Guilin city center

Release Calendar (approved June 24)

Change Log

DateEvent or UpdateMilestones Affected
June 24Initial version of schedule approved by TSC by mail vote.

N/A

July 9M1 milestone requirements not met.  TSC agrees to slip M1 to July 13.M1
July 13M1 milestone requirements not met.  M1 slips to July 16.M1
July 16Project milestone status 100%, but requirements still not resolved. M1 slips to July 23.M1
July 23TSC approved M1 (2 week slip from original plan)M1
August 6M2/3 milestone reqirements not met.  M2/3 slips to August 11M2/3
August 13TSC approved M2/3 with conditionsM2/3
September 10TSC agrees that M4 milestone requirements not met.  Agrees to review again on Sept 17.M4
September 17TSC approves M4 with exceptionsM4