R5 El Alto Release

EUAG has decided that R5 El Alto will be a "maintenance/technical debt" release.

https://wiki.lfnetworking.org/display/LN/EUAG+2019-04-09+meeting+minutes

The El Alto release will be shortened (3-month cycle) and focused on internal (tech) debt and defect backlogs. And every 5th ONAP release will be a maintenance release.

PTLs had taken short cuts to meet deadlines, working but want to make the platform more robust. PTL driven code fixes and code hardening.

S/W Enhancements (e.g. GUI enhancements) would be pushed to R6. Feature enhancements would be pushed to R6

R5 will be focused on Refactoring, JIRA backlog reduction, vulnerability issues, Test Coverage, Test Automation (CI/CD pipeline), Deployment procedure, Documentation.

R5 - Security Scans, scan code reports sent to PTL for major things to fix. Vulnerabilities have been built. Vulnerability management process. Security gates checklist.

SUMMARY: There will be no new Software development for new functionality in R5; but there will be Jira tickets worked on (PCI/SON); and modeling work for 5G RAN.


TITLEDESCRIPTIONCATEGORYWIKI
PCI/SON ENHANCEMENTSOptimization and PCI (SON) development. Dublin Carry-over items will be worked in R5. There are two Jira tickets open for SDN-C.

5G Operational

Optimization

OOF (SON) in R5 El Alto, OOF (SON) in R6 Frankfurt
5G SERVICE MODELINGDefining and Modeling a 5G Service for Design Time and use by other 5G Use Cases. Defining the Platform Data & Information model and PNF Resource for a 5G RAN.

5G FCAPS

Discovery

5G Operational


R6 5G-SPECIFIC USE CASES (Frankfurt Release)


Release 6 will be a "normal" release but with an extended M1 from June to Aug 29.


TITLEDESCRIPTIONCATEGORYWIKI
5G SERVICE MODELING & CREATION
Defining and Modeling a 5G Service for Design Time and use by other 5G Use Cases. Defining the Platform Data & Information model and PNF Resource for a 5G RAN.

5G FCAPS

Discovery

5G Operational

5G RAN SERVICE MODELING & DEFINITION in R6 Frankfurt
OOF SON ENHANCEMENTS

Optimization and OOF SON development. Dublin Carry-over items.

OOF (SON). SDN-R Network. Policy Control Loop Coordination.

5G Operational

Optimization

OOF (SON) in R5 El Alto, OOF (SON) in R6 Frankfurt
5G CONFIGURATION (ConfigDB)
Run-time configuration data persistency (configDB/MariaDB).5G CM (FCAPS)5G CONFIGURATION (ConfigDB)
NETWORK TOPOLOGY MANAGEMENT5G Network Topology Management. 5G Network representation and management.5G OperationNETWORK TOPOLOGY MANAGEMENT
PERFORMANCE MEASUREMENTSPerformance Measurements Use Cases (including Bulk PM, RT PM and PM Dictionary)

Data Collection

5G FCAPS

PERFORMANCE MEASUREMENTS USE CASES: Bulk, RT, Dictionary

      BULK PM

     (PERFORMANCE

     MEASUREMENTS)

Performance Measurements 5G RAN Bulk Upload. Improvements will be made and carry - overs from R4 Dublin.

Partially 5G Specific, and Partially "Generic". Can be evolved for use with generic PNFs (beyond 5G)

Data Collection

5G FCAPS

5G BULK PM Management in R6 Frankfurt

     5G PM DICTIONARY

     (PERFORMANCE

     MEASUREMENTS)

Support for handling & support for PM Dictionary & PM Schema (from standards).

Eventually other PNFs will support faults, but right now 3GPP specific formatting is used in the PM artifact. Can be evolved for use with generic PNFs (beyond 5G)

PNF Support

Data Collection

5G FCAPS

FM META DATA & PM DICTIONARY in R6 Frankfurt

5G FM META DATA

(FAULT MANAGEMENT)


Support for handling FM Meta Data.

