks;
- S - ~6 Man/Weeks;
- M - ~8 Man/Weeks;
- L - ~12 Man/Weeks;
- XL - > 12 Man/Weeks.