Release Schedule

Approved: TBD

Activity Log

DateRevEvent or UpdateMilestones Affected
10/25/21r1

Added continuous delivery view to the schedule, per the working group feedback and PTL meeting review.

(Magnus Buhrgard )

All
09/30/21
TSC approved schedule

All

Note:  milestone dates are approved, but there is interest in the community to change the appearance of the schedule to better communicate the agile aspect of the release process.  Magnus and Ciaran have launched a working group to develop a proposal for the TSC.  Therefore, although the dates are approved, the schedule remains "draft".

09/15/21
First draft postedAll