Eventually other PNFs will support faults but right now 3GPP specific formatting is used in the FM. Can be evolved for use with generic PNFs (beyond 5G)

PNF Support

Data Collection

5G FCAPS

FM META DATA & PM DICTIONARY in R6 Frankfurt

NETWORK SLICING

END-TO-END NETWORK SLICING MANAGEMENT

Advanced 5G functionality, for Network Slicing development and early steps in long-lead development.

(CMCC) LIN MENG Lingli Deng Advanced 5G functionality, Management of Network Slicing development 

5G Operational

Optimization

NETWORK SLICING in R6 Frankfurt
LICENSING MANAGEMENTLicensing Management with ONAP and xNFs. The topics for how to create licenses, manage licenses and handling terms between a vendor and service providers. This will evolve beyond 5G but may start as a 5G U/C.
LICENSING MANAGEMENT
RAN STANDARDS HARMONIZATION WITH ONAP

There are many standards ORAN and 3GPP harmonization with ONAP.

O1, A1 definitions. Encoding protocol to use.

ORAN repository (proprietary to ORAN)


MOBILITY STANDARDS HARMONIZATION WITH ONAP

ORAN-ONAP Alignment Use Case

5G NRM (Network Resource Model) CONFIGURATIONConfiguration Management (CM Notify/ Update) using RESTful (HTTPS) Interface.

5G CM

(FCAPS)

5G Network Resource Model (NRM) Configuration in R6 Frankfurt


5G U/C COMMITMENTS BY PROJECT:

The following table indicates commitment by project. The impacts have been accepted and are supported by the PTL of each ONAP Platform component and corresponding Jira Tickets are in place. There are three states:

N/A = A "N/A" means that there is no interaction, no dependency, and no work for that Use Case for that component.

? = A "?" means that there is not final commitment from the PTL for that project, and no Jira ticket exists yet.

YES = This means that (1) PTL INFORMED & COMMITTED - has agreed to support the changes needed for that Use Case, (2) DEVELOPMENT SUPPORT - there is development (company) support (3) JIRA TICKETS - and a Jira ticket exists. Please see the corresponding WIKI page for that Use Case to find out more details on impact, PTL support and Jira Ticket(s).


Use CaseSDCVIDPortalSOAAI ESRCTRLRDCAEOOFPolicyCLAMPDMaaPAAFVNF SDKREQTSModel S/COOMVIMPombaCIACLIConsul
Bulk PM(star)N/AN/AN/AN/AN/AYESN/AN/AN/AYESN/AN/AYESN/AN/AN/AN/AN/AN/AN/A
OnboardingYESN/AN/AN/AN/AN/AN/AN/AN/AN/AN/AN/AYESYESN/AN/AN/AN/AN/AN/AN/A
NetConfN/AN/AN/AYESN/AYESN/AN/AN/AN/AN/AN/A1N/AYESN/AN/AN/AN/AN/AN/AN/A
FM PM DictYESN/AN/AN/AN/AN/AN/AN/AN/AN/AN/AN/AN/AYESN/AN/AN/AN/AN/AN/AN/A
OOF PCIN/AN/AN/AN/AN/AYESYESYESYESN/AN/AN/AN/AYESN/AN/AN/AN/AN/AN/AN/A
PNF PnPN/AYESYESYESYESYESYESN/AN/AN/AN/AYESN/AYESN/AN/AN/AN/AN/AN/AN/A
S/W Upg
N/AN/AN/AN/AN/AYESN/AN/AN/AN/AN/AN/AN/AN/AN/AN/AN/AN/AN/AN/AN/A
SlicingYESN/AN/AN/AN/AN/AN/AN/AN/AN/AN/AN/AN/AN/AYESN/AN/AN/AN/AN/AN/A
ORAN Harmonize




















Licensing Managmt




















5G NRM




















Config DB Topology




















5G Service Modeling





















REQ = VNF Requirements Project. The VNF-RQTS project applies to both VNFs and PNFs. A "YES" here means that there are new requirements for the vendors.

