No.ItemWhoNotes
1

Integration testing status update

 2

EXT API Bug Fix update - EXTAPI-602 - multiple instantiations of same service fails IN PROGRESS

  • Discussed in TSC meeting on 4/7. Solution:
    • Short term solution: Ahila to create IT ticket for re-opening nbi repo and re-activating Jenkins job, and push the fix to repo. Committers to merge the fix.
      • Ahila P Fix pushed to repo, Jenkins job created. to be reviewed but no review yet. to check with TSC
    • Possible long term solution: OOF to take over extapi/nbi repo - N.K. Shankaranarayanan to check with OOF
  • PTL meeting on 4/11 also had a follow-up discussion, to investigate exiapi/nbi repo dependency
3

Update on Core Slicing issues:

1)  https://jira.onap.org/browse/SO-3810 2)  https://jira.onap.org/browse/SO-3835
3)  https://jira.onap.org/browse/SO-3838

  • SO-3810, SO-3838 in progress
  • CBA package from I release not working properly, getting help from Sashmita.
4

Discussion on joint work proposal (IBN, CCVPN and NS)

  • Introduction of ML prediction MS
  • Introduction of workflow and API of intent interaction
  • Introduction of Intent-driven Closed-loop Autonomous Networks in R11
  • Intent-driven E2E Network Slicing proposal with key tasks:
    • Integration of ML prediction MS with DCAE (IBN and network slicing teams)
    • Enhancement to intent creation and workflow to support E2E Network Slicing based on UUI, AAI and DCAE (IBN team)
    • Enhancement to the closed-loop and the ML prediction MS for 5G KPI monitoring to support IBN (NS team)

Recording