Release Schedule (Approved Dec 10, 2020)

Activity Log

DateEvent or UpdateMilestones Affected
Mar 1TSC approves M3 with exceptions.  Exceptions to be closed by RC0.
Feb 25TSC determined that there is insufficient information to make decision, so M3 pushed out 4 days to March 1M3
Feb 1Uploaded ONAP Honolulu r1 to show changes to M1 and M2 datesM1, M2
Jan 25M2 approved with exceptionsM2
Jan 21Requirements not met. M2 slipped to Jan 25M2
Jan 14M1 approved with exceptionsM1
Jan 11Requirements not met.  M1 slipped to Jan 14M1
Dec 10TSC approved scheduleALL
Dec 10M1 moved out 4 days to Jan 11M1
Nov 20Second draft posted
Nov 11First draft posted