Model S/C = Modelling Subcommittee. This U/C impacts the ONAP Platform Information and/or Data Model.

Ctrlr = This includes all of the controllers in ONAP including SDN-C, SDN-R, APP-C and VF-C

(star) Stretch Goal (N/A) but if extra resources are available some changes may be made.

Note (1): x

Note (2): x 


5G USE CASE ASSESSMENT:

The following table was to assess whether use cases are related to 5G (are 5G specific) or whether they are general PNF use cases.

The General PNF use cases have been moved to their own wiki: General PNF Support Use Cases

TITLERequirement / Platform Enhancement vs E2E Use Case
5G Specific
5G SERVICE MODELING

Requirement / Platform Enhancement

5G Specific
PNF PRE-ONBOARDING & ONBOARDING Use Case

Requirement / Platform Enhancement


General
CONFIGURATION WITH NETCONFRequirement / Platform Enhancement

General

BULK PM

Requirement / Platform Enhancement

* Could be evolved eventually to be PNF & domain generic.

5G Specific *
5G FM META DATA & 5G PM DICTIONARY

Requirement / Platform Enhancement

* Could be evolved eventually to be PNF & domain generic.

5G Specific *

PNF PLUG AND PLAY
E2E Use Case

General

PNF S/W UPGRADE

Requirement / Platform Enhancement 

General
OOF SON ENHANCEMENTS

Requirement / Platform Enhancement

5G Specific
NETWORK SLICINGE2E Use Case

5G Specific

MOBILE SERVICE CHAINING

Requirement / Platform Enhancement 

General

USE CASE REALIZATION CALLS:

Links to the Use Case Realization Calls:

Use Case Realization Call: April 10, 2019 - Controller LCM API Evolution

Use Case Realization Call: April 17, 2019

Use Case Realization Call: April 24, 2019 - Arch POB/OB Flow

Use Case Realization Call: May 1, 2019 - A&AI Graph Graph Visualizer

Use Case Realization Call: May 8, 2019 - A&AI Model Browser Demo

Use Case Realization Call: May 15, 2019 - A&AI Sparky (Run-time browser) Demo

Use Case Realization Call: May 22, 2019Edge Automation Overview

Use Case Realization Call: May 29, 2019 - Model, U/C, Arch WoW Discussion

Use Case Realization Call: June 5, 2019 - U/C discussion

Use Case Realization Call: June 19, 2019 - IoT Creation

Use Case Realization Call: July 10, 2019 - PNF S/W Upgrade

Use Case Realization Call: July 17, 2019 - U/C discussions

Use Case Realization Call: July 24, 2019 - OOF PCI Demo (Shankar)

Use Case Realization Call: July 31, 2019 - U/C discussions

Use Case Realization Call: August 7, 2019 - 5G NRM (YaoGuang Wang)

Use Case Realization Call: August 14, 2019 - ORAN/3GPP & ONAP Alignment (Marge, Vimal)

5G Use Case Meeting notes for August 8, 2019 - 5G U/C Network Slicing R6 Proposal (Shankar/Swami)

5G Use Case Meeting notes for August 15, 2019 - 5G U/C Meeting Aug 15, 2019

Use Case Realization Call: August 21, 2019 - Modeling S/C Meeting

5G Use Case Meeting notes for August 22, 2019 - 5G U/C Meeting Aug 22, 2019

SUPPORTING DOCUMENTS:

DocumentFile
R5 El Alto Proposals

Use Case TemplateUse Case Tracking Template
Use Case Analysis (from U/C realization Calls)

MEETING RECORDINGS

Meeting RecordingsFILE
May 30 2019 5G U/C Meeting










  • No